Attachment 9 -ASBUILT DWGS - Shelter Electrical 2.pdf
PDF 4 MB Posted
- Attached to
- Pre-Engineered Steel Aircraft Canopies IDIQ
- Solicitation number
- FA480921R0009
View the file
Other files
Show all 29
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
U
DATE
SHEET
DRAWN BY
OF
PROJECT NUMBER
DRAWING NUMBER
1 2 3 4 5 6 7 8 9 10 11
A
B
C
D
E
F
G
7 8 9 10 111 2 3 4 5 6
H
B
C
D
E
F
G
H
VKAG 18-1041
CONSTRUCT SECONDARY DISTRIBUTION FOR
AIRCRAFT SHELTERS, 10218, P2
15 FEB 2018
1" = 800'
CENME
VKAG 18-1041
C O
N S
T R
U C
T
S
E C
O N
D A
R Y
D
I S
T R
I B
U T
I O
N
F
O R
A I R
C R
A F
T
S
H E
L T
E R
S
P
L O
C A
T I O
N
P
L A
N
A
N
A
W I N
G
I N
D E
X
LOCATION PLAN
SCALE: 1"=800'
FINAL DETERMINATION REVEALS NO PRIME OR UNIQUE
FARMLAND ON THE BASE
NOTE
BASE CONTRACTING
BASE CIVIL ENGINEER
GATE 2 (SLOCUMB GATE)
CONTRACTOR'S
STORAGE AREA
GATE 1 (BERKELEY GATE)
VISITOR'S CENTER
MAG. VAR
. 9°-22'W
JUN 11
N
PROJECT LOCATION
DRAWING INDEX
DWG NO SHT NO DESCRIPTION
G-1 1 LOCATION PLAN AND DRAWING INDEX
C-1 2
RAMP SITE AND UTILITY PLAN
E-1 3
SITE CONDUIT PLAN
E-2 4
SITE CONDUIT PLAN AND DETAILS
E-3 5
ELECTRICAL SERVICE B
E-4 6
TRENCHING AND DUCTBANK DETAILS
E-5 7
EQUIPMENT MOUNTING DETAILS
HAUL ROUTE
GATE 3 (OAK FOREST GATE)
AS-BUILT
SCALE
FACILITY
H
T
R
F
U
B
T
I
T
S
R
O
F
U
DATE
SHEET
DRAWN BY
OF
PROJECT NUMBER
DRAWING NUMBER
P R
O J E
C T
T
L E
D R
A W
I N
G
S
H E
E
A M
E
T H
U N
I T
S
A
T E
S
A
F
O R
C
V
I L
E
N G
I N
E E
R
S
Q U
A D
R O
N
S E
Y M
O U
R
J O
H N
S O
N
A
R
B
S
E
N
O R
H
R
O L I N
A
P R
O J E
P
A
S E
C O
N T
R A o
T A
K
D
D A
T E
D E
S C
R I P
T I O
N R
E V
1 2 3 4 5 6 7 8 9 10 11
A
B
C
D
E
F
G
7 8 9 10 111 2 3 4 5 6
H
A
B
C
D
E
F
G
H v:\PROJECTS\FY-18\vkag 18-1041\vkag 18-1041 as-built\VKAG 18-1041 C-1.dwg
15 FEB 2018
AS-SHOWN
CENME
VKAG 18-1041
C O
N S
T R
U C
T
S
E C
O N
D A
S
T R
I B
U T
I O
N
F
O R
A I R
C R
A F
T
S
H E
L T
E R
S
P
R A
M
T
E
A
I L I T
Y
P
L A
N
I L
T
F A
D
C
F A
F
10032
LEGEND:
GROUNDING / TIE DOWN POINT
SANITARY SEWER
STORM DRAINAGE
WATER LINE
EXISTING ELECTRICAL UNDERGROUND
ENTRY CONTROL POINT
10739
10740
10741
10721
10722
10723
10724
10725
10726
10742
10743
10744
10745
10746
NOTES:
1. REPLACE ANY TIE DOWNS REMOVED OR DESTROYED DURING CONSTRUCTION.
2. MINIMUM DISTANCE FROM TIEDOWN CENTER POINT TO AN UNDOWELED JOINT IS 914 MM (3'). WHEN TIE
DOWNS OCCUR 914MM (3') FROM SINGLE POINT, ORIENT BAR PARALLEL WITH THE JOINT. IF CENTER POINT
OCCURS 914MM (3') FROM ADJACENT JOINTS, ORIENT BAR PARALLEL WITH EITHER JOINT.
3. BAR WILL BE 32MM (1.25") ASI 4130.
TIEDOWN AND GROUNDING POINT, SECTION A-A
SCALE: 1-1/2"=1'
36"
5"
3" RADIUS
(NOTE 3)
#5 REBAR, FOUR
EACH WAY, TYP
10' LONG
3/4" COPPER
GROUND ROD
(CADWELD TO
STEEL)
#1/0 BARE
COPPER
C1
TIEDOWN AND GROUNDING POINT, PLAN
SCALE: 1-1/2"=1'
A A
C1
1245 3
T
R
F
U
B
T
A P
P R
V D
D A
T E
I
T
S
R
O
F
U
G
D E
S C
R I P
T I O
N R
E V
F
E
H
D
C
B
P R
O J E
T
L E
D R
A W
I N
G
S
H E
M
E
SCALE
DATE
T H
U N
I T
A
T E
S
A
R
C
V
I L
E
N G
I N
E E
R
S
Q U
A D
R O
N
S E
Y M
O U
R
J O
H N
S O
N
A
R
S
E
N
O R
R
O L I N
A
SHEET
DRAWN BY
OF
PROJECT NUMBER
245 3
DRAWING NUMBER
A
678910
G
F
E
H
D
C
B
678910
A v:\PROJECTS\FY-18\vkag 18-1041\vkag 18-1041 as-built\VKAG 18-1041 E-1.dwg
P R
O J E
A
S E
C O
N T
R A
T A
D
N S
T R
U C
T
S
E C
O N
D A
S
T R
I B
U T
I O
N
F
O R
A I R
C R
A F
T
S
H E
L T
E R
S
P
S I T
E
C
O N
D U
L A
N
15 FEB 2018
AS SHOWN
CENME
VKAG 18-1041
I L
T
F A
D
C
F A
F
ELECTRICAL SERVICE AREA "B"
SCALE: 1" = 40'
ABBREVIATIONS:
A AMPERES
AFI AIR FORCE INSTRUCTION
AFF ABOVE FINISHED FLOOR
COMM COMMUNICATION
HDPE HIGH-DENSITY POLYETHYLENE
MECH MECHANICAL
NFPA NATIONAL FIRE PROTECTION ASSOCIATION
RM ROOM
SCH SCHEDULE
THW THERMOPLASTIC HEAT AND WATER RESISTANT INSULATED WIRE
THWN THERMOPLASTIC HEAT AND WATER RESISTANT NYLON COATED
UFC UNIFIED FACILITIES CRITERIA
V VOLTS
XFMR TRANSFORMER
ELECTRICAL LEGEND:
ELECTRICAL CONDUIT ROUTE - UNDERGROUND
TRANSFORMER (EXISTING)
GENERAL NOTES:
1. ALL CONDUIT BELOW AIRFIELD PAVEMENTS TO BE DIRECTIONALLY BORED
UNLESS OTHERWISE NOTED. UNDERGROUND CONDUIT SHALL BE SMOOTHWALL
SCH 80 HDPE.
