Combined_QA's_Phase_III_28Feb2019.xlsx

XLSX spreadsheet 30 KB Posted

Attached to
Demolition of Facilities Phase 3 Federal contract opportunity
Solicitation number
FA481919Q7004
Issued by
Department of the Air Force Air Combat Command

About this file

Q&A's following the site visit held 12 and 13 Feb

View the file

Other files for this federal contract opportunity

Show all 24

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PPIF

Pre Proposal Inquiry FormSolicitation No: FA481919Q7004
Contracting Officer Name: Mrs. Melissa SandersDemolition of Facilities Phase 3, Tyndall AFB Florida
Contract Administrator Name: SrA James SearsQuote Due Date 07 March 2019

Email: 325CONS.Construction@us.af.mil

Question No.Reference (Sect/Para/Page)QuestionGovernment Response
1Pre-Site Visit InquiryIs there an incumbent contractor currently performing these services or if this is a new requirement. If there is an incumbent, could you please provide the contract number?This is a new requirement and as such there is no incumbent contractor.
2Pre-Site Visit InquiryCan the past performance be a combination of the prime contractor and a subcontractor? Or, does all past performance provided have to have been performed by the prime contractor?CONS - Yes
3Pre-Site Visit InquiryCan we have a specific list of the buildings and structures where the slab/foundations are to remain? The building list says “structure only” for some sites but during the walk thru, there were some question. One, specifically, was Bldg. 5025.See attached list
4Pre-Site Visit InquiryAt Bldg. 5025, there is a 4’ retaining wall along the concrete dock area and the building “straddles” this wall. Once the building is removed, and particularly if the slab is removed, pressure from the backfill and the gap this removal will create may cause failure of the retaining wall. How should this be addressed?Environmental - As much of the retaining wall as possible should be maintained. Retaining wall should be stabilized at ends to prevent failure. Erosion control should be completed in the opening created by removing the facility to prevent the earth from washing out into the bay. Silt fencing, erosion control socks, or any other form of erosion/sedimentation control devices can be utilized to stabilize and prevent bank erosion pre/post construction. All stormwater drains must be marked and covered.
5Pre-Site Visit InquiryIs there a list of equipment to be salvaged by the facility from Bldg. 421?No, majority of equipment will be removed ahead of time remaining equipment will be in unsafe areas. The contractor will safe the areas, remove identified equipment and stage in parking lot of building.
6Pre-Site Visit InquiryWe were unable to access many of the buildings to be demolished. Will some provisions be made for debris in the buildings since we couldn’t see inside to estimate loads?No, facilities should be estimated with admin/office furniture. If there are questions on specific facilities CE will try and collect photos of interiors. Need list of specific facilities.
7Pre-Site Visit InquiryStructure 631 is 4 steel columns wrapped in block. It spans a busy access point for the facility. What will be involved in closing this gate for a period to allow for the safe removal of the structure?Base Gate Closure will be coordinated through Base CE, Base Security (BDOC) and the contractor. Must be scheduled 14 days ahead of time. ALL equipment, safety requirements and personnel will need to be on sight the day before to ensure everything is in place. (if crane is used lift/safety plan is required to be submitted and approved 3 days ahead of time)
8Pre-Site Visit InquiryWhat is required for individual perimeter site protection while the demolition of each structure is progressing? Will “orange fence” be sufficient or, must we use temporary fence panels?Environmental - Orange constuction fencing installed correctly with signage clearly making the dangers will surfice. All environmental requirements for dust control, asbestos, and sedimentation and erosion control is also required, along with any additional best management practices.
9Pre-Site Visit InquiryThe PWS says that all sites are to be finished with grass. “Site restoration establishment of turf or sod”. Some of the sites are in the middle of a much larger concrete area. Are we to plant grass in areas surrounded by concrete or will a list be made available where gravel/dirt/stone will suffice?See attached list for clarification
10Site Visit InquiryWill a SWPPP be necessary for each site?Environmental - Yes, see attached SWPPP template(s).
11Site Visit InquiryWill the contractor be awarded bids for individual facility site cleanup or will the bid be awarded for all 47 facilities?This requirement will be awarded for all facilities.
12Site Visit InquiryCan I get the square yard measurement for each facility? I have the images from FedBizOpps.gov but I could use more details about each facilitySee building floor plans that are avalable, all other measurements need to be varified by the contractor.
