SOW 23-9004 Demolish Fire Training Bldg Facility 1345.pdf
PDF 1 MB Posted
- Attached to
- Facility 1345 Demo
- Solicitation number
- FA480027S0010
About this file
This is a Statement of Work (SOW) for demolition services at Joint Base Langley-Eustis (JBLE) in Virginia. The contractor shall demolish Fire Training Building, Facility 1345 and perform site restoration within a 60-day period of performance (30 days for demolition and disposal, 30 days for seeding and grass establishment). Project number is MUHJ 23-9004, with a document date of 29 April 2026.
The scope requires complete demolition of the disused fire training building including foundation, footings, roofing, ceilings, walls, HVAC systems, concrete slab, and underground utilities, leaving a clean site. The contractor must disconnect all utilities at the point of entry without disrupting service to adjacent buildings, refill ruts and holes with suitable fill, grade and reseed the area, and protect adjoining property and roadways from damage. The contractor shall submit written notification to the Contracting Officer seven days prior to work commencement, identifying building number, demolition designation, commencement and completion dates, work hours, expected noise and vibration levels, utility interruptions, and contractor representative contact information. All demolition waste and debris must be diverted from landfills; concrete and asphalt must be recycled; all other non-recyclable materials must be legally disposed off-base with dump receipts provided. Within 10 days of final inspection, the contractor shall submit AutoCAD as-built record drawings on computer disc and 24" x 36" paper copies showing utility locations, grade and elevation changes, and all design modifications, along with a completed DD Form 1354 (Transfer and Acceptance of Military Real Property). Performance thresholds require zero environmental compliance discrepancies and no more than two valid customer complaints for demolition work, utilities notification, site restoration, and submittal compliance. Normal work hours are Monday through Friday, 7:30 a.m. to 4:30 p.m., including weekends and federal holidays with Contracting Officer approval. The contractor must secure the job site with a temporary 6-foot high chain link fence with brown UV-resistant netting, provide chemical sanitary toilets serviced regularly and subject to Base Medical Officer inspection, and submit numbered submittals on AF Form 3000 with Quality Control certification.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Sources Sought Facility 1345 Demo.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Draf t
Solicitation Attachment 3
STATEMENT OF WORK
FOR
DEMOLITION SERVICES
Demolish Fire Training Building, Facility 1345
PROJECT MUHJ 23-9004
JBLE-LANGLEY, VA
29 April 2026
Solicitation Attachment 3
STATEMENT OF WORK (SOW)
FOR
DEMOLITION SERVICES
1. DESCRIPTION OF SERVICE. The Contractor shall furnish all personnel, vehicles and equipment required to perform Contractor services to demolish a Fire Training Build-ing, Facility 1345 at JBLE-Langley, Virginia. All work shall be performed in accordance with attached drawings, specifications, and all applicable laws, regulations, standards and commercial practices as described in the statement of work with the focus on safety and customer service. The period of performance is 60 days, (30 days for demolition and dis-posal the structure and 30 days for seeding and grass establishment). The Contractor is encouraged and expected to use innovative approaches to accomplish SOW requirements efficiently and effectively in a timely manner at reduced costs, and in a way, which fosters pride and ownership in the work performed.
1.1. SCOPE OF WORK.
The work under this project consists of demolishing a disused fire training building, Facil-ity 1345 located at JBLE-Langley, VA. Demolish all appurtenances including (but not limited to) foundation, footings, roofing, ceilings, walls, HVAC, concrete slab, and under-ground utilities leaving a clean site.
The scope of work includes all required labor, equipment and material associated with the demolition of one facility. The following is a list of principal items:
Ensure all utilities are disconnected at the point of entry for the facility. Disconnect and cap any underground water, sewage electrical and Communication to the building. Dis-connect electrical service from the closest electrical device serving the facility. Contractor shall ensure demolition of all utilities will not disturb service to adjacent buildings to re-main.