2.COORDINATE LOCATION OF BORING PITS WITH CONTRACTING OFFICER.
3.CONTRACTOR TO IDENTIFY AND LOCATE ALL EXISTING UNDERGROUND UTILITIES.
UTILITIES SHOWN ARE NOT GUARANTEED TO BE COMPREHENSIVE.
4.MAINTAIN 10" HORIZONTAL AND 18" VERTICAL SEPARATION BETWEEN ALL OTHER
UTILITIES.
5.ALL WORK TO COMPLY WITH NFPA 70, AFI 21-136, UFC 3-550-01, UFC 3-530-01,
UFC 3-260-01 AND T.O. 00-25-172.
6.ALL LOW VOLTAGE WIRING SHALL BE COPPER, STRANDED, 600V, TYPE THW OR
THWN UNLESS OTHERWISE NOTED.
7.COORDINATE LOCATION OF HANDHOLES WITH CONTRACTING OFFICER.
8.DISCONNECT SWITCH, TOP OF HANDLE 6'-6" AFF.
RESTRICTED AREA BOUNDARY ENTRY CONTROL
POINT
40'
40' 120'
1"=40'
NEW COMMUNICATION CONDUIT ROUTE - UNDERGROUND
BORE DEPTHS - H-11 TO BLDG 4538
PIN DEPTH PIN DEPTH
1 3'-9" 2 4'-10"
3 5'-6" 4 6'-6"
5 7'-8" 6 8'-6"
7 9'-10" 8 10'-1"
9 10'-4" 10 10'-11"
11 11'-4" 12 11'-5"
13 11'-3" 14 11'-2"
15 11'-0" 16 10-6"
17 9'-8" 18 9'-4"
19 8'-9" 20 8'-6"
21 7'-8" 22 6'-0"
23 4'-10" - -
BORE DEPTHS - H-11 TO I-11
PIN DEPTH PIN DEPTH
1 3'-6" 2 4'-8"
3 6'-10" 4 7'-7"
5 8'-11" 6 9'-8"
7 10'-6" 8 10'-8"
9 10'-8" 10 10'-5"
11 10'-3" 12 10'-2"
13 9'-9" 14 9'-3"
15 9'-1" 16 8'-10"
17 9'-0" 18 8'-8"
19 8'-6" 20 8'-8"
21 8'-10" 22 8'-3"
23 8'-1" 24 7'-6"
25 6'-10" 26 5'-10"
27 3'-9" - -
N
MAG. VAR. 9°-34'W
MAR '17
M
*NOTE: TYPICAL DISTANCE
BETWEEN PINS = 10'-0"
10741
H-13
10742
H-12
10743
H-11
10744
H-10
10745
H-9
10746
H-8
10740
H-14
10722
I-12
10723
I-11
10724
I-10
10726
I-8
10721
I-13
10725
I-9
*NOTE: TYPICAL DISTANCE
BETWEEN PINS = 10'-0"
MECH
RM
400A DISCONNECT
INSTALL 400A
DISCONNECT
EXISTING
XFMR
T4538
ELECTRICAL
HANDHOLE
100 AMP DISCONNECT
& PANEL B-1 TO BE
INSTALLED ON
UNISTRUT RACK
400A PANEL
INSTALL 2-100A
3 POLE BREAKERS
2-1/2" CONDUIT
OVERHEAD IN
HANGER BAY
COMM HANDHOLE
WALL MOUNTED
DRY TYPE
TRANSFORMER
1245 3
T
R
F
U
B
T
A P
P R
V D
D A
T E
I
T
S
R
O
F
U
G
D E
S C
R I P
T I O
N R
E V
F
E
H
D
C
B
P R
O J E
T
L E
D R
A W
I N
G
S
H E
M
E
SCALE
DATE
T H
U N
I T
A
T E
S
A
R
C
V
I L
E
N G
I N
E E
R
S
Q U
A D
R O
N
S E
Y M
O U
R
J O
H N
S O
N
A
R
S
E
N
O R
R
O L I N
A
SHEET
DRAWN BY
OF
PROJECT NUMBER
245 3
DRAWING NUMBER
A
678910
G
F
E
H
D
C
B
678910
A v:\PROJECTS\FY-18\vkag 18-1041\vkag 18-1041 as-built\VKAG 18-1041 E-2.dwg
P R
O J E
A
S E
C O
N T
R A
T A
D
N S
T R
U C
T
S
E C
O N
D A
S
T R
I B
U T
I O
N
F
O R
A I R
C R
A F
T
S
H E
L T
E R
S
P
S I T
E
C
O N
D U
L A
N
A
T
A I L S
15 FEB 2018
AS SHOWN
CENME
VKAG 18-1041
I L
T
F A
D
C
F A
F
N
MAG. VAR. 9°-34'W
MAR '17
M
40'
40' 120'
1"=40'
GENERAL NOTES:
1. 1 CONDUCTORS PER PHASE UTILIZING A #8 COPPER CONDUCTOR WILL
LIMIT THE VOLTAGE DROP TO 2.04% OR LESS WHEN SUPPLYING 7.21
AMPS FOR 490 FEET ON A 208 VOLT SYSTEM. (LIGHTS AT FURTHEST
SHELTER) 10740 & 10746.
