This is a Statement of Work (SOW) for interior wall painting services at a federal facility (16 TRS, Building 45) with a 14-day period of performance.
The contractor must paint 3,321 square feet of interior hallway walls from red to white. Required tasks include site preparation with protective coverings for floors, fixtures, molding, and furniture; surface preparation involving cleaning, patching minor imperfections, sanding, and application of high-hide primer to prevent red paint bleed-through; paint application to achieve full uniform coverage; site cleanup and debris removal; and a joint final inspection with the facility manager. The final white finish must visually match the color, sheen, and texture of adjacent white hallway walls with a continuous, opaque finish showing zero visibility of underlying red paint or primer layers. All work must be contained to designated hallway areas without damage to non-targeted surfaces such as ceilings, baseboards, or doors.
Pricing must be submitted as a firm-fixed-price bid including all labor, materials (primer, paint, tape, drop cloths), equipment, and cleanup costs. Material specifications require commercial-grade primer and paint, with high-hide primer highly recommended for the red-to-white transition. Work must be scheduled and phased to minimize disruption to normal daily operations and hallway foot traffic. The contractor must adhere to OSHA safety regulations for indoor painting, including proper ventilation and safe material storage, and handle all disposed materials according to local environmental regulations.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| walls 5.jpg | JPG image | |
| walls 8.jpg | JPG image | |
| walls 4.jpg | JPG image | |
| walls 9.jpg | JPG image | |
| walls 1.jpg | JPG image | |
| walls 11.jpg | JPG image | |
| walls 2.jpg | JPG image | |
| walls 3.jpg | JPG image | |
| walls 6.jpg | JPG image | |
| walls 7.jpg | JPG image | |
| walls 10.jpg | JPG image | |
| WD 15-5455 rev. 32.pdf | ||
| Solicitation - FA480126Q0038.pdf | ||
| 1449 - FA480126Q0038.pdf |
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK
16TRS Wall Paint
14 Days PoP
1. 16 TRS needs the current red walls in building 45 to be painted to white.
Required Tasks
The contractor shall perform the following tasks:
• Site Preparation: Protect all floors, fixtures, molding, and nearby furniture from paint splatter, dust, and debris.
• Surface Preparation: Clean and prep the 3,321 square feet of designated red wall surfaces. This includes patching minor imperfections, sanding where necessary, and applying appropriate primer to ensure the current red color does not bleed through the final white finish.
• Paint Application: Apply white paint to the designated walls to achieve full, uniform coverage.
• Site Cleanup: Remove all painting materials, protective coverings, and debris from the premises. Restore the work area to its original operational condition.
• Final Inspection: Conduct a joint walk-through with the facility manager to ensure full coverage, color match, and area cleanliness.
2. Specific Requirements (What Needs to Be Done)
• The contractor must transform 3,321 square feet of interior hallway walls from red to white.
• The final white finish must visually match the color, sheen, and texture of the adjacent white hallway walls.
• The application must result in a continuous, opaque finish with zero visibility of the underlying red paint or primer layers.
• All work must be contained to the designated hallway areas without causing damage or altering non-targeted surfaces (e.g., ceilings, baseboards, doors).
3. Relevant Information for Pricing Determination
Vendors proposing a bid should consider the following parameters when calculating their final pricing:
Category Details
Total Area 3,321 square feet of wall space.
Inclusions Bids must be firm-fixed-price and include all costs for labor, materials (primer, paint, tape, drop cloths), equipment, and clean-up.
Material Specifications
Primer and paint must be commercial grade. A high-hide primer is highly recommended due to the transition from red to white.
Special Conditions
Work must be scheduled and phased to minimize disruption to normal daily operations and foot traffic in the hallways.
Regulations & Safety
The contractor must adhere to standard OSHA safety regulations regarding indoor painting, including proper ventilation and safe storage of materials while on site.
All disposed materials must be handled according to local environmental regulations.