13Site Visit InquiryWhat are the environmental code/rules/specifications for the facilities that are located near water.Enviromental - It is the responsibility of the contractor to verify what permits are required per Section 3.2.1. Contractor must consult with 325 CES it any permits are required and all applications must be reviewed and signed by the 325 CES Commander. If permits are deemed required by the 325 CES, the contractor will stop work and address environmental concerns.
14Site Visit InquiryOn Building #2699 - wooden pilings. Are they to be removed?Pilings to be left in place unless damaged. Area between and around pilings to be leveled with gravel to prevent ponding. Pilings may be used in future project.
15Site Visit InquiryOn Building #5025 - can we use a vinyl retaining wall or seawall to hold back the dirt from washing into the water?Environmental - As much of the retaining wall as possible should be maintained. Retaining wall should be stabilized at ends to prevent failure. Erosion control should be completed in the opening created by removing the facility to prevent the earth from washing out into the bay. Silt fencing, erosion control socks, or any other form of erosion/sedimentation control devices can be utilized to stabilize and prevent bank erosion pre/post construction. All stormwater drains must be marked and covered.
16Site Visit InquiryCan we get a list of the buildings that the slabs stay?See attached list for clarification
17Site Visit InquiryThe solicitation specifically addresses Florida Department of Environment Emergency Final Order OGC No. 18-1335. That order allows for start of work without submitting 10 day pre-demolition notification - The demolition requirements in the PWS (3.3.1.1) appear to contradict the Florida Department of Environment Emergency Final Order. Please clarify.Environmental - Plan normal requirements for all faciities, letter will expire prior to the start of all facilities so the normal 10 day notice would need to be completed for most of the buildings. The only thing the letter would do is exempt the 10 day notice. All other regulations and requirements still must be met.
18Site Visit InquiryThe specifications call for an existing conditions survey, where a pre-demolition hazardous materials survey may be performed (if physically possible) assuming that the buildings can be survey and asbestos or other hazardous materials can be identified and removed, how will the Contractor be compensated for abatement activities?Environmental - Contractor provides the estimate and plan. If the facility could be abated dumping fee would be greatly reduced.
19Site Visit InquiryIt appears that the intent of the of the PWS is to include concrete slab and foundation removal and site restoration for all buildings except:
B26 Garage door structures only, B83 Structure Only, B168 Structure Only - By structure only, do you mean down to top of grade slab? Does "Structure Only" include removal of any concrete pedestals, knee walls or equipment pads? Please verify.See attached for clarification (removed flush to concrete)
20Site Visit InquiryUnder General Description of Project, (2.2.1 of the PWS) item g. - The site restoration is very vague. Please provide a complete description of the requirements for Site Restoration.Environmental - The source of backfill shall be natural or virgin material (other than the operation of a borrow pit facility) and shall be in an area which has not previously been used for commercial or industrial activities. One soil sample will be collected from the borrow source and analyzed for the following parameters: Volatile Organic Compounds (VOCs) per Method 8260, Semi-volatile Organic Compounds (SVOCs) [Base/Neutrals (e.g., PAHs, Pesticides, PCBs) and Acid Extractables (e.g., Phenols)] per Methods 8270/8081/8082, RCRA metals by Method 6020, Petroleum Residual Organics (by FL-PRO), Analytical results will be compared to the FDEP residential Soil Cleanup Target Levels to determine acceptability of the proposed material as clean fill. Compact the backfill to a firmness approximately equal to that of the soil next to the trench in location outside the plane described by one (vertical) to two (horizontal) slope downward from the roadway shoulder point or the gutter line in accordance with Standard Plans, Index 120-001 or 120-002. Apply 125-9.2.1 when compacting side-drain pipe backfill under driveways serving a property that is not single residential lot. See attachment for additional information per locations.
21Site Visit InquiryUnder General Description of Project, (2.2.1 of the PWS) item 2.2.4 Hazardous Waste, The contractor is directed to collect and stage any Hazardous waste materials discovered as a result of the existing conditions survey. Is it the intent of the documents that the removal and staging of hazardous materials should be included in the individual pricing for each work item? Will Tyndall AFB provide containers/packaging for any discovered Hazardous Waste? How will the contractor be compensated for collection of Hazardous Waste? Packaging?, Transportation? Disposal?Environmental - Hazardous waste is identified as oils, paints, cleaning material, 55 gal drums, maintence racks that need to be removed from the facilities prior to demolition. The effort to move the items from the building to the parking lot should be included in the estimate. The government will dispose of or purpose the material at a later date.