2. 1 CONDUCTORS PER PHASE UTILIZING A #10 COPPER CONDUCTOR
WILL LIMIT THE VOLTAGE DROP TO 2.58% OR LESS WHEN SUPPLYING
3.0 AMPS FOR 490 FEET ON A 120 VOLT SYSTEM. (RECEPTS AT
FURTHEST SHELTER) 10740 & 10746.
3. 1 CONDUCTORS PER PHASE UTILIZING A #10 COPPER CONDUCTOR
WILL LIMIT THE VOLTAGE DROP TO 2.55% OR LESS WHEN SUPPLYING
7.21 AMPS FOR 350 FEET ON A 208 VOLT SYSTEM. (LIGHTS AT SECOND
FURTHEST SHELTER) 10745 & 10741.
4. 1 CONDUCTORS PER PHASE UTILIZING A #10 COPPER CONDUCTOR
WILL LIMIT THE VOLTAGE DROP TO 1.60% OR LESS WHEN SUPPLYING
3.0 AMPS FOR 350 FEET ON A 120 VOLT SYSTEM. (RECEPTS AT 2ND
FURTHEST SHELTER) 10745 & 10741.
5. 1 CONDUCTORS PER PHASE UTILIZING A #10 COPPER CONDUCTOR
WILL LIMIT THE VOLTAGE DROP TO 1.33% OR LESS WHEN SUPPLYING
7.21 AMPS FOR 210 FEET ON A 208 VOLT SYSTEM. (LIGHTS AT 1ST
FURTHEST SHELTER) 10744 & 10742.
6. 1 CONDUCTORS PER PHASE UTILIZING A #12 COPPER CONDUCTOR
WILL LIMIT THE VOLTAGE DROP TO 1.58% OR LESS WHEN SUPPLYING
3.0 AMPS FOR 210 FEET ON A 120 VOLT SYSTEM. (RECEPTS AT 1ST
FURTHEST SHELTER) 10744 & 10742.
7. 1 CONDUCTORS PER PHASE UTILIZING A #14 COPPER CONDUCTOR
WILL LIMIT THE VOLTAGE DROP TO 1.94% OR LESS WHEN SUPPLYING
7.21 AMPS FOR 120 FEET ON A 208 VOLT SYSTEM. (LIGHTS IN SHELTER
WHERE PANEL IS LOCATED) 10743 (#12 WILL BE USED).
8. 1 CONDUCTORS PER PHASE UTILIZING A #14 COPPER CONDUCTOR
WILL LIMIT THE VOLTAGE DROP TO 1.40% OR LESS WHEN SUPPLYING
3.0 AMPS FOR 120 FEET ON A 120 VOLT SYSTEM. (RECEPTS IN SHELTER
WERE PANEL IS LOCATED) 10743 (#12 WILL BE USED).
PER SHELTER AMP IS:
(1.25*150W/208V*8QTYLIGHTS+180VA/120*QTYRECPT)*(1 SHELTER)=10.21 AMPS.
(1.25*150W/208*8+180/120*2)*(1 SHELTER)=10.21 AMPS.
150 WATT LIGHTS (ON SPEC SHEET) NO 208 VOLT GIVEN CONTINUOUS LOAD 1.25
MULTIPLY.
10.21A*7 SHELTERS = 71.47 AMPS
71.47 AMPS/(3 PHASE) = 23.81 AMPS PER EACH PHASE
LIGHTS = 7.21 AMPS
RECEPTACLES 3 AMPS
1 CONDUCTORS PER PHASE UTILIZING A #1 COPPER CONDUCTOR WILL LIMIT THE
VOLTAGE DROP TO 1.01% OR LESS WHEN SUPPLYING 23.82 AMPS FOR 340 FEET ON
A 208 VOLT SYSTEM.
FOR ENGINEERING INFORMATION ONLY:
110.0 AMPS RATED AMPACITY OF SELECTED CONDUCTOR
0.1427 OHMS RESISTANCE (OHMS PER 1000 FEET)
0.046 OHMS REACTANCE (OHMS PER 1000 FEET)
2.2880000000000003 VOLTS MAXIMUM ALLOWABLE VOLTAGE DROP AT 1.1%
2.083 ACTUAL VOLTAGE DROP LOSS AT 1.01% FOR THE CIRCUIT.
0.9 POWER FACTOR
= (8)-150 WATT EXPLOSION PROOF/WP LED FLOODLIGHTS W/ MOUNTING
HARDWARE PER SHELTER (TYP)
= (2)-20A, 125V TWO GANG EXPLOSION-PROOF/WP RECEPTACLES PER SHELTER,
48" AFF (TYP)
= (1)-20A, TWO POLE, 120-277V EXPLOSION PROOF/WP SNAP
SWITCH PER SHELTER, 48" AFF (TYP)
= JUNCTION BOX
PANEL #1 (10743/H-11)
CKT CKT
1 H-12 LIGHTS 2 H-9 LIGHTS
3 H-12 LIGHTS 4 H-9 LIGHTS
5 H-11 LIGHTS 6 H-8 LIGHTS
7 H-11 LIGHTS 8 H-8 LIGHTS
9 H-10 LIGHTS 10 H-13 LIGHTS
11 H-10 LIGHTS 12 H-13 LIGHTS
13 H-14 LIGHTS 14 H-10 RECEPTS
15 H-14 LIGHTS 16 H-11 RECEPTS
17 H-9 RECEPTS 18 H-14 RECEPTS
19 H-12 RECEPTS 20 H-13 RECEPTS
21 SPACE 22 H-8 RECEPTS
*PANEL #1 IS 120/208 FED FROM PANEL
LOCATED WITHIN BUILDING 4538.
