Attachment 1 - Specifications Oct 09.pdf

PDF 3 MB Posted

Attached to
Repair/Construct Base Pavements
Solicitation number
FA4659-10-R-0008
Issued by

About this file

Attachment 1 - Specifications

View the file

Other files

File Type Posted
Amendment 1.rtf RTF text file
DFARS 252.222-7999.pdf PDF
Attachment 2 - Climatological Data.pdf PDF
Attachment 1 - Drawings Oct 09.pdf PDF
FA465910R0008.doc DOC document
Attachment 3 - PAST AND PRESENT PERFORMANCE QUESTIONNAIRE.docx DOCX document
Cover Letter.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

TECHNICAL PROVISIONS

JFSD 200948 BASE PAVEMENTS BASIC CONTRACT

GRAND FORKS AFB

NORTH DAKOTA

June 2009

TECHNICAL PROVISIONS

JFSD 200948

TABLE OF CONTENTS

SECTION 01000 STATEMENT OF WORK

1. SCOPE: .........................................................01000-1

2. PROJECT DESCRIPTION: ...........................................01000-1

3. STANDARDS TESTS, QUALITY AND GUARANTEES ........................01000-2

4. BASE CIVIL ENGINEERING WORK CLEARANCE REQUEST: .................01000-2

5. UTILITY OUTAGES: ...............................................01000-2

6. FIRE REGULATIONS: ..............................................01000-4

7. CONSTRUCTION MANAGEMENT STANDARDS: .............................01000-4

8. UTILITY AVAILABILITY: ..........................................01000-6

9. CONTINUED USE OF FACILITIES: ...................................01000-6

10. ADMINISTRATION REQUIREMENTS: ...................................01000-6

11. NOTIFICATION OF CONSTRUCTION MANAGEMENT OFFICE (CMO): ..........01000-7

12. SUBMITTALS: ....................................................01000-8

13. ENVIRONMENTAL PROTECTION: ......................................01000-14

14. CONTRACTOR QUALITY CONTROL (CQC): ..............................01000-17

15. FOLLOW UP INSPECTIONS: .........................................01000-18

16. OPERATING MANUAL: ..............................................01000-19

17. TRAINING: ......................................................01000-19

18. SECURITY REQUIREMENTS: .........................................01000-19

19. SITE VISITS ....................................................01000-20

20. CONSTRUCTION QUALITY CONTROL DAILY REPORT...................... 01000-20

21. RECORDS MANAGEMENT REQUIREMENTS BY CONTRACTOR . . . . . . . . . 01000-22

ATTACHMENTS A, B, C, AND D. . . . . . . . . . . . . . . . . . . . . 01000-23

SECTION 02551 BITUMINOUS PAVEMENT, PORTLAND CEMENT CONCRETE

PAVEMENT, CURBING AND ADJUSTING MANHOLES

1. SCOPE OF WORK: .................................................02551-1

2. MATERIALS: .....................................................02551-1

3. SAMPLING AND TESTING: ..........................................02551-4

4. CORRELATION AND WORK CONDUCTANCE: ..............................02551-4

5. PATCHING: ......................................................02551-4

6. CRACK SEALING: .................................................02551-5

7. COMPACTION: ....................................................02551-5

8. CONCRETE POURING: ..............................................02551-5

9. RECYCLED MATERIALS: ............................................02551-6

SECTION 02763A PAVEMENT MARKINGS AND TRAFFIC SIGNS

1. GENERAL: .......................................................2763A-1

2. PRODUCTS: ......................................................2763A-3

3. EXECUTION: .....................................................2763A-5

SECTION 02784 CONCRETE PAVER STONES AND CAST IRON TREE GRATES

1. GENERAL: .......................................................02784-1

2. PRODUCTS: ......................................................02784-1

3. EXECUTION: .....................................................02784-2

SECTION 02831 CHAIN LINK FENCE

1. GENERAL: .......................................................02832-1

2. PRODUCTS: ......................................................02832-2

3. EXECUTION: .....................................................02832-5

SECTION 02832 SEGMENTAL CONCRETE BLOCK RETAINING WALL

1. GENERAL: .......................................................02832-1

2. PRODUCTS: ......................................................02832-4

3. EXECUTION: .....................................................02832-7

SECTION 02922 SODDING

1. APPLICABLE PUBLICATIONS: .......................................02922-1

2. SUBMITTALS: ....................................................02922-1

3. SOURCE INSPECTIONS: ............................................02922-1

4. DELIVERY, STORAGE AND HANDLING .................................02922-1

5. MATERIALS: .....................................................02922-2

6. SODDING TIMES: .................................................02922-3