22Site Visit InquiryIn the PWS, item 3.2.1 - Scrap Metal Recycling, the contractor is directed to utilize the base recycling program and to take the scrap metal generated from demolition activities to Emerald Coast Recycling/DBA Lewis Metals. If the contractor has another scrap metal recycler that he/she deals with can they take metals to that facility instead, or are the mandated to use this particular facility? Who gets the benefit from the revenue gained from the recycle of metals? This specification indicates that the Contractor will submit invoices to the Contracting Officer for reporting requirement for base recycling program. An invoice usually implies payment; Will the Contractor be paid for transportation charges to the base recycling facility? or is the term "invoice" meant to include weight tickets to track the total waste and waste to be recycled?As stated in the PWS, the contractor will use Emerald Coast Recycling/DBA Lewis Metals because of the exist base recycle contract that is inplace. The money from the recycled metal will go back to the government. The contractor should estimate to transport the recycle metal from base to Emerald Coast Recycling/DBA Lewis Metals. The invoice is to show delivery of the metal, no money will go to the contractor from Emerald Coast Recycling/DBA Lewis Metals.
23Site Visit InquiryItem 8 - Utility Considerations, in the PWS, directs the contractor to cut and cap services, including water, gas, sewer and electric, as the demolition is a requirement of a catastrophic storm, and utilities are generally cut and capped immediately after such an event, can you provide us with any information regarding what (if) any utilities still need to be cut and capped? How many services and what type? Size of services? Location? How will the contractor be compensated for any costs incurred for utility disconnects?Cost should be included in estimate to cut and cap utilities (water, sewer). Contractor to coordinate gas (TECO), cable (Meia Com) and electic (GCEC) again cost should be included in estimate. Locations will be closest to mains as possible.
24Site Visit InquiryWill the base have electricity and water available for abatement operations and dust control? if so, will there be any usage fees assessed to the contractor?No usage fee if available. If facility has water/power connected it can be used by the contractor. Fire hydrants close to facility can be used as a water aource. Recommend generator for electical power to ensure power availability. Any facility that does not have water contractor will need to provide a means to transport and discarge the water. Vehicle can be filled at the closest fire hydrant. Contractor to provide backflow preventer at any hookup points.
25Site Visit InquiryB5026 - Does the slab get removed?Concrete foundation stays remove building only (flush to concrete).
26Site Visit InquiryB2699 - Which pillions will get removed, concrete, wood or both?Pilings will stay unless damaged, area around piling to be leveld with gravel to prevent ponding. Pilings to be used for future construction.
27Site Visit InquiryB1259 - How much fence is to be removed?Front and sides to tree line.
28Site Visit InquiryB1259 - Will lead contaminated materials be recycled?Yes
29Site Visit InquiryB1259 - Does the dirt mound from behind the building get remove as well?No
30Site Visit InquiryB5025 - Does the 4’ retention wall get removed, how many feet? How do you want to stabilize the material?Environmental - No, As much of the retaining wall as possible should be maintained. Retaining wall should be stabilized at ends to prevent failure. Erosion control should be completed in the opening created by removing the facility to prevent the earth from washing out into the bay. Silt fencing, erosion control socks, or any other form of erosion/sedimentation control devices can be utilized to stabilize and prevent bank erosion pre/post construction. All stormwater drains must be marked and covered. See above questions.
31Site Visit InquiryB131 - Does this site get backfilled, graded and hydro-seeded or does it require gravel and compacted for a parking lot?See attached backfill sod or hydroseed no ponding
32Site Visit InquiryB1479 - Is the tower included in the demo of this building?Yes, to include footers for antenna
33SOW DocumentB1479 - Will the government provide disconnection of the fuel lines from the fuel tank or is it the responsibility of the contractor?Government will coordinate with Alutiiq to disconnect the fuel tank and generator inside B1479. Contractor will move the fuel tank and generator to the parking lot at the site for government to dispose of at later date.
34SOW DocumentWill hydroseeding or sodding be required for site restoration?Yes
35SOW DocumentWill hazardous materials such as paint cans, oil canisters ect. be disposed of by the contractor or by the government?Environmental - Hazardous waste identified as oils, paints, cleaning material, 55 gal drums, maintence racks that need to be moved out of the facilities prior to demolition will be staged in the parking lot on site and disposed of by the government.