PANEL #2 (10723/I-11)
CKT CKT
1 I-12 LIGHTS 2 I-9 LIGHTS
3 I-12 LIGHTS 4 I-9 LIGHTS
5 I-11 LIGHTS 6 I-8 LIGHTS
7 I-11 LIGHTS 8 I-8 LIGHTS
9 I-10 LIGHTS 10 I-13 LIGHTS
11 I-10 LIGHTS 12 I-13 LIGHTS
13 SPACE 14 I-10 RECEPTS
15 SPACE 16 I-11 RECEPTS
17 I-9 RECEPTS 18 SPACE
19 I-12 RECEPTS 20 I-13 RECEPTS
21 SPACE 22 I-8 RECEPTS
*PANEL #2 IS 120/208 FED FROM SHELTER PANEL
LOCATED WITHIN BUILDING 4538.
ABBREVIATIONS:
A AMPERES
AFF ABOVE FINISHED FLOOR
CKT CIRCUIT
G GROUND
MECH MECHANICAL
RECEPTS RECEPTACLES
TYP TYPICAL
V VOLT
W/ WITH
WP WATER PROOF
ELECTRICAL LEGEND:
S
G
RECEPT 2#10 1#12G
PANEL 1 - CKT 18
CLASS i SW (TYP)
1 PER SHELTER
RECEPT 2#10 1#12G
PANEL 1 - CKT 20
RECEPT 2#10 1#12G
PANEL 1 - CKT 19
UNDERGROUND
DIRECTIONAL BORE
PHASE I (NOTE 1)
RECEPT 2#12 1#12G
PANEL 1 - CKT 16
IN GROUND
PULL BOX
RECEPT 2#12 1#12G
PANEL 1 - CKT 14
RECEPT 2#10 1#12G
PANEL 1 - CKT 17
RECEPT 2#10 1#12G
PANEL 1 - CKT 22
RECEPT 2#10 1#12G
PANEL 2 - CKT 20
RECEPT 2#10 1#12G
PANEL 2 - CKT 19
RECEPT 2#10 1#12G
PANEL 2 - CKT 22
RECEPT 2#10 1#12G
PANEL 2 - CKT 17
RECEPT 2#12 1#12G
PANEL 2 - CKT 14
RECEPT 2#12 1#12G
PANEL 2 - CKT 16
LIGHTS 2#10W/G
PANEL 2 - CKT 2,4
LIGHTS 2#8W/G
PANEL 2 - CKT 6,8
LIGHTS 2#10W/G
PANEL 2 - CKT 9,11
LIGHTS 2#12W/G
PANEL 2 - CKT 5,7
LIGHTS 2#10W/G
PANEL 2 - CKT 1,3
LIGHTS 2#10W/G
PANEL 2 - CKT 10,12
LIGHTS 2#8W/G
PANEL 1 - CKT 6,8
LIGHTS 2#10W/G
PANEL 1 - CKT 2,4
LIGHTS 2#10W/G
PANEL 1 - CKT 9,11
LIGHTS 2#12W/G
PANEL 1 - CKT 5,7
LIGHTS 2#10W/G
PANEL 1 - CKT 1,3
LIGHTS 2#10W/G
PANEL 1 - CKT 10,12
LIGHTS 2#8W/G
PANEL 1 - CKT 13,15
10741
H-13
10742
H-12
10743
H-11
10744
H-10
10745
H-9
10746
H-8
10722
I-12
10723
I-11
10724
I-10
10726
I-8
10721
I-13
10725
I-9
10740
H-14
G
G
G
G
G
G
G
G
G
G
G
G
PANEL #1
(SEE DETAIL 1 - SHEET E-5)
ELECTRICAL
HANDHOLE
COMM HANDHOLE
H
T
R
F
U
B
T
I
T
S
R
O
F
U
DATE
SHEET
DRAWN BY
OF
PROJECT NUMBER
DRAWING NUMBER
P R
O J E
T
L E
D R
A W
I N
G
S
H E
M
E
T H
U N
I T
A
T E
S
A
R
C
V
I L
E
N G
I N
E E
R
S
Q U
A D
R O
N
S E
Y M
O U
R
J O
H N
S O
N
A
R
S
E
N
O R
R
O L I N
A
P R
O J E
A
S E
C O
N T
R A
T A
D
D A
T E
D E
S C
R I P
T I O
N R
E V
1 2 3 4 5 6 7 8 9 10 11
A
B
C
D
E
F
G
7 8 9 10 111 2 3 4 5 6
H
A
B
C
D
E
F
G
H v:\PROJECTS\FY-18\vkag 18-1041\vkag 18-1041 as-built\VKAG 18-1041 E-3.dwg
15 FEB 2018
AS-SHOWN
CENME
VKAG 18-1041
C O
N S
T R
U C
T
S
E C
O N
D A
S
T R
I B
U T
I O
N
F
O R
A I R
C R
A F
T
S
H E
L T
E R
S
P
E L E
C T
R I C
A L
S
E R
V I C
E
B
I L
T
F A
D
C
F A
F
J U
N E
I L
T
10032
SERVICE "B" RISER
NOTES:
1. BRANCH CKT WIRING METHOD SHALL BE
NTP-THREADED INTERMEDIATE METAL CONDUIT
(IMC).
2. SECURE/SUPPORT CONDUIT TO SHELTER FRAME.
3. ALL ENCLOSURES/EQUIPMENT INSIDE SHELTER
SHALL BE LISTED FOR CLASS 1, DIVISION 2 HAZ
LOCATIONS AS REQUIRED BY THE NATIONAL
ELECTRIC CODE (NEC).
4. BOXES AND FITTINGS NOT REQUIRED TO BE
EXPLOSIONPROOF ENCLOSURES SHALL CONTAIN
NO ARCING DEVICES; ADDITIONALLY, THESE
ENCLOSURES MUST COMPLY WITH NEC ARTICLE 501
PART III THAT IDENTIFIES THE GENERAL PURPOSE
ENCLOSURES THAT ARE ALLOWED IN CLASS I,
DIVISION 2 LOCATIONS.
5. CONDUITS ENTERING AN EXPLOSIONPROOF
ENCLOSURE REQUIRE A SEALING FITTING WITHIN 18
INCHES OF THE CONDUIT ENTRANCE. SIX INCH
CONDUITS SHALL BE REQUIRED WHERE LISTED TO
ALLOW ADDITIONAL CAPACITY FOR FUTURE USE.
