FA466125R0012

B3705 SNYDER RANGE QUESTIONS AND ANSWERS

1. We would like to know if this is a brand-new contract OR if there is (was) an incumbent performing these services. If not brand new, could you please provide the current / previous contract number?

A: This is a brand-new contract.

2. Can you provide the floor plan of building 3705?

A: See Amendment 01 Attachments.

3. Should Vendor / Contractor need to provide a separate alternative price for removal of all asbestos containing flooring?

A: This facility was constructed in 2002 and does not require asbestos testing.

4. If yes, should Vendor / Contractor provide separate line-item price with Bid?

A: N/A

5. The areas shown during the walk total approximately 2,300sq ft. The solicitation states remove 2,945 but install 3,945. Reason for this difference?

A: This is an error, both numbers should be 2,945.

6. Also, are there areas that were unseen that are included? Are the areas highlighted in yellow and marked by an X included below the only areas to be addressed for flooring?

A: The drawing is correct.

7. In Section 1.6.2.1 it states "Reinstall baseboards (mentioned in section 1.6.1.3)” In the scope of work, there is not a Section 1.6.1.3 and we were not shown an area where baseboards need to be reinstalled. Is the expectation to install baseboard in some areas, or is it all just cove base in the affected areas?

A: SOW error, Section 1.6.2.1 has been updated.

8. What is under the carpet?

A: Glue

9. Are there any media restrictions for the sandblasting portion?

A: When sandblasting Contractor must take precaution of damaging Government property.

10. Are the handrails to be included in the painting portion?

A: No

11. Will exterior appliances be moved or removed before sandblasting? (example: cameras, coax, signage)

A: The Government will not remove any appliances

12. Do the areas on the exterior to be painted only include siding and trim around windows?

A: Contract must re-paint all sandblasted exterior portions to include wall panels, window trim, door trim, flashing, screw heads, bolt heads, rivet heads, doors. To exclude the facia, soffits and roof panels.

13. In section 1.6.2.3. it states “The Contractor shall paint the exterior metal siding using zinc oil-based paint. 5,100 square feet. Paint shall match existing color.” If a more suitable solution is found, is it possible to use that option?

A: Color is Butler Birch White Or Equal.

14. If positive results are found, will abatement be handled as a contract modification with additional funding, or by Dyess AFB directly with a temporary shutdown until eradicated?

A: This facility was constructed in 2002 and does not require any testing.

15. Does the government anticipate asbestos being present, or is this included as a contingency only?

A: This facility was constructed in 2002 and does not require any testing.

16. Please confirm whether the following items are included in the painting scope:

Gutters Soffit Handrails Cement fiber–framed garage doors at the rear of the building HVAC units/protrusions from the building

A: No Gutters, soffit, handrails, Cement Fiber, HVAC.

17. Who is responsible for moving furniture in preparation for carpet removal?

A: End User.

18. Is the new flooring to be installed over the existing VCT in areas where the , VCT exists or will the VCT need to be removed before the laminate is installed?

A: Flooring is only being installed where carpet is being removed.

19. Could you please provide specific product details for the “Dyess Standard Brown (12mm) LVT” (manufacturer, style, color code).

A: Boulevard 0800 Aspen or Equal.

20. Can you provide the specific color and manufacturer of the cove base?

A: Armstrong 102 mm (4”) High Rubber cove Base; 79 Sandstone or equal

21. Will the walk-off mats in the building entrances be removed completely and covered with new flooring, replaced or worked around?

A: Flooring is only being installed where carpet is being removed.

22. Is there a schedule of work available for this project?

A: See Amendment 01

23. Please clarify if sandblasting is required on all exterior metal siding, or only on an as-needed basis where foreign debris or heavy corrosion is present.

A: The exterior of the building is to be resealed and painted. Appropriate industry standards for surface painting preparation are required.

24. Our concern is that full sandblasting of all siding may not be necessary and could damage the existing metal surfaces. Is alternate cleaning/preparation methods (such as power washing and spot sanding/grinding) acceptable in areas where sandblasting is not necessary to properly prepare the surfaces to be painted?

A: Utilize industry standards as appropriate.

25. Par. 1.6.1.1 states 2,945 sf of carpet and adhesive shall be removed. Par. 1.6.2.1.1 states that 3,945 sf of new LVT shall be installed. Please verify this is just a typographical error and the approx. quantity of new LVT is 2,945 sf.

A: 2945 is correct.

26. Will the Govt. issue a change order for the asbestos abatement?

A: There is no asbestos.

27. Par. 1.6.2.1 states that the Contractor shall “reinstall baseboards throughout the notated portions of the facility…”. Par. 1.5.1, Demolition and Removal, does not mention removal of any baseboards. Does the Govt. wish to install new baseboards, or is this reference to baseboards a typographical error?

A: If baseboards need to be removed to demo carpet, they are to be reinstalled.

28. What type of subfloor is under the existing carpet? Is it concrete, tile, or both?

A: Foundation Is Concrete with tile on top. Not for entire Area.

29. Does the Govt. require the Contractor to remove ALL paint from the building exterior prior to pressure wash? Please verify the Govt. wishes the new paint to be applied to the bare metal siding.

A: Utilize industry standards as appropriate

Are there any Quality Control Manager requirements for this project?

A: Yes.

30. Are there any Site Safety Health Officer requirements for this project?

A: Yes.

31. Will daily reports, or QC reports be required on a daily basis?

A: No.

32. Is certified payroll required for this project?

A: Yes.

33. Will monthly progress billings be allowed for this project?

A: Yes.

34. Other than having a Superintendent onsite at all times, are there any other Superintendent requirements?

A: No.

35. Is a bid bond required to be submitted with our proposal, or will it only be required of the apparent technically acceptable low bidder? If so, for what value?

A: Not Required.

36. What sheen/finish is required for D?

A: Semi-Gloss.

37. Am I permitted to pressure wash the building before painting?

A: Please Utilize appropriate industry standards for proper paint application.