SECTION 01 45 01
CONTRACTOR’S QUALITY CONTROL
PART 1 GENERAL
1.1 QUALITY CONTROL
1.1.1 The Contractor is responsible for an effective quality control system in compliance with contract clause 52.246-12, “Inspection of Construction”. The quality control system shall consist of plans, procedures, and organization necessary to manage all task orders to produce end products that comply with the contract requirements. The system shall cover all construction operations, both on site and off site, and shall be keyed to the proposed construction sequence.
1.1.2 The Contractor shall establish, maintain, and implement a complete Quality Control Plan to ensure the requirements of the contract are provided as specified as part of the original solicitation. This plan shall then be continually maintained throughout the life of the Contract by all successful bidders and resubmitted whenever changes are made or upon request.
1.1.2.1 This plan shall be submitted in a three-ring binder and shall contain all requirements.
The binder shall have a cover sheet that includes the solicitation number, subsequent contract number, Contractor name, address, and business phone number. Quality Control Officer’s name, address, and business phone number. All listed requirements shall be included. The contents of the binder shall be fully tabulated and a table of contents will be used.
1.1.3 Notification of Noncompliance. The Contracting Officer (CO) will notify the Contractor of any detected noncompliance with the requirements of this section. The Contractor shall take immediate corrective action after receipt of such notice. If the Contractor fails or refuses to comply promptly, the CO may issue an order stopping all or part of the work until satisfactory corrective action has been taken. No part of the time lost due to such stop orders shall be made the subject of claim for extension of time or for excess costs or damages by the Contractor.
1.2 QUALITY CONTROL PLAN CONTENTS
1.2.1 The Quality Control Plan shall identify:
1.2.1.1 Personnel, procedures, instructions, tests, forms, and records to be used.
1.2.1.2 The person within the Contractor’s organization identified as the Quality Control Officer.
1.2.1.3 The authority and responsibilities of all the quality control personnel.
1.2.1.4 Procedures for reviewing and approving all shop drawings, product data samples or other submittals before submission to the Contracting Officer. Include procedures for obtaining field measurements.
QSEU 12-2002 01 45 01-1
1.2.1.5 Method of documenting quality control operation, inspection, and testing of both prime and subcontract work including samples of proposed forms.
1.2.1.6 Method of documenting and tracking deficiencies including responsibilities and procedures for correcting deficiencies.
1.3 COORDINATION MEETINGS
1.3.1 Initial Quality Meeting. After the pre-construction conference, before issuance of any task order under this contract the Contractor shall meet with the CO and CE Representative and discuss the contractor’s Quality Control Plan. During the meeting, a mutual understanding of the system details shall be developed, including the forms for recording quality control operations, control activities, testing, administration of the system for both on site and off site work, and the interrelationship of contractor's management and control with the government's quality assurance. Minutes of the meeting shall be prepared by the Government and signed by both the Contractor and the CO. The minutes shall become a part of the contract file. There may be occasions when subsequent conferences will be called by either party to reconfirm mutual understandings and/or address deficiencies in the quality control system or procedures that may require corrective action by the Contractor.
1.3.2 Interface with Government Inspectors. The Quality Control Officer may request meetings with the Government to discuss quality issues when they arise. The Government reserves the right to conduct quality meetings at its discretion.
1.4 QUALITY CONTROL DOCUMENTATION
1.4.1 The Contractor shall maintain current records (daily construction logs) providing documented evidence that required quality control activities and/or tests have been performed. These records shall be provided to the CO daily. These records shall include the work of subcontractors and suppliers and shall be on a form acceptable to the CO that includes, as a minimum, the following information:
1.4.1.1 Contractor/subcontractor and their area of responsibility.
1.4.1.2 Work performed each day, giving location, description, and by whom.
1.4.1.3 Visitors (including inspectors) on site each day.
1.4.1.4 Test and/or control activities performed with results and references to specifications/ drawings requirements. List deficiencies noted along with corrective action.
1.4.1.5 Job safety evaluations stating what was checked, results, and instructions or corrective actions.
1.4.1.6 Instructions given/received and conflicts in plans and/or specifications.
1.4.2 These records shall indicate a description of trades working on the project; the number of personnel working; weather conditions encountered; and any delays encountered. These records shall cover both conforming and deficient features and shall include a statement
QSEU 12-2002 01 45 01-2
that equipment and materials incorporated in the work and workmanship comply with the contract.
1.4.3 These records shall be available to government personnel upon request.
PART 2 PRODUCTS – Not Used
PART 3 EXECUTION – Not Used
END OF SECTION 01 45 01