6. USE BOXES, JUNCTIONS, AND CONDUIT AS
REQUIRED TO WIRE EACH LIGHT FIXTURE, TOGGLE
SWITCH, AND RECEPTACLES IN EACH RESPECTIVE
SHELTER. SIZE CONDUITS IAW NEC.
7. THE CONTRACTOR IS RESPONSIBLE TO DETERMINE
ALL CONDUCTORS SIZES USING NFPA 70 & UFC
3-501-01 AND RESIZE CONDUCTORS AS NECESSARY
WITH ALLOWANCE FOR EXTRA CAPACITY.
8. CONTRACTOR IS REQUIRED TO PROVIDE A PANEL
SCHEDULE ON FOR CONSTRUCTION DRAWINGS.
E3
EXTERIOR OF BUILDING
500 KVA 277/480
3-250 MCM
4" CONDUIT
USE EXISTING SPARE
4" CONDUIT TO
INSTALL NEW
FEEDERS.
INTERIOR OF BUILDING
MOUNT AT
EXISTING
SERVICE
INSTALL 400 AMP
SHELTER DISCONNECT #2
AT HANGER WALL
FUSE AT 225 AMP
INSTALL 2 100 AMP 3 POLE
BREAKERS
LOCATED AT CORNER OF HANGER
400 AMP MLO 120/208
ELECTRICAL HANDHOLE
RACEWAYS TO LOAD AS DESCRIBED ON SHEET E-2.
EXPLOSION PROOF 100AMP DISCONNECT
RUN 2.5 CONDUIT WITH 3-350 MCM
2.5 CONDUIT
W/ 3-4/0
3.5" CONDUIT
W/ 4 500 MCM
AND GRND
2 SETS 4-2/0 IN
2" CONDUIT
INSTALL 4-#1 WITH GROUND
INSTALL 400A SE
RATED DISCONNECT
FUSED AT 300 AMP
RUN 2.5 CONDUIT WITH 3-350 MCM
RUN 2.5 CONDUIT WITH 3-350 MCM
EXISTING
480/277
AMP
SERVICE
FUSED AT 225 FOR
INRUSH ENCLOSED
CB WITH ADJ TRIP
MAY BE REQUIRED.
EXISTING
TRANSFORMER
T4538
BEHIND HANGAR
PROVIDE SERVICE
GROUNDING AS
REQUIRED BY NEC
2 SIX INCH CONDUITS DIRECTIONAL
BORE TO AIRCRAFT SHELTERS
(TYPICAL OF 2 LOCATIONS
INSTALL 6 INCH SEAL OFF AT HANGER
REDUCE DOWN TO 2" TO PANEL
TYPICAL OF 2 LOCATIONS
ROUTE NEW FEEDER THROUGH
EXISTING 1200 SWITCH GEAR TO
AVOID EXISTING OVERHEAD
OBSTRUCTION
150 KVA 480V-120/208
WALL MOUNTED TRANSFORMER
480V-120/208
208*400*1.732/1000 = 144KVA
EXPLOSION PROOF 3 PHASE 100 AMP
PANEL SHELTER H-11
ELECTRICAL SERVICE "B" TO SHELTER PANELS
UNDER PARKING APRON
SHELTER
DISCONNCT #1
SHELTER PANEL
EXTERIOR OF BUILDING
H
T
R
F
U
B
T
I
T
S
R
O
F
U
DATE
SHEET
DRAWN BY
OF
PROJECT NUMBER
DRAWING NUMBER
P R
O J E
T
L E
D R
A W
I N
G
S
H E
M
E
T H
U N
I T
A
T E
S
A
R
C
V
I L
E
N G
I N
E E
R
S
Q U
A D
R O
N
S E
Y M
O U
R
J O
H N
S O
N
A
R
S
E
N
O R
R
O L I N
A
P R
O J E
A
S E
C O
N T
R A
T A
D
D A
T E
D E
S C
R I P
T I O
N R
E V
1 2 3 4 5 6 7 8 9 10 11
A
B
C
D
E
F
G
7 8 9 10 111 2 3 4 5 6
H
A
B
C
D
E
F
G
H v:\PROJECTS\FY-18\vkag 18-1041\vkag 18-1041 as-built\VKAG 18-1041 E-4.dwg
15 FEB 2018
AS-SHOWN
CENME
VKAG 18-1041
C O
N S
T R
U C
T
S
E C
O N
D A
S
T R
I B
U T
I O
N
F
O R
A I R
C R
A F
T
S
H E
L T
E R
S
P
T R
E N
C H
I N
G
A
C
T B
A N
K
D
E T
A I L S
I L
T
F A
D
C
F A
F
W
A
D D
C
K E
R
M
A T
E R
I A
L
D
E T
A I L
10032
TRENCHING AND DIRECTIONAL
BORING NOTES:
1. THE CONTRACTOR SHALL PROTECT ALL EXISTING STRUCTURES
ENCOUNTERED IN HIS WORK. THE CONTRACTOR SHALL BE
RESPONSIBLE TO REPLACE ANY CURB AND GUTTER, SIDEWALK,
ASPHALT, ETC.. THAT IS DAMAGED BY HIS WORK, AT NO ADDITIONAL
COST TO THE GOVERNMENT AND TO THE SATISFACTION OF THE
CONTRACTING OFFICER.
2. THE SATISFACTORY FILL MATERIAL SHALL BE PLACED AND
COMPACTED IN 6" LIFTS TO 95% OF CE 26 MAXIMUM DENSITY.
PLACING AND COMPACTING OF THE SATISFACTORY FILL SHALL BEGIN
AS SOON AS THE CONCRETE IS FIRM ENOUGH TO ALLOW FOOT
TRAFFIC, WITHOUT DISPLACEMENT. SATISFACTORY FILL FOR THE
TRENCH UNDER THE ASPHALT SHALL BE SC, SP, SW, OR THE ABC
MATERIAL REMOVED DURING EXCAVATION.