7. SITE PREPARATION: ..............................................02922-3

8. SODDING: .......................................................02922-4

9. RESTORATION AND CLEAN UP: ......................................02922-5

10. PROTECTION OF TURFED AREAS: ....................................02922-5

11. TURF ESTABLISHMENT PERIOD: .....................................02922-5

12. FINAL ACCEPTANCE: ..............................................02922-5

SECTION 16375 ELECTRICAL DISTRIBUTION SYSTEM, UNDERGROUND

1. GENERAL: .......................................................16375-1

2. PRODUCTS: ......................................................16375-6

3. EXECUTION: .....................................................16375-9

SECTION 329219 SEEDING AND HYDROMULCHING

1. GENERAL: .......................................................329219-1

2. PRODUCTS: ......................................................329219-2

3. EXECUTION: .....................................................329219-6

Base Pavements Basic Contract

Section 01000

Technical Provisions

1. SCOPE OF WORK:

1.1. Work to Be Done: The work consists of furnishing all plant, labor, and materials to perform all work in strict accordance with plans and specifications and terms of contract.

1.2. Location: The site of the work is Grand Forks Air Force Base, ND.

2. PROJECT DESCRIPTION: The contractor shall perform work all work associated with, but not limited to the following:

2.1 Placing a hot bituminous pavement overlay with tack coat on streets and roads as directed.

2.2 Remove and replace existing concrete and asphalt pavement, including base course repair as directed.

2.3 Excavate and install new suitable subbase and base material and new asphalt or concrete pavement as directed. Construct new asphalt or concrete roads, parking lots, driveways and sidewalks.

2.4 Make minor patches as directed.

2.5 Make major patches as directed, including base course repair.

2.6 Remove and replace existing concrete sidewalks, brick paver sidewalks, curb and gutter as directed.

2.7 Raise or lower manholes and access covers as required to meet new or existing pavement surface.

2.8 Install or repair sewer inlets as directed.

2.9 Seal cracks 1/8 inch wide or wider. Seal joints. Refer to UFC 3-250-08FA - Standard Practice for Sealing Joints and Cracks in Rigid and Flexible Pavements (latest dated addition).

2.10 Apply a bituminous sand seal or fog coat as directed.

2.11 Mill pavements as directed.

2.12 Remove driveway materials and replace with concrete or asphalt as directed.

2.13 Install new concrete curb and gutter, brick pavers sidewalk and concrete sidewalk as directed.

2.14 Install new PVC storm drain line as directed.

2.15 Install new manholes as directed.

2.16 Stripe pavements as required, to include site development (i.e. parking plan).

2.17 Relocate/Install reserved parking and traffic signs. Refer to Air Force UFC 3-120-01- Air Force Sign Standard (latest dated addition).

2.18 Install light poles, block heater plug-ins with associated foundations, conduit, wiring, etc. to adequately light parking lots.

2.19 Contractor shall provide surveying equipment and expertise to facilitate all work necessary, and associated with the accomplishment of all delivery orders issued under this contract. Surveying requirements may be, but not limited to establish roadway, curbs, gutters, storm sewer inlet elevations, drainage structures and flow slopes/lines, determine cuts and fills, general project layout, and for government and contractor recommend alterations and modifications to awarded delivery orders, and to provide as-built drawings to include cross sectional details for all work that requires as-builts.

2.20 Hydro-mulching/seeding or sodding shall be performed on all areas disturbed by the contractor activities, both existing and new work, and other areas as directed by the contracting officer’s representative. Access areas leading to and from project locations disturbed by contract operations shall also receive hyrdo-mulching/seeding and/or sodding

2.21 Perform lime stabilization of soil. Refer to UFC 3-250-11 Soil Stabilization for Pavements (latest dated addition).

2.22 Perform cement stabilization of soil. UFC 3-250-11 Soil Stabilization for Pavements (latest dated addition).

2.23 Build segmented block retain walls, install light poles, and electric plug in poles.

2.24 Obtain permits, documentation, and apply/execute all other administrative and field requirements for compliance with the ND State rules and regulations, and the Environmental Protection Agency

01000 - 1 of 43 JFSD 200948

(EPA) rules and regulations as they apply to Storm Water Pollution Prevention for construction activities.