36SOW DocumentWill there be any special requirements from Tyndall AFB Environmental on these projects?Environmental - State and Federal regulations, codes, environmental permitting are to be strictly abided for all areas. Example, stormwater runoff drains properly covered to prevent contaminents from entering system, dust control measures, etc. Storm water drains should be secured during demolition to ensure no contaminants are introduced to the storm water runoff. After construction is completed surrounding area should be properly graded to accommodate the drains. Sod and silt fencing should be installed to limit any runoff from loose soil. All BMP's are to remain until the area has been properly stabilized.
37SOW DocumentWhat will be the requirements for a crane on the flight line?Safety/Air OPS - FAA waiver, lift plan, safety plan, base approval on lifts, and flight lin training for operators
38SOW DocumentWhat will be the requirements for any equipment on the flight line?Flight OPS approval, operators require flight line training class.
39SOW DocumentWhen is the anticipated date for Award?CONS - Award will be made based on review of the received quotes, Notice of contract award will be posted to FBO when award is made
40SOW DocumentAre we able to complete another site walk next week? Due to only one representative being permitted at the site walk and the complexity of the project?CONS - No second site visit will be held for this requirement
41SOW DocumentCan we crush concrete onsite?Environmental - Crusher would require permiting and environmental approval (3 to 6 month process per site)
42SOW DocumentWill we be able to work extended hours and weekends if necessary to meet the period of performance?Weekend work and extended hours can be granted based on Government discretion. Contractors will submit requests and they will be reviewed on a case by case basis.
43SOW DocumentCan you provide drawings of the buildings?Yes for all on file
44SOW DocumentPer the PWS, we are to assume ACM/LBP in multiple buildings. There is also a CLIN for ACM/LBP testing. Are we able to complete a survey/testing prior to submitting an abatement price? This could be a substantial difference in pricing if all are assumed ACM/LBP versus abatement then demo.CONS - Contractor can complete testing at contractors expence
45SOW DocumentRefrigerant recovery will be done by Alutiq per the specs. Will the prime contractor incur any costs associated with this task?No
46SOW DocumentContractor is responsible for staging all HAZMAT. Are we responsible for the transportation and disposal to an approved facility or is there a current contractor onsite who handle this?Environmental - No, Government to dispose of oil, paint cleaners, containers at later date.
47SOW DocumentWhen is the anticipated NTP?NTP will be determined based on the date of contract award.
48SOW DocumentHow many days on badging approval?Typical badging processes are in place on Tyndall AFB and can take anywhere from 7 to 10 days.
49Solicitation DocumentA 10 day notification is referenced in the specs, due to the emergency status of the base and the structural concerns of many of the buildings will a 10 day notification be required?Yes
50Solicitation DocumentAre there any secured areas where escorts will be required?Yes, 1800 area concrete slab removal is in fenced compound. Facility Manager will provide an escort.
51Solicitation DocumentWill you provide a complete lead and asbestos surveyEnvironmental - No, will provide what is on file only
52Solicitation DocumentWill containerized paint, solvents and oil will be removed by others?If in faciity it will be removed by contractor and staged on site for government to dispose of later.
53Solicitation DocumentWill refrigerant be drained from units prior to removal?Yes
54Solicitation DocumentWill we have an area to store concrete debris, with space for crushing for reuse to fill holes?No
55Solicitation DocumentWill an area be set aside for separating metals containing lead?No
56Solicitation DocumentCan you tell us what land fields will be available for disposal in Panama City. I understand some are filling up.Contractor responsible to locate landfills. Recommend checking with Steelfield Mill Landfill.
57Solicitation DocumentAre we to assume that drywall, VCT, stucco, caulking, pipe insulation, roof mastic and A/C duct contain asbestos?Environmental - Test all facilities to clear for asbestos and LBP listed in PWS: The following facilities should be treated as ACM/LBP, tested and abated if possible (safe to enter) by the contractor. B131, B205, B248, B310, B375, B419, B421, B451, B453, B470, B529, B532, B580, B802, B822, B1259 LED, B1404, and B2699. If the facility cannot be abated the facility will be classified as ACM/LBP contaminated and sent to an authorized landfill with no recycling.