3. AREAS OF DEMOLITION SHOWN ARE APPROXIMATE. CONTRACTOR
SHALL FIELD DETERMINE EXACT WIDTH AND QUANTITY OF
DEMOLITION REQUIRED.
4. THE CONTRACTOR SHALL MINIMIZE THE INCONVENIENCE TO THE
BASE PERSONNEL, DURING ALL CONSTRUCTION, THE CONTRACTOR
SHALL MAINTAIN TRAFFIC FLOW TO BASE PERSONNEL.
5. DIRECTIONAL BORING SHALL COMPLY WITH UFC 3-550-01 WITH
SPECIAL ATTENTION GIVEN TO PARAGRAPH 3-11.4 AND APPENDIX B.
UFC 3-550-01 REQUIRES A MINIMAL DIRECTIONAL BORING DEPTH OF
24 INCHES UNDER ASPHALT PAVEMENT AND NONPAVEMENT
COVERED AREAS FOR VOLTAGES UNDER 6OO VOLTS; HOWEVER,
MINIMAL DEPTH UNDER AIRFIELD PAVEMENTS SHALL BE 48" IAW
DETAILS 2 & 6 ON THIS DRAWING. CONTRACTOR IS RESPONSIBLE TO
DETERMINE APPROPRIATE DEPTH OF BORING REQUIRED TO AVOID
DAMAGING 10' X 3/4" TIEDOWN/GROUNDING RODS AND ALL OTHER
UNDERGROUND UTILITIES. (SEE CIVIL DRAWING C1)
6. CONCRETE SLABS TO BE REMOVED SHALL BE SAW CUT, FULL DEPTH
AROUND THE PERIMETER ADJACENT TO CONCRETE PAVEMENT AND 1
FOOT INSIDE OF THE ENTIRE PERIMETER ADJACENT TO CONCRETE
OR ASPHALT PAVEMENT. ALL DEBRIS SHALL BE REMOVED BY
CONTRACTOR AND DISPOSED OF OFF BASE. THE CONTRACTOR
SHALL EXERCISE EXTREME CAUTION TO INSURE NO DAMAGE
OCCURS TO SLABS OR ASPHALT PAVEMENT ADJACENT TO SLABS
BEING REPLACED.
7. WHERE SLABS ARE REMOVED, THE REMOVED SECTION SHOULD BE
RECTANGULAR WITH LENGTH ≤ (1.25 X WIDTH).
TYPICAL DUCTBANK SECTION
NOT TO SCALE
NOTE:
DEPTH MAY BE VARIED TO AVOID EXISTING UTILITIES
E4
ASPHALT/PAVEMENT CONDUIT TRANSITION
NOT TO SCALE
E4
TRANSITION FROM UNDER GROUND TO SHELTER
NOT TO SCALE
E4
REPAIR AIRFIELD CONCRETE PAVEMENTS (FULL DEPTH)
NOT TO SCALE
E4
FOREIGN OBJECT DEBRIS FENCE DETAIL
NOT TO SCALE
E4
JT SEALANT DETAIL (BACKER MATERIAL) FOR AIRFIELD PAVEMENT
NOT TO SCALE
E4
M
I N
NCDOT SF-9.5A SURFACE THICKNESS TO
MATCH EXISTING ASPHALT
COMPACTED FILL
EXISTING
EARTH
8" CONCRETE 3000 PSI
OVER TRENCH 12" PAST
TRENCH EACH SIDE
6" SCHEDULE 40 HDPE WHEN
CONCRETE ENCASED
3000 PSI
CONCRETE
BACKFILL
6" ALL SIDES
VARIES
EXISTING ASPHALT
MAGNETIC
MARKING
TAPE
6" MIN DIAMETER
HDPE - LESS THAN
1,000 V
CONCRETE ENCASED SCH 40 HDPE PER
NEC AND AFJMAN 32-1080 GUIDANCE
LISTED HDPE-PVC ELECTROFUSION TYPE
COUPLING USE APPROVED REAMING
MEANS TO REMOVE SHARP EDGES PRIOR
TO JOINING CONDUITS
NEW BEND
RADIUS NOT TO
EXCEED
MANUFACTURERS
RECOMMENDATION
AND 5%
OVALIZATION
48" MIN BELOW SURFACE OF PAVEMENT ALL
VOLTAGE CLASSES LESS THAN 34.5KV (NOMINAL)
HDPE CONDUIT
TRANSITION - LAYOVER
TO CONNECT TO PVC
EXTEND CONCRETE
ENCASEMENT
TO PAVEMENT EDGE OR
UNTIL HDPE
MIN DEPTH FROM GROUND
LEVEL IS ACHIEVED
ASPHALT THICKNESS TO
MATCH EXISTING
TO HANDHOLE
ASPHALT
PAVEMENT
TO SHELTER
AIRFIELD PAVEMENT COVERED AREA
TRANSITION TO
AIRFIELD PAVEMENT
15"-18"
AIRFIELD PAVEMENT
THICKNESS
6" SCH 80 HDPE CONDUIT APPROVED/LISTED
FOR DIRECTIONAL BORING
PAINT & OIL
DRILL & EPOXY
DEFORMED TIE BARS
DOWEL IF JOINT WAS ORIGINALLY
DOWELED OR IF REPAIR IS 1/3 OR
MORE OF SLAB WIDTH
DRILL & EPOXY
NEW CONCRETE
650 PSI
FLEXURAL
CONCRETE
(15"-18" THICK)
RE-ESTABLISH LONGITUDINAL
JOINT DOWELS
REFERENCE:
TM 5-822-9/AFM 88-6, CHAPTER 10, REPAIR OF RIGID
PAVEMENTS USING EPOXY RESIN GROUTS, MORTARS
AND CONCRETE
TM 5-822-9/AFM 88-6, CHAPTER 3, RIGID PAVEMENTS
FOR AIRFIELD DATED AUGUST 1988 FOR DOWEL AND
TIE BAR SIZE AND SPACING
ACI 503R-80, "USE OF EPOXY COMPOUNDS WITH
CONCRETE" FOR GUIDANCE ON BONDING
UNHARDENED CONCRETE TO HARDENED CONCRETE.