2.25 The contractor shall coordinate with the appropriate facility mangers, housing tenants, Civil Engineering personnel and Security Forces personnel to the extent necessary to provide area access, develop required plans, traffic control, and to de-conflict mission requirements.

This coordination shall be completed and approved by 319 CES, and/or the contracting officer 10 days prior to the start of on-site work. Preliminary site investigations to prepare required submittals and plans may have to be complete prior to the 10 day requirement of user coordination.

3. STANDARD TESTS, QUALITY, AND GUARANTEES:

3.1. Tests or trials to determine the effectiveness of performance of a completed assembly or fabricated system shall be made by the contractor, without cost to the Government.

3.2. All articles, supplies and equipment, parts, and assemblies thereof, of standard manufacturers or for which design requirements are not prescribed by these specifications shall be guaranteed against any failure in the proper use or operation caused by defective material, workmanship, or design for the full warranty time which is standard with the manufacturer and/or supplier.

3.3. The contractor shall deliver to the Contracting Officer one copy of manufacturer's standard warranty before final inspection of the facility.

4. BASE CIVIL ENGINEERING WORK CLEARANCE REQUEST: Prior to any construction activity the contractor shall initiate, prepare, and walk-through an AF Form 103, Work Clearance Request 14-28 calendar days prior to any work (especially excavation) activities. The Base Civil Engineering will assist the contractor by providing points of contact; however, the responsibility for executing and tracking status of the work clearance request s, and coordinating utility markings with the Base Civil Engineer shops and/or other utility companies is solely that of the contractor. The contractor shall compose and provide sketches/drawings/ and dimensioning details showing the specific location of the intended area of work (especially excavation) at the request of getting an AF 103. The contractor shall physically stake, flag, or demarcate (in accordance with base civil engineer work clearance manager) to define the boundaries of all required utility locates at the location of proposed work. The contractor should allow 10-20 days for processing the work clearance request between the various activities that must coordinate on the request.

The contractor shall submit to the CO and provide the Construction Representative with a copy of the completed AF Form 103 with all attached record utility drawings, and shall comply with all instructions for hand excavation and other methods of safeguarding the buried utilities prior to on-site work. The contractor shall take caution within the area 3 feet to either side of a utility pre-identified to the contractor.

If the contractor damages any utility within this six-foot boundary, the contractor is responsible for restoring the utility to its original working condition. Work to repair the damaged utility will commence immediately and will continue uninterrupted until the utility is restored. If the contractor damages a utility that was not identified or is not within the 6-foot boundary of the utility marking, the contractor shall notify the CO and Construction Representative to determine the method of repair (i.e., in-house or by contract). If the damaged utility requires repair by an outside source or someone not in the contractors employ (e.g., someone to repair specialty lines) and the contractor is responsible for the damage; the contractor shall coordinate and schedule persons making repairs and shall furnish prompt payment for the work to such persons.

5. UTILITY OUTAGES:

5.1. The contractor shall perform the work under this contract with a minimum of outage time for all utilities, for any facility or system. The contractor shall attempt to schedule any work that requires utility outages (electrical, water, gas, etc.) which will close down or limit normal activities in the building, construction area, or other affected areas (as determined by the contractor with

01000 - 2 of 43 JFSD 200948 coordination of engineering project management personnel) at a time other than regular work periods of the organization occupying the facility. A process and policy has been established by 319 CES for scheduling and notifications regarding all utility outages. Attachment B to this specification section contains the process and policy for the scheduling of utility outages at Grand Forks AFB. This coordination shall be the contractors responsibility. As this policy and other attachments are updated, new revisions will be provided to the contractor by the

CO.

5.2. In the event a scheduled outage is canceled by the Government, the CO shall notify the contractor at least 24 hours in advance of the time for the outage to start. In this case the contractor waives the right to any claim for equitable adjustment or increased cost of performance under the contract as a result of this cancellation.