Upon completion of demolition, contractor shall refill ruts and other holes created by dem-olition with suitable fill, then grade and reseed appropriately in accordance with 32 92 19 Seeding.
Adjoining property, roadways, parking areas, sidewalks and other adjacent items shall be completely protected from damage during demolition activities.
All work shall be accomplished in accordance with specifications 01 11 00 Special Condi-tions, 01 12 00 Environmental Management Special Conditions and 02 41 00 Demolition and Deconstruction, 32 92 19 Seeding, drawings, and terms and conditions of the contract.
See Appendix A, B and C.
1.1.1. Demolition Notification. The Contractor shall provide written notification to the Contracting Officer seven days prior to commencement of work identifying the following:
Solicitation Attachment 3
a. Building number
b. Demolition designation
c. Commencement date
d. Work hours, expected noise and vibration levels
e. Utility interruptions (dates and hours)
f. Demolition completion date
g. Contractor’s representative’s name and phone number for contract issues.
1.1.2. Demolition Debris. The Contractor shall use all reasonable means to divert demo-lition and demolition waste from landfills and incinerators and to facilitate their recycling or reuse. Revenues or other savings obtained from salvaging or recycling shall accrue to the Contractor. The recycle materials shall be submitted to the Contracting Officer at con-tract closeout. All demolished materials that cannot be recycled shall be legally disposed of off base. All concrete and asphalt shall be recycled. All dump receipts shall be provided to the Contracting Officer.
1.1.3. Drawings, Manuals and Checklists. The Contractor shall provide within 10 days of final inspection, an AutoCAD version of as-built record drawings on computer disc and one 24” x 36” paper copies of as-built record drawings. The drawings shall at a minimum provide utility locations, correct grade and elevation if changed, and all changes or modi-fications from the original design drawings. Ten days prior to final inspection, the Con-tractor shall complete a DD Form 1354, Transfer and Acceptance of Military Real Property for each building (see Appendix A).
2. SERVICE DELIVERY SUMMARY. The Service Delivery Summary (SDS) captures the service requirements that can be measured and are considered to be critical operational requirements. The SDS includes Performance Objectives that describe the desired end result or outcome the Contractor shall achieve. The Performance Thresholds state the min-imum acceptable level of performance in terms of quality, timeliness and quantity in real-istic and achievable standards. These thresholds are critical to mission success. The SOW paragraphs reference the details of the Performance Objective in the SOW. Each require-ment includes a government-determined performance objective. (Note that the Perfor-mance Objective is merely a reference point for government personnel and does not relieve the Contractor of any other contractual requirements.)
2.1. SERVICE DELIVERY SUMMARY
PERFORMANCE OBJECTIVE PERFORMANCE THRESHOLD
Environmental Compliance: Comply with all federal, state, local, and JBLE-Langley, VA Environmental Laws, Regulations, Instructions and Publications and the National Emis-sion Standards for Hazardous Air
The Contractor’s performance shall be deter-mined ACCEPTABLE when the number of discrepancies does not exceed 0 in any envi-ronmental compliance requirement.
Solicitation Attachment 3
Pollutants (NESHAP) and attached Specifications Sections
Demolish Building 1345 in accord-ance with the SoW and standard com-mercial practices
The Contractor’s performance shall be AC- CEPTABLE when service does not exceed 2 valid customer complaints.
Utilities. Provide notification of any disruption of service
The Contractor’s performance shall be deter-mined ACCEPTABLE when service does not exceed 2 valid customer complaints.
Perform site restoration in accordance with attached this SOW.
The Contractor’s performance shall be deter-mined ACCEPTABLE when service does not exceed 2 valid customer complaints.
Submit plans, reports, and submittals as indicated in the SOW.
The Contractor’s performance shall be deter-mined ACCEPTABLE when service does not exceed 2 valid customer complaints.
3. GOVERNMENT-FURNISHED FACILITIES/SERVICES. The government may provide water and electricity. The connection costs to fire hydrants and electrical sources are the Contractor’s responsibility. State approved double backflow preventers shall be used for hydrant connections.