15"-18"
AIRFIELD PAVEMENT
THICKNESS
R 48"
90°
6" GALVANIZED RMC
HDPE TO RMC
6" GALVANIZED RMC, 90°
SWEEP, RADIUS (R) = 48"
6" SCH 80 HDPE CONDUIT APPROVED/CERTIFIED
FOR DIRECTIONAL BORING
48" MIN ALL
VOLTAGES
CONDUIT
SEAL
INSTALL 6" TO 3" EXPLOSION
PROOF REDUCER
WARNING LIGHT (LOCATE 16' 0C)
TO CONSTRUCTION
FENCE SUPPORTS
2"X4"
(PRESSURE TREATED)
MAINTENANCE AND REPAIR OF THE FOD FENCE AND FLASHING LIGHTS SHALL BE BY THE
CONTRACTOR ON A CONTINUAL BASIS AND SHALL BE TO THE SATISFACTION AND EXTENT
AS DIRECTED BY THE CONTRACTING OFFICER. CONTRACTOR SHALL CONSTRUCT AND
SECURE FOD FENCE FABRIC AND FRAMES TO WITHSTAND 35 TO 45 MPH GUSTS OF
NOTE:
ENGINE BLAST. EACH SECTION OF FENCE SHALL BE SECURED TO ADJACENT SECTIONS.
2"x4" 12GA. WWF
COVERED WITH BURLAP
MESH, STAPLED
4' O.C.
CMU (AS REQUIRED)
BATTERY OPERATED FLASHING
CMU (AS REQUIRED)
W
D
T
AIRFIELD PAVEMENT
SURFACE
POURED JOINT SEALER
BACKER
MATERIAL
JOINT BOTTOM
INITIAL SAWCUT
OR INSERT
W = WIDTH OF SEALANT RESERVOIR (SEE TABLE)
D = DEPTH OF SEALANT (1.0 TO 1.5 X W)
T = DEPTH OF INITIAL SAWCUT
a. 1/4 SLAB THICKNESS FOR PAVEMENTS LESS THAN 12 INCHES
b. 3 INCHES FOR PAVEMENTS 12-18 INCHES
c. 1/8 SLAB THICKNESS FOR PAVEMENTS MORE THAN 18 INCHES
*DESIGNER MAY WANT TO CONSIDER REQUIRING 1/4 SLAB THICKNESS
TABLE
JOINT SPACING
FT
WIDTH. IN.
MIN MAX
< 25 1/2 5/8
25-50 1/4 7/8
>50 1.0 1-1/8
NOTES:
1. SEPARATING TAPE OR NONABSORBENT TAPE REQUIRED TO PREVENT JOINT SEALANT FROM
FLOWING INTO SAWCUT, TO SEPARATE NON-COMPATABLE MATERIALS AND TO PREVENT JOINT
SEALANTS FROM BONDING TO BOTTOM OF RESERVOIR.
2. TOP OF SEALANT WILL BE 1/8-IN. TO 1/4-IN. BELOW TOP OF PAVEMENT.
3. COMPRESSION SEAL MUST BE IN COMPRESSION AT ALL TIMES.
REFERENCE: TM5-825-3/AFM 88-8, CHAPTER 3, RIGID PAVEMENTS FOR AIRFIELDS.
H
T
R
F
U
B
T
I
T
S
R
O
F
U
DATE
SHEET
DRAWN BY
OF
PROJECT NUMBER
DRAWING NUMBER
P R
O J E
T
L E
D R
A W
I N
G
S
H E
M
E
T H
U N
I T
A
T E
S
A
R
C
V
I L
E
N G
I N
E E
R
S
Q U
A D
R O
N
S E
Y M
O U
R
J O
H N
S O
N
A
R
S
E
N
O R
R
O L I N
A
P R
O J E
A
S E
C O
N T
R A
T A
D
D A
T E
D E
S C
R I P
T I O
N R
E V
1 2 3 4 5 6 7 8 9 10 11
A
B
C
D
E
F
G
7 8 9 10 111 2 3 4 5 6
H
A
B
C
D
E
F
G
H v:\PROJECTS\FY-18\vkag 18-1041\vkag 18-1041 as-built\VKAG 18-1041 E-5.dwg
15 FEB 2018
AS-SHOWN
CENME
VKAG 18-1041
C O
N S
T R
U C
T
S
E C
O N
D A
S
T R
I B
U T
I O
N
F
O R
A I R
C R
A F
T
S
H E
L T
E R
S
P
E Q
U I P
M E
M
U
N T
I N
G
D
E T
A I L S
I L
T
F A
D
C
F A
F
10032
PANEL #2 SCHEDULE
NOT TO SCALE
E5
SHELTER CONDUIT RUN DETAIL
NOT TO SCALE
E5
EQUIPMENT CONFIGURATION ON COLUMN
NOT TO SCALE
E5
TYPICAL SHELTER EQUIPMENT LAYOUT DETAIL
NOT TO SCALE
E5
PANEL #1 SCHEDULE
NOT TO SCALE
E5
PANEL
TERMINAL
HOUSING W/
REMOVABLE
GLAND PLATES
NEW BRANCH PANELS SHALL
BE CONFIGURED WITH MAN
POWER FEED FROM BOTTOM
AND BRANCH CIRCUITS
EXITING FROM TOP
100A
208Y/120V
3-PHASE
BRANCH
PANEL
WP/EP
CONDUIT FILL SHALL BE IAW
NEC. ALL CONDUIT SHALL BE
THREADED NTP IMC UNLESS
OTHERWISE NOTED. PROVIDE
CONDUIT SEALS AS REQUIRED
FOR CLASS I, DIV 2 (ABOVE
RAMP) AND CLASS I, DIV 1
(UNDER SHELTER PAVEMENT).