5.3. Prior to the required shutdown of utilities, the contractor will coordinate a momentary shutdown to validate the effective operation of valves, switches etc. The contractor is responsible for shutting down the utility using his own workforce or by requesting the shutdown from the utility company (or appropriate Civil Engineer Shop) responsible for the service. The contractor shall coordinate with the appropriate Civil Engineer Shop or public utility to determine who will perform the shutdown. The contractor shall pay any fees associated with the required shutdown and shall comply with all instructions pertaining to the shutdown. Once work begins on an approved outage work must continue without interruption until utility services to the affected line(s) and/or facility are restored.

5.4. The contractor shall not disturb communication wiring to facilities. Where such facilities require removal of communication equipment and wiring to accomplish the work involved, the contractor shall coordinate with the Communications Squadron to determine the scope of effort and gain authority from the Communications Squadron to work in communications systems. The contractor shall allow for the accomplishment of such removals by the telephone company or communications personnel for the systems they service. If construction activities damage any communication equipment or wiring, the contractor shall restore services as soon as possible, but no later than 24 hours, and at no cost to the Government.

5.5. Prior to the start of work, the contractor shall coordinate with appropriate agencies with a work clearance request (AF Form 103) in order for the Government to locate and mark existing underground utilities, and to inform necessary Government agencies of the contractors intention to work. The contractor will not begin any work until this permit has been completed and approved (see Section 4.1). The contractor shall identify and locate all valve or utility shut-off locations for use in the event of accidental damage prior to work. To preclude accidental damage the contractor shall locate, and determine the depth of all known utilities represented on the work clearance request, and/or represented on record utility drawings, and/or physically marked on site; by hand digging (or hydro excavating) prior to any excavation with power equipment. The contractor shall document and detail any utilities or communications lines discovered during excavations that are not identified by the AF Form 103, and/or the record utility drawings that were missing or incorrectly located. The notes and detailing shall be graphically represented and dimensioned on the contractor’ s required post construction as-built drawing submittal to the government. The missing or incorrectly located lines shall be clearly marked for ease of identification to the Government of such discoveries on the contractor submitted post construction as-built drawings.

5.6. Record drawings and other mapping products showing existing facilities and underground utilities are available to the contractor through the Base Civil Engineer drafting office, and when applying for the AF Form 103. The Government does not guarantee the accuracy or adequacy of existing record drawings/maps. The contractor is responsible to verify all dimensions and actual conditions in the field when executing individual delivery orders. Failure to verify the dimensions and locations will be at the contractor’s risk and shall not relieve the contractor from accomplishing the work required by the contract at the quantities/price awarded by the Government. The contractor shall immediately repair any utility line shown on a record drawing, 01000 - 3 of 43 JFSD 200948 the AF 103, record drawings, and/or marked utilities (or made known to the contractor) damaged during construction work at no cost to the Government. The CO, construction representative, and the POC listed on the AF 103 shall be notified immediately in the event of damage to any utility or communication lines. Prior to digging the contractor shall review available record drawings, AF 103, and/or located utilities to determine if all utilities have been located. Should the record drawings, and AF form 103 indicate the existence of an underground utility but there are no markings to indicate the utility has been located, the contractor shall request a relocate, and/or hand dig to verify existence of the line prior to mechanical, motorized excavation (excluding hydro excavations).

6. FIRE REGULATIONS: Compliance with local, Air Force, and NFPA 241 (Safeguarding Building

Construction and Building Operation) regulations are mandatory. Fire extinguishers rated and approved by the National Fire Protection Association; of sufficient size, type, and quantity to cope with all known hazards, will be available and provided by the contractor during the execution of this contract.

6.1. The primary contractor is responsible to have personnel properly trained in safe welding, cutting, open flame operations and specific requirements of AFOSH Standard 91-5 and CFR 1910 252.

This individual shall be certified in writing, by the installation Fire Department to issue the AF Form 592 for the duration of the contract. It shall be the responsibility of the primary contractor to coordinate all certification training instruction with the installation Fire Department.

6.2. Contractor/user must post a fire guard for twenty-four (24) hours (or certifies the facility fire safe) after welding, cutting and open flame operations in facilities when the following situations apply:

6.2.1. Fire detection/sprinkler systems cannot be returned to service.

6.2.2. Fire detection/sprinkler systems do not exist.

6.3. Fire Protection, Detection, or Suppression Systems: Established systems shall remain operational to the maximum extent possible. Systems in areas unaffected by this contract shall remain operational throughout contract duration. Interruption (disconnection) of systems shall be:

6.3.1. Coordinated (7) seven days in advance with the Contracting Officer and the Base Fire

Department.