58Solicitation DocumentAre we to assume that the underside of roof decking on the shingle roofs contains lead?Environmental - Test all facilities to clear for asbestos and LBP listed in PWS: The following facilities should be treated as ACM/LBP, tested and abated if possible (safe to enter) by the contractor. B131, B205, B248, B310, B375, B419, B421, B451, B453, B470, B529, B532, B580, B802, B822, B1259 LED, B1404, and B2699. If the facility cannot be abated the facility will be classified as ACM/LBP contaminated and sent to an authorized landfill with no recycling.
59Solicitation DocumentShould the firing range be cleared of residual lead prior to demo?Environmental - Lead monitoring will be required and equipment leaving the area wil need to be cleaned, collected and properly disposed to prevent the transfer of lead contaminants to other sites.
60Solicitation DocumentCan residents and authorized personnel with work permits be allowed to work on the project?All workers are required to pass a base background check
61Solicitation DocumentDoes the base have disposal sites?No
62Solicitation DocumentWill environmental oversight personnel authorize or approve alternate abatement methods for abating hazardous materials (i.e. keeping materials wet and not containing)?Environmental - All state/federal regulations and requirements must be followed
63Solicitation DocumentCan we wet blast lead paint if found on the exterior of buildings?Environmental - If used the water and paint waste would need to be collected and dispossed of properly. Again all state and fedural regulations must be followed.
64Solicitation DocumentPermits: Are any state permits or inspections required?Yes
65Solicitation DocumentConcrete testing: Will there be an administrative period between award and NTP? If yes, could we use this time to test concrete for suitability for recycling?Yes
66Solicitation DocumentPOP: will there be administrative period between award and NTP to submit and have returned all required documents, permits etc.? If yes how long will that duration be?There is a requested 21 day mobilization period where the contractor is expected to submit documents and permits to in bonds and initial schedules. The period of performance begins after this mobilization period, and the NTP will be issued during this time.
67Solicitation DocumentPOP/mobilization: Is the 21 day mobilization in addition to or included in the 120 day POP?The 21 day mobilization period is in addition to the period of performance.
68Solicitation DocumentConcrete testing: PWS 2.1.1 c. Can we have access to any and all sites on first day of NTP to perform concrete testing on at all locations in order to determine suitability for recycling?Yes
69Solicitation DocumentBack fill: In areas to receive soil backfill and or regrading, Will seeding of grass suffice or is sod required?Sod or hydroseed
70Solicitation DocumentBack fill: PWS 2.1.1g. During the site visit it was discussed to bring back excavated foundations to grade with stone and or soil and seed/straw. Can you please clarify which areas will require stone and which are to have only soil.see attached
71Solicitation DocumentACM and LBP: Can you please provide the LBP and ACM survey?Environmental - Yes, all surveys on record are attached
72Solicitation DocumentACM and LBP survey: is additional ACM and LBP surveying of the buildings required and part of the scope of this project? If yes, can you please define scope and quantities require?Environmental - Test all facilities to clear for asbestos and LBP listed in PWS: The following facilities should be treated as ACM/LBP, tested and abated if possible (safe to enter) by the contractor. B131, B205, B248, B310, B375, B419, B421, B451, B453, B470, B529, B532, B580, B802, B822, B1259 LED, B1404, and B2699. If the facility cannot be abated the facility will be classified as ACM/LBP contaminated and sent to an authorized landfill with no recycling.
73Solicitation DocumentHazardous Materials disposal : PWS 2.2.4 Other than material that is part of the building structure( ACM and LBP) I.E. containers of paint, oil, chemicals, etc.) is disposal of Hazardous material within the scope of work or will the government take possession of the materials?Environmental - Contractor will remove the containers of paint, oil, chemicals, ect, for the facility and stage on site fot the gornment to dspose of.
74Solicitation DocumentMetal recycling: PWS 2.2.1 a. The scope of work calls for all metal to be recycled and proceeds to be returned to the government. In order to keep the cost down for the government and to have a reasonable cost benefit to the recycling effort. Can the extent of what is recovered for recycling be based on what would be typically economically advantages if the proceeds were to be keep by the contractor? If no can you please clarify the extent of what must be recycled I.E. beams, joist, nothing below ___ size….?No, recycle all from 1/2" pipe up (bulk)
75Solicitation DocumentUtilities: PWS 2.1.1 d. 8.1 & 8.2 Will the government identify location of valves, tees and/or mains?Yes
76Solicitation DocumentUtilities: PWS 2.1.1 d. & 8.4 As discussed at the site visit. Will the government have the feeds to the buildings from the transformers disconnected?Yes they will coordinate with GCEC and ALUTIIQ to have electrical disconnected from the secondary side of the transformer that feeds the facility to be demolished.