INSTALL CONDUIT HUBS
IAW MANUFACTURES
RECOMMENDATION
CONDUIT
SEAL
LIGHTING BRANCH CKTS
CONV. RECEPTACLE BRANCH CKTS
GALVANIZED "STRUT"
METAL FRAMING
SYSTEM TO SUPPORT
EQUIPMENT
4 IN. SQUARE HOLLOW
GALVANIZED STEEL END
POSTS WITH FLANGED
BASE AND CLOSED TOP
E3
E4
100 A
DIS-
CONNECT
WP/EP
ANCHOR TO AIRFIELD
PAVEMENT
EXISTING AIRCRAFT RATED
PAVEMENT 15-18 INCHES
GALVANIZED
RMC
ONE(1)-20A, TWO POLE, 120-277V
EXPLOSION PROOF/WP SNAP
SWITCH PER SHELTER (APPLETON
CONTENDER SERIES FACTORY
SEALED TUMBLER SWITCH
EDS318 OR EQUAL)
EIGHT(8)-150 WATT
EXPLOSION
PROOF/WP LED
FLOODLIGHTS W/
MOUNTING
HARDWARE PER
SHELTER
TWO(2)-20A, 125V
TWO GANG
EXPLOSION-PROOF/WP
RECEPTACLES PER
SHELTER
[CROUSE-HINDS ENR
32201 OR EQUAL
AND MATING PLUG
ENR 32201 OR EQUAL]
NOTE: DEMOLISH
ALL EXISTING
PANEL BOARDS,
LIGHTS, CONV
RECEPTACLES AND
LIGHT SWITCHES.
JUNCTION BOX
BRANCH PANEL &
DISCONNECT
PANEL #1 IN SHELTER(10743/H-11) SERVING SHELTERS 10740 - 10746 NEW WORK
CKT
LOAD
KVA
DESCRIPTION PH N G CB A B C CB PH N G DESCRIPTION
LOAD
KVA
CKT
1 .59
H-12 LIGHTS #10 #10 #12 20
5.77
20 #10 #10 #12 H-9 LIGHTS
.59 2
3 .59 5.77 .59 4
5 .59
H-11 LIGHTS #12 #12 #12 20
5.77
20 #8 #8 #10 H-8 LIGHTS
.59 6
7 .59 5.77 .59 8
9 .59
H-10 LIGHTS #10 #10 #12 20
5.77
20 #10 #10 #12 H-13 LIGHTS
.59 10
11 .59 5.77 .59 12
13 .59
H-14 LIGHTS #8 #8 #10 20
5.88 20 #12 #12 #12 H-10 RECEPTS .36 14
15 .59 5.88 20 #12 #12 #12 H-11 RECEPTS .36 16
17 .36 H-9 RECEPTS #10 #10 #12 20 6 20 #10 #10 #12 H-14 RECEPTS .36 18
19 .36 H-12 RECEPTS #10 #10 #12 20 6 20 #10 #10 #12 H-13 RECEPTS .36 20
21 0 SPARE 20 3 20 #10 #10 #12 H-8 RECEPTS .36 22
PNL #1
208Y/120V
MAINS:
10,000
MLO
AIC
3 PHASE 4 WIRE
100 AMP MAX
LOAD TYPE
( R ) CONV REC
( L ) LIGHTING
CONNECTED
21 100%
40.39 125%
DEMAND
61.39 125%TOTAL
MULTI-BLDG FACTOR 70% 50.04
21 MOUNT: SURFACE
50.49 NEMA: WP, CLASS 1 DIV 2 EXPLOSIONPROOF
71.49 MAN/MODEL# COOPER CROUSE-HINDS D2LCS342G OR EQUAL
PHASE A
PHASE B
PHASE C
PANEL TOTALS
4.03 KVA
3.67 KVA
3.08 KVA
23.42 AMPS
20.42 AMPS
17.54 AMPS
0 FED FROM: NEW PANEL BLDG 4538
PANEL #2 IN SHELTER(10723/I-11) SERVING SHELTERS 10721 - 10726 NEW WORK
CKT
LOAD
KVA
DESCRIPTION PH N G CB A B C CB PH N G DESCRIPTION
LOAD
KVA
CKT
1 .59
I-12 LIGHTS #10 #10 #12
20 5.77 20
#10 #10 #12 I-9 LIGHTS
.59 2
3 .59 20 5.77 20 .59 4
5 .59
I-11 LIGHTS #12 #12 #12
20 5.77 20
#8 #8 #10 I-8 LIGHTS
.59 6
7 .59 20 5.77 20 .59 8
9 .59
I-10 LIGHTS #10 #10 #12
20 5.77 20
#8 #8 #10 I-13 LIGHTS
.59 10
11 .59 20 5.77 20 .59 12
13 0 SPARE 20 3 20 #12 #12 #12 I-10 RECEPTS .36 14
15 0 SPARE 20 3 20 #12 #12 #12 I-11 RECEPTS .36 16
17 0.36 I-9 RECEPTS #10 #10 #12 20 3 20 SPARE 0 18
19 0.36 I-12 RECEPTS #10 #10 #12 20 6 20 #10 #10 #12 I-13 RECEPTS .36 20
21 0 SPARE 20 3 20 #10 #10 #12 I-8 RECEPTS .36 22
PNL #2
208Y/120V
MAINS:
10,000
MLO
AIC
3 PHASE 4 WIRE
100 AMP MAX
LOAD TYPE
( R ) CONV REC
( L ) LIGHTING
CONNECTED
18 100%
34.62 125%
DEMAND
52.62 125%TOTAL
MULTI-BLDG FACTOR 70% 42.89
18 MOUNT: SURFACE
43.28 NEMA: WP, CLASS 1 DIV 2 EXPLOSIONPROOF
61.28 MAN/MODEL# COOPER CROUSE-HINDS D2LCS342G OR EQUAL
PHASE A
PHASE B
PHASE C
PANEL TOTALS
3.44 KVA
3.08 KVA
2.72 KVA
20.54 AMPS
17.54 AMPS
14.54 AMPS
FED FROM: NEW PANEL BLDG 4538
JUNCTION BOX
TO/FROM ADJACENT
SUN SHELTER OR
DISTRIBUTION PANEL
(IF NECESSARY)
JUNCTION BOX
BRANCH PANELS
& DISCONNECTS
(AS NECESSARY)
TO/FROM ADJACENT SUN SHELTER OR
DISTRIBUTION PANEL (IF NECESSARY)
FOR UNDERGROUND
CONNECTION FROM
TRANSFORMER
(AS NECESSARY)
File details come from the government source that posted it. Updated .