6.4. USAF Welding, Cutting, or Brazing Permit: . Prior to any soldering, brazing, torch cutting, and welding, the contractor must obtain a signed AF Form 592, USAF Welding, Cutting, or Brazing Permit from the Base Fire Department’s Technical Services Element. When any of these activities take place in a facility containing smoke detectors and the system alarms, the contractor shall replace any detectors (smoke, heat, etc.) in the immediate area that alarmed. If contractor activities disables or damages an existing fire alarm system in a facility, the contractor shall post a fire guard/watch until the system is made operational. Only the Base Fire Department can relieve the contractor of this requirement.

7. CONSTRUCTION MANAGEMENT STANDARDS:

7.1. GENERAL: For most construction projects or delivery orders, the Base Civil Engineer will provide the contractor with the primary construction site boundaries. Contractors shall have trailers only at that site (if applicable).

7.1.1. Storage Area: To the maximum extent possible, contractor storage shall take place at the job site and will be properly delineated, and secured. Exceptions may be for massive soil, backfill, milling, and aggregate paving materials. However, there may be no alternate storage areas on base available to the contractor. The contractor shall be

01000 - 4 of 43 JFSD 200948 prepared to store materials off of the installation at any given time throughout this contract at his/her expense.

7.1.2. A visually acceptable site at Grand Forks Air Force Base is an important construction standard. Contractor’s trailers must follow the base paint standards; therefore, they are to be antique linen or white in color. The contractor shall maintain the trailers in good condition or must remove them. The contractor is responsible for the security of this property and general housekeeping of the area(s).

7.2. PLANS

7.2.1. Site Plan: Prior to starting a deliver order the contractor shall submit a site plan indicating the location of the safety and construction barriers, location of all site trailers, equipment and material storage areas, and location and type of traffic control devices.

Site photographs prior to the start of work may be included with the plan. At completion of work, the contractor shall remove the facilities and restore the site to the original condition. Maps and base overhead photos are available at the Base Civil Engineering office to assist in plan preparations.

7.2.2. Haul Routes and Dirt/Debris Control Plan: The contractor shall submit per delivery order

(if applicable) truck and material haul routes requests along with a plan for controlling and cleaning (or removing) dirt, debris, and dust that migrates to adjacent base roadways and the haul route itself. As a minimum, the plan shall identify the contractor’s equipment being utilized for cleaning, the frequency of checks and cleaning, and additional measures to reduce dirt, dust, and debris from migrating off of the construction area.

7.3. CONTRACTOR’S TEMPORARY FACILITIES

7.3.1. Administrative Field Offices (if applicable): Contractor’s administrative field office and storage trailers shall be in like new condition and the exterior must be clean and shall be white or antique linen. Contractor shall be responsible for all temporary utility connections to their trailers. Storage of material/debris under the trailers is prohibited. If the contractor wishes to pursue a field office a request shall be made to the contracting officer for approval and location options. The base does not guarantee that a request will be approved. Requests will be considered based on availability of space, and other criteria.

7.3.2. Dumpsters (if applicable): Equip dumpsters with a secure cover. The cover shall be closed at all times, except when being loaded with trash and debris. Locate dumpsters behind the construction barricades within the area of work, and of the public view/access.

Empty site dumpsters when they become full to keep the site free of debris and trash.

7.3.3. Temporary Sanitation Facilities (if applicable): All temporary sewer and sanitation facilities shall be self-contained units provided by the contract for his/her employees.

The doors shall be self-closing. The unit shall be placed behind the construction barricades and out of the public view.

7.3.4. Construction Site Clean Up and Safety Fence:

7.3.4.1. The construction site must be kept clean and free of debris. Clean up shall be performed at the end of each work day in conjunction with a complete general clean up at the end of the project.

7.3.4.2. A safety fence shall be provided, set up and maintained by the contractor to enclose those areas that pose a safety hazard to people and vehicles (Example excavations holes not filled in, areas of rebar in vertical

01000 - 5 of 43 JFSD 200948 configurations, tripping hazards, work areas in immediate vicinity of a occupied base facility entrance , etc…. The safety fence will match the base standard (Federal Color Standard #23531) (or bright orange where it protects areas), high density polyethylene grid or approved equal, a minimum of 1.1 m (42 inches) high, supported and tightly secured to steel posts located on minimum 3 m (10 feet) centers. The contractor must remove the fence from the work site upon completion of the contract.