77Solicitation DocumentUtilities: PWS 2.1.1 d. & 8.4 Can the underground conduit between building service and transformers be left in place if wire is removed and building service conduit is removed to the “90” below grade?5' outside the facility perimiter (foundation) should be removed
78Solicitation DocumentUtilities: PWS 2.1.1 d. 8.1 & 8.2 Can the government please identify any water valves that serve multiple buildings?Yes
79Solicitation DocumentTrees and shrubs: Do trees and shrubs (near the footprint of the buildings) that are removed/damaged need to be replaced or migrated?Trees should be protected (as they are not many left), bushes can be removed if in the foot print of the building
80Solicitation DocumentBuilding 2699 Yacht club: Are the concrete and wooden piers to remain?Yes, unless damaged (split/cracked)
81Solicitation DocumentBuilding 1259 firing range: Will the government remove all stored bulk lead prior to demo?Environmental - Government will provide drums for the contractor to put the lead filters into, all other fragmented led can be turned in as scrap metal. Contracor is required to wear proper PPE for handling material with led contaminants.
82Solicitation DocumentBuilding 1259 firing range: Are the grounds and or building components contaminated with lead?Environmental yes, metal can still be recycled, concrete should be disposed of properly which requires TCLP samples to conduct a HazWaste Determination
83Solicitation DocumentBuilding 1259 firing range: Is the steel components of the building to be recycled or treated as hazardous waste?Environmental Recycled
84Solicitation DocumentBuilding 1259 firing range: Does the soil around the building need to be removed or can it be graded without concern for lead contamination /exposure?Environmental Soil around Facility is contaminated with lead, but soil remediation is not part of the scope for this PWS. Proper PPE must be used while demolishing the facility and foundation.
85Solicitation DocumentBuilding 1259 firing range: Fence removal What is the limits of the fence removal?Front of facility and both sides to the tree line.
86Solicitation DocumentBuilding 1479 base LMR: Is the antenna removal within the scope of work?Yes, to include footers of antenna
87Solicitation DocumentBuilding 1479 base LMR: Is the removal of the antenna foundation within the scope of work?Yes
88Solicitation DocumentRadioactive waste: Is there any demo of radioactive material /contamination that is within the scope of work? If yes can you please identify location and quantity?No
89Solicitation DocumentMedical waste :Is there any medical waste removal that is within the scope of work? If yes can you please identify location and quantity?No
90Solicitation DocumentFOD plan: Can You please provide the bases current FOD plan?Environmental 4' silt fencing is to be used and properly installed and maintained to catch debris that may blow around due to demolition of facility. Debry should be wet during demolision to prevent FOD from blowing on runway. Air OPS should be notified immediately if any debry blows out to the runway.
91Solicitation DocumentCan you please provide a definition or specification for "class 4 construction waste".Environmental construction waste non hazardous
92Solicitation DocumentLandfills: Can you please provide a list of approved landfills for C&D and/or HazMat (ACM and Concrete as well)?No
93Solicitation DocumentOil/water separator: At the site walk I learned that there is an oil/water separator system in one or more buildings Is the removal within the scope of work? If yes can you please identify with buildings contain oil/water separators?Buildings B83, B168 have oil/water seperators but only the facility is being removed. If not already covered, the OWS must be during construction along with any inlet drain leading to the OWS.
94Solicitation DocumentStaging of hazardous material: PWS 2.2.4, Can you please provide requirements for staging hazardous materials for government removal?Environmental A space will be identified at each facility to stage the materials removed from the facility. Materials will be staged on a concrete or asphalt area. Any items that are leaking should be contained in a standard containment to minimize spillage.
95Solicitation DocumentArchaeological monitoring agent: PWS 3.3.5, Are we required to have a full time archaeological monitoring agent whenever earth is disturbed such as slab on grade removal or only when disturbing virgin soil below grade?Environmental - Any foundation or slab deeper than 6 inches in the ground requires an Archaeologist monitor on site.
96Solicitation DocumentOn the walk some of the buildings still had computers and other possible sensitive equipment. Will all of the sensitive military equipment be removed before demo begins or will we have to work with the AF in securing these assets during demo?Items to be removed from facilities will be identified with the contractor prior to start of demolision of each facility.
97Solicitation DocumentOn the walk some locations were to be filled with clean fill, some with gravel, and some with grass. Could it please be identified which locations receive which finishing treatment?see attached
98Solicitation DocumentCan the historical asbestos surveys be provided for the buildings?Environmental - Yes what is on record. See attached
99Solicitation DocumentCan as builts be provided for the buildings?Yes see attached for what the base has
100Solicitation DocumentCan the limits of the concrete pad for B334 be provided?See attached for discription of work (bullards ramps footprint of facility)
101Solicitation DocumentCan the big red devise in the floor of B375 be identified?Pallet scale, to be removed and saved.
102SOW Document2.2.3 of the PWS identifies facilities to be treated as ACM/LPB facilities. Are Hazmat surveys to be performed on these prior to demolition and should this be included in the bid price?Environmental - Test all facilities to clear for asbestos and LBP listed in PWS: The following facilities should be treated as ACM/LBP, tested and abated if possible (safe to enter) by the contractor. B131, B205, B248, B310, B375, B419, B421, B451, B453, B470, B529, B532, B580, B802, B822, B1259 LED, B1404, and B2699. If the facility cannot be abated the facility will be classified as ACM/LBP contaminated and sent to an authorized landfill with no recycling.
103SOW Document2.2.3 of the PWS identifies facilities to be treated as ACM/LPB facilities. Will the removal of hazardous material resulting from a post award Hazamat survey confirming the existence and quantify of these materials be treated as an unforeseen condition? Will a change order be issued for removal of the quantifies material.No, estimates should reflect your process of abatement and disposal
104SOW Document2.2.3 of the PWS identifies facilities to be treated a s. Is it the AF's intent for the contractor to treat these facilities as hazmat and price the entire structure as class 4 debris?Environmental - Test all facilities to clear for asbestos and LBP listed in PWS: The following facilities should be treated as ACM/LBP, tested and abated if possible (safe to enter) by the contractor. B131, B205, B248, B310, B375, B419, B421, B451, B453, B470, B529, B532, B580, B802, B822, B1259 LED, B1404, and B2699. If the facility cannot be abated the facility will be classified as ACM/LBP contaminated and sent to an authorized landfill with no recycling.
105SOW Document2.2.3 of the PWS identifies facilities to be treated as ACM/LPB facilities and states that the entire facility will be classified as ACM/LBP contaminated if entire facility cannot be abated. That is a determination that can only be made post award and after a survey has been performed. Will the AF entertain requiring all bidders to include Hazmat surveys for ALL buildings in the project scope with unit prices for removal of these potential materials once they have been identified in a survey that can only be performed post award?Environmental - Test all facilities to clear for asbestos and LBP listed in PWS: The following facilities should be treated as ACM/LBP, tested and abated if possible (safe to enter) by the contractor. B131, B205, B248, B310, B375, B419, B421, B451, B453, B470, B529, B532, B580, B802, B822, B1259 LED, B1404, and B2699. If the facility cannot be abated the facility will be classified as ACM/LBP contaminated and sent to an authorized landfill with no recycling.
106SOW Document2.2.3 of the PWS identifies facilities to be treated as ACM/LPB facilities. Will the AF entertain unit price for Class 4 disposal fees for any of the identified structures that cannot be completely abated and must be classified as ACM/LBP contaminated?Complete an honest estimate to encompass hazardous material and standard construction material.
107SOW Document2.2.4 of the PWS; will there be any cost associated for the reclamation of refrigerants reclaimed by Alutiiq? Is the government bearing any cost associated with refrigerant removal?No cost to contractor for work Alutiiq completes to reclamation refrigerant from facilities.
108SOW Document2.2.4 of the PWS indicates the potential of previously stored hazardous material that are not ACM/LBP. Does an inventory or list of buildings that may contain these OTHER hazardous wastes exist for pricing purposes? If the potential for these hazardous materials other than ACM/LBP exists and no inventory or other quantifying element exists, will this be treated as an unforeseen condition and the contractor receive compensation for this unidentifiable and unquantifiable hazardous material.If there is a hazardous material found that has leaked or is leaking it would be considered a unforseen. Most of the materials in the facilities are containerized and not leaking. They are to be removed and staged in the parking lot of the facility by the contractor for the government to dispose of at a later date.
109SOW Document8.0 of the PWS Utility Considerations. Are the lines of the utilities leaving the buildings to be abandoned in place between the designated point of capping/plugging and the building or are these lines to be removed as part of the building demolition scope? If they are to be removed, estimated quantities and sizes of these lines need to be provide as well as any pavement and sidewalk destruction and restoration that would have to take place.Utilities are to be cut capped. Lines should be removed within a 5' perimiter of the facility. Remaining line from cap location to facility can be appandoned in place.
110Solicitation DocumentThe bid schedule CLIN 0050 Abatement Testing: Is this CLIN for ACM/LBP surveys on ALL structures or just those identified in section 2.2.3 of the PWS? Please identify any other structures that will be required to be tested prior to demolition.Environmental - Test all facilities to clear for asbestos, facilities listed in PWS: The following facilities should be treated as ACM/LBP, tested and abated if possible (safe to enter) by the contractor. B131, B205, B248, B310, B375, B419, B421, B451, B453, B470, B529, B532, B580, B802, B822, B1259 LED, B1404, and B2699. If the facility cannot be abated the facility will be classified as ACM/LBP contaminated and sent to an authorized landfill with no recycling.
111Solicitation DocumentIs all concrete required to be disposed of at a class 4 landfill.Contractor can recycle the concrete is it is tested and clear as clean for reuse.
112Solicitation DocumentIs all backfill material to be natural or virgin soil/material.Environmental If required the source of backfill shall be natural or virgin material (other than the operation of a borrow pit facility) and shall be in an area which has not previously been used for commercial or industrial activities. One soil sample will be collected from the borrow source and analyzed for the following parameters: Volatile Organic Compounds (VOCs) per Method 8260, Semi-volatile Organic Compounds (SVOCs) [Base/Neutrals (e.g., PAHs, Pesticides, PCBs) and Acid Extractables (e.g., Phenols)] per Methods 8270/8081/8082, RCRA metals by Method 6020, Petroleum Residual Organics (by FL-PRO), Analytical results will be compared to the FDEP residential Soil Cleanup Target Levels to determine acceptability of the proposed material as clean fill. Any backfill must be certified clean and meet requirements.
113Solicitation DocumentConfirm gravel is not a required backfill material at any site.see attached list for clarification
114Solicitation DocumentAre any building components other than transformers and light poles scheduled to be removed by others ;i.e. chillers, AHUs compressors, etc.No
115SOW Document3.2.1 of the PWS, please confirm that all scrap metal once seperated is to be hauled to 2312 Industrial Drive.Base Recycling Contract information, Contractor should contact below location for questions on operations.

Emerald Coast Recycling/DBA Lewis Metals 2312 Industrial Drive Panama City, Florida 32405 Office Phone: 850 769-1336

116Solicitation DocumentWill the base recycling contractor haul all salvaged material to 2312 Industrial Drive or is this the responsibility of the contractor.NO the Contractor awarded the demolition project will transport scrap metal to the designated location.
117SOW Document3.3.5 of the PWS is the archaeological monitor to be on site at all times or only when slab and subsurface foundations are being removed.Environmental - only when slab and subsurface foundations are being removed. See above answer.
118Solicitation DocumentConsidering all sites are less than and acre in size, will an NPDES or other permit be required to be filed with the FDEP?Environmental - It is the responsibility of the contractor to verify what permits are required per Section 3.2.1. Contractor must consult with 325 CES it any permits are required and all applications must be reviewed and signed by the 325 CES Commander. If permits are deemed required by the 325 CES, the contractor will stop work and address environmental concerns.
119Solicitation DocumentIn regards to sewer capping. Is it acceptable to brick and grout the line at the manhole? Instead of digging up and putting an actual cap on the line.Where possible. Close open ends of abandoned underground utilities which are indicated to remain in place. Provide sufficiently strong closures to withstand hydrostatic or earth pressure which may result after ends of abandoned utilities have been closed. Close open ends of concrete or masonry utilities with not less than eight inch thick brick masonry bulkheads. Close open ends of conduit with plastic plugs, or other acceptable methods suitable for size and type material being closed. Wood plugs are not acceptable. If flowable fill is used it must be non shrink.
120Solicitation Document
121Solicitation Document
122Solicitation Document
123Solicitation Document
124Solicitation Document
125Solicitation Document
126Solicitation Document
127Solicitation Document
128Solicitation Document
129Solicitation Document
130Solicitation Document
131Solicitation Document
132Solicitation Document
133Solicitation Document
134Solicitation Document
135Solicitation Document
136Solicitation Document
137Solicitation Document