4. GENERAL INFORMATION
4.1. Normal Hours of Operation. Normal hours of operation are Monday through Friday, 7:30 am to 4:30 pm including weekends and federal holidays. Hours other than specified require approval from the Contracting Officer and will be negotiated on a case-by-case basis.
4.2. Work Site. The Contractor must ensure that the job site and equipment is secured at the end of the workday. The construction site and equipment shall be contained within a temporary 6’ high chain link fence with brown UV resistant “tennis” netting.
4.3. Sanitary Facilities. The Contractor shall provide chemical sanitary toilets at the work site. The chemical toilets must be serviced regularly and will be subject to government inspection by the Base Medical Officer. All sanitary deficiencies shall be corrected within 24 hours after notification.
4.4. Submittals. The Contractor shall provide to the Contracting Officer submittals iden-tified on the Submittal Register (see Appendix A). Number submittals sequentially (1, 2, 3, 4, etc.). Re-submittals shall retain the original number in addition to an alpha suffix (1A, 1B, 1C, etc.). The Contractor shall review, update and resubmit the submittal register at least every 30 days to reflect additions and changes.
4.4.1. Coordinate preparation and processing of submittals with the performance time of the contract. Transmit each submittal sufficiently in advance to ensure completion within
Solicitation Attachment 3 the stated performance time. Allow sufficient review time so that installation will not be delayed because of the time required to process submittals, including time for resubmittals.
4.4.2. Allow two weeks for initial review. Allow additional time if processing must be delayed permitting coordination with subsequent submittals. The Government will promptly advise the Contractor when a submittal being processed must be delayed for co-ordination.
4.4.3. No extension of Contract Time will be authorized because of failure to transmit submittals to the Government sufficiently in advance of the Work to permit processing.
4.4.4. Prior to submittal, each respective line item on every transmittal form (AF Form 3000) shall be reviewed, signed and dated by the Contractor’s Quality Control (CQC) representative certifying that the accompanying submittal complies with the contract requirements. Include the following information:
a. Name of Contractor
b. Submittal Number
c. Line Item Number
d. Action Taken
e. Date of Review
f. CQC Representative Signature
4.4.5. All submittals shall include one completed AF Form 3000 and four copies of all attachments. Two completed copies of the AF Form 3000 with attachments will be re-turned to the Contractor for action.
5. APPENDICES.
Appendix A - Publications, Instructions and Forms Appendix B – Drawings
a. Project Location
b. Facility 1345 Exterior Pictures
Appendix C – Specifications
a. 01 11 00 Special Conditions
b. 01 12 00 Environmental Management Special Conditions
c. 02 41 00 Demolition and Deconstruction,
d. 32 93 29 Seeding
Solicitation
APPENDIX A
Publications and Forms
PUBLICATIONS
Title Date Corp of Engineers Manual, EM 385-1-1
Safety and Health Requirements Current Edition
JBLE-Langley Hazardous Waste Management Plan
December 2003
FORMS
Department of Defense (DD) Form 1354, Transfer and Acceptance of Military Real Property
JBLE-Langley Submittal Register AF Form 103, Base Civil Engineering Work Clearance Request
Solicitation Attachment 3
APPENDIX B
Project Location
Facility 1345; SITE LOCATION in North Base
Facility 1345; SITE VIEW
Solicitation
Facility 1345; FRONT VIEW
| STATEMENT OF WORK |
| FOR |
| DEMOLITION SERVICES |
| Demolish Fire Training Building, Facility 1345 |
| PROJECT MUHJ 23-9004 |
| JBLE-LANGLEY, VA |
| for |
| DEMOLITION SERVICES |
| PERFORMANCE THRESHOLD |
| PUBLICATIONS |
| FORMS |
PERFORMANCE OBJECTIVE
File details come from the government source that posted it. Updated .