7.3.5. Grass Cutting/Weed Control: Cut grass (or annual weeds) within the construction and storage sites to a 4 inch height at least once a week during the growing season unless the grass area is not visible to the public. Trim the grass around the fences at times of grass cutting. Grass or weeds on stockpiled earth shall be maintained as described above.

8. UTILITY AVAILABILITY: All reasonable quantities of utilities (water and electricity) will be made available from existing outlets (distribution points) to the contractor without charge. The Government may not be held responsible for interruptions of utility service and will not be liable for contractor delays, damages, or increased costs occasioned by any such interruption of service. The government will not modify existing distribution points for contractor use. The contract shall gain approval and provide all materials, labor, equipment to facilitate utility use. Communications, telephone service and cable TV services are not provided by the base and are available through public service carriers in the area.

9. CONTINUED USE OF FACILITIES: Occupied facility associated or adjacent pavements that are a part of this contract (including facility parking lots), the contractor shall ensure appropriate notification and coordination takes place prior 10 days prior to delivery order accomplishment (or on-site work) with the facility manager, or housing resident. For general areas of the base (streets, roads, walks, trails, etc., not having a specific facility manager), the contractor shall coordinate phasing of the work with Civil Engineering project manager, construction manager, and the construction representative, as described in paragraph 2.25 of this section, submitted plans, and/or as approved through the Contracting Officer.

10. ADMINISTRATION REQUIREMENTS

10.1. CONTRACTOR PERSONNEL REQUIREMENTS

10.1.1. Contractor, Subcontractors and Other Contractor Associated Personnel: Furnish a list of contact personnel of the contractor and subcontractors including addresses and telephone numbers for use in the event of an emergency. As changes occur and additional information becomes available, correct and change the information contained in previous lists.

10.1.2. Supervision: The contractor shall designate in writing at least one qualifying superintendent/ supervisor capable of reading, writing, and conversing fluently in the English language on the job site during working hours. This individual shall have authority to make decisions for prime contractor in matters of work schedules, obligating material and labor resources to include funding decision in the event that contract modifications are required. In addition, if a Quality Control (QC) representative is required on the contract; that individual shall have fluent English communication skills and authority to direct, change, and correct deficient work – on the work site.

10.2. PRECONSTRUCTION CONFERENCE: After contract award, prior to commencement of any work at the site; the contractor shall schedule a preconstruction meeting with the Contracting Officer to discuss and develop a mutual understanding relative to the execution of the project. The contractor shall be prepared to discuss/and or present required plans, submittals, and thoroughly discuss the project execution to include, but not limited to; schedule, traffic control, material and equipment storage, haul routes, restricted area entry (if applicable) and all other general aspects with execution of the work with Civil Engineering, Security Forces, Safety, Fire Dept, Base Operations, Contracting Officer, and the users of the facility or area under contract.

Administration the contract, value engineering, base entry, restricted area entry, safety program, preparation of the progress schedules and report, shop drawings, submittals, scheduling

01000 - 6 of 43 JFSD 200948 programming, and the general execution of the work shall also be discussed. Major subcontractors who will engage in the work shall also attend. The preconstruction conference is the place where all major components of the project are deliberated and decided. The contractor shall come prepared to the preconstruction meeting; otherwise the meeting may be stopped and rescheduled at the contractor’s expense. In some cases a pre-work meeting will be required if the preconstruction conference is held too far in advance of on-site activities. An example of this circumstance would be if a delivery order was awarded in the fall of the year and on-site work (with exception of meeting Bona Fide Need) would take place the following spring/summer.

10.3. AVAILABILITY OF CADD DRAWING FILES: After award and upon request, the electronic

“Computer Aided Drafting and Design (CADD)” drawings files and GIS products will be made available to the Contractor for use in preparation of construction data related to the referenced contract subject to the following terms and conditions. Data contained on these electronic files shall not be used for any purpose other than as a convenience in the preparation of construction data for the referenced project. Any other use or reuse shall be at the sole risk of the Contractor and without liability or legal exposure to the Government. The Contractor shall make no claim and waives to the fullest extent permitted by law, any claim or cause of action of any nature against the Government, its agents or sub consultants that may arise out of or in connection with the use of these electronic files. The contractor shall, to the fullest extent permitted by law, indemnify and hold the Government harmless against all damages, liabilities or costs, including reasonable attorney’s fees and defense costs, arising out of or resulting from the use of these electronic files. These electronic CADD drawing files are not construction documents.

