This document is a Questions and Answers file for Building 9118 Demolition at Dyess Air Force Base. The Q&A covers 18 detailed questions about the demolition project, including specific requirements for transformer removal, utilities disconnection, site preparation, and disposal of demolition materials. Key details include: the contractor must remove the transformer and install a junction box, cut and cap plumbing and gas lines at exterior valves, demolish the concrete driveway to the street curb, and remove both parameter and exterior piers. The contractor is responsible for obtaining their own subcontractors, bringing topsoil, and disposing of demolished materials off-base, with specific instructions to refer to environmental specifications for dumping requirements. Access to the base requires proper clearance, and only the building's door is bullet-resistant, not the walls.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Photos of Building.pdf | ||
| Solicitation Amendment FA466125R00040001 SF 30.pdf | ||
| Drawings.pdf | ||
| Solicitation - FA466125R0004.pdf | ||
| Wage Determination.pdf | ||
| Statement of Work Redacted.pdf | ||
| Provisions 1.pdf | ||
| Progress Schedule Draft.xlsx | XLSX spreadsheet |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Building 9118 Demolition Questions and Answers
1. Can photos be provided of the interior and exterior of the building?
a. Answer: Yes, please see photos attachment.
2. Does the Contractor need to remove the transformer and its cabling?
a. Answer: Contractor shall remove the transformer, leave the existing cabling intact, and install a junction box.
3. Can photos be provided of the transformer?
a. Answer: Due to its location, photos of the transformer could not be provided.
4. Can a list of plumbers/electricians that Dyess uses be provided to work on this requirement?
a. Answer: All Contractors are expected to provide their own subcontractors.
5. How does electricity get to the building?
a. Answer: Electricity comes through the north side of the building from the transformer
6. Does the Contractor need to bring their own topsoil?
a. Answer: Yes, please refer to the specifications which topsoil to use and how much.
7. Will the demolished material be dumped somewhere specific? Or is the contractor responsible for finding a way to dispose of the material?
a. Answer: Contractor is responsible for finding a way to dispose the material off base.
8. Does the Contractor need to remove the underground conduit to the transformer?
a. Answer: No
9. Is the Government saving anything from the demolition? For example, there are light bulbs in the supply closet, grills in the garage, etc.
a. Answer: Anything that is within the building is being saved by the government. Anything that is left at the beginning of the demolition phase is the contractor’s responsibility.
10. Will the comm equipment be removed before the demolition begins?
a. Answer: Comm Squadron will be notified about the equipment.
11. How far does the plumbing need to be removed to?
a. Answer: Plumbing service shall be cut and capped from outside water valve.
12. Does the Contractor need to remove just the parameter piers? Or do they need to remove the interior piers as well?
a. Answer: Contractor shall remove the parameter and exterior piers
13. What are the dumping requirements?
a. Answer: Please refer to the Environmental Specifications for dumping details and requirements.
14. Does the concrete driveway need to be demolished?
a. Answer: Yes, per the drawings the driveway shall be demolished to the curb of the street.
15. Can someone come in MUNS facility for dumping?
a. Answer: No, that someone needs proper clearance to have access onto base and must check-in at the MUNS gate to have an escort to the facility.
16. Are there armor/bullet-proof walls on the building?
a. Answer: No, only the door is bullet resistant.
17. What are the exact dimensions of the foundation that need to be demolished?
a. Answer: Please refer to the given as-builts for any dimensions.
18. Does the Contractor need to tie the gas line to a different location? Or should it be capped off?
a. Answer: Gas line needs to be cut and capped at the gas valve outside.