Differences may exist between the CADD files and the corresponding construction documents.

The Government makes no representation regarding the accuracy or completeness of the electronic CADD files and the corresponding construction documents. In the event that a conflict arises between the signed and sealed construction documents prepared by the Government and the furnished CADD files, the signed and sealed construction documents shall govern. The Contractor is responsible for determining if any conflict exists. Use of these CADD files does not relieve the Contractor of duty to fully comply with the contract documents, including and without limitation, the need to check, confirm and coordinate the work of all contractors for the project. If the Contractor uses, duplicates and/or modifies these electronic CADD files for use in producing construction data related to this contract, all previous indicia of ownership (seals, logos, signatures, initials and dates) shall be removed.

10.4. ELECTRONIC MAIL (E-MAIL) ADDRESS: The Contractor shall establish and maintain electronic mail (e-mail) capability along with the capability to open various electronic attachments in Microsoft, Adobe Acrobat, and other similar formats. Within 10 days after contract award, the Contractor shall provide the Contracting Officer a single (only one) e-mail address for electronic communications from the Contracting Officer related to this contract including, but not limited to contract documents, invoice information, request for proposals, and other correspondence. The Contracting Officer may also use email to notify the Contractor of base access condition when emergency conditions warrant, such as blizzards, terrorist threats, etc. Multiple email address will not be allowed. It is the Contractor’s responsibility to make timely distribution of all Contracting Officer initiated e-mail with its own organization including field office(s). The Contractor shall promptly notify the Contracting Officer, in writing, of any changes to this email address.

11. NOTIFICATION TO THE CONSTRUCTION MANAGEMENT OFFICE (CMO): The contractor shall notify assigned construction representative at least 10 days in advance of starting all work. This shall include, but is not limited to, notification when the initial work shall begin; when work shall resume after stoppage exceeding 7 or more days; and when work shall begin following all specified exclusion periods.

The official Notice to Proceed does not constitute sufficient notification to CMO that work shall begin.

11.1. Contractor Furnished Equipment Data: Approximately 3 days prior to project final inspection the contractor shall furnish the following data to the Contracting Officer.

01000 - 7 of 43 JFSD 200948

11.1.1. Equipment List: An itemized equipment list, showing unit retail value and nameplate data including serial number, model number, size, manufacturer, etc., for all contractor furnished items of plumbing fixtures, mechanical equipment, and electrical equipment installed under this contract.

11.1.2. Guarantees: Provide a list of all equipment items which are specified to be guaranteed accompanied by a copy of each specific guarantee. For each specific guaranteed item the list shall include the name, address and telephone numbers of the subcontractor who installed the item, the supplier or distributor and the manufacturer. The completion date of the guarantee period shall correspond to the applicable specification requirements for each guaranteed item.

11.2. Warranty Service Calls: The contractor shall furnish to the Contracting Officer the names of local service representatives and/or contractors that are available for warranty service calls and who will respond to a call within the time periods as follows: 4 hours for emergency calls (water and sewer distribution, critical electrical service systems and transportation systems) and within 7 days of written notice for all other systems. The names, addresses, and telephone numbers for day, night, weekend, and holiday service responses shall be furnished to the Contracting Officer and also posted at a conspicuous location in each mechanical and electrical room or close to the unit.

11.3. Work Schedule: Working hours for the contractor will normally be between the hours of 7:30 a.m. and 4:30 p.m. excluding Saturdays, Sundays, and Federal holidays. If the contractor desires to work during periods other than above, additional Government inspection forces may be required. The contractor must make his/her request to the Contracting Officer three days in advance of his/her intention to work during periods other than normal duty hours/days. However, if inspectors are required to perform in excess of their normal duty hours/days solely for the benefit of the contractor, the actual cost of inspection at overtime rates will be charged to the contractor.

12. SUBMITTALS:

12.1. Material Submittals: After acknowledgment of Notice to Proceed the contractor shall submit to the Contracting Officer for approval four copies of manufacturer's data, catalog cuts, samples, or other information as required for the items on the Material Submittal Schedule and the Technical Provisions. No progress payments will be made until all material submittals are received or other arrangements have been made through the Contracting Officer.

12.2. Submittal Preparation: In preparing submittals it shall be incumbent upon the contractor to clearly and fully demonstrate that proposed materials, systems, or methods meet or exceed all applicable specific requirements of the Technical Provisions. Whenever possible, parameters such as units of measurement, testing protocols and technical vernacular specified in the text will be those employed or referenced by the contractor or his agent in demonstrating compliance. When not possible, the contractor will clearly and fully demonstrate, by written notation, how other parameters, employed or referenced, compare with those specified.

12.3. Shop Drawing Submittals: Shop drawings, when required, shall consist of a complete list of equipment and materials, including manufacturer's descriptive and technical literature;

performance charts and curves; catalog cuts and installation instructions. Shop drawings shall be prepared to graphically demonstrate proposed layout and anchorage of materials, equipment and appurtenances; and material/equipment relationships to other parts of the work including clearances for maintenance and operation. They shall also contain complete wiring and schematic diagrams; and any other details to graphically demonstrate that a system has been fully coordinated and will properly function as a unit. See Material Submittal Schedule.

12.4. Test Submittals: See Material Submittal Schedule for tests required.

01000 - 8 of 43 JFSD 200948

12.5. As-Built Drawings:

12.5.1. Redline Markup Drawings. The contractor shall maintain a separate set of awarded contract drawings (including modification changes to said set) at the project site marked up to fully indicate as-built (actual) field conditions for each aspect of the project. These drawings shall be modified in red ink to differentiate between field changes and original configuration regardless of the origin of change. The redline markup drawings shall be maintained in current status at all times according to actual site conditions. They shall be located in a common area accessible for inspection by the Construction Representative, and Contracting Officer. The redline markup drawings shall be neatly maintained, protected from soiling, and periodically approved by the Construction Representative for accuracy. The redline markups drawings shall be submitted 10 days before the final inspection for approval by the Contracting Officer and/or his/her representative. Upon approval the redline markup drawings shall be returned to the contractor.

12.5.2. As-Built Drawings. The contractor shall, at his own expense, provide a qualified individual or firm to transfer all revisions from the redline markup drawings to the awarded drawings to create the as-built drawings. Upon completion of the transfer both the redline markup drawings and the as-built drawings shall be submitted to the Contracting Officer for approval. The contractor has 20 calendar days to create the as-built drawings beginning from the day the approved redline markup drawings are returned to the contractor. Work shall be accomplished in a professional manner and the quality standards set forth in the following paragraphs shall be met.

12.5.3. One complete set of full-size paper as-built drawings, and one electronic set of as-built drawings on a CD or DVD will be provided by the contractor for each submittal requirement.(original or re-submittal)

12.5.4. Drawings, paper or electronic, shall comply with the latest version of the A/E/C CADD

Standard available at : https://tsc.wes.army.mil/Products/standards/aec/default.asp Electronic drawings shall be created in model space at a scale of one to one (1 to 1). A paper space layout will be set-up for each drawing. All X-references shall be attached and bound to each affected sheet. Drawings must open in the specified Auto Cad format and be ready to plot without manipulation of files, directories, or other encumbrances.

No securities or safeguards that would prevent full control of any drawing will be installed. Changes made or inserted shall be completely drawn in Auto Cad to depict changes. Clouding, notation, or photo insertion to indicate changes are not acceptable unless approved in advance and can only be used on rare occasions.

12.5.5. Electronic as-built drawings are to be delivered in Auto Cad 2004 compatible format.

The contractor shall provide one CD or DVD containing all drawings properly labeled including awarded original drawings that were not changed. Drawing names shall mirror the awarded original drawing names and identified on the index sheet and each page.

Any changes to the number of sheets in the drawing set will require the renumbering /labeling of the entire set. All drawings in the set must be clearly distinguishable from construction drawings. The words “AS-BUILT” or “RECORD DRAWING” must be prominently displayed in the drawing area or inside the revisions block of the border.

The CD/DVD must also contain a second drawing set electronically plotted to a raster media such as .TIFF, .PDF, or JPEG for fast viewing.

12.5.6. Projects affecting exterior elements such as site or utility plans must comply with section

13.6.

12.5.7. The contractor shall present, format, and follow all prescribed direction in this section to prepare as-built drawings regardless of how the awarded drawings, and all drawings incorporated by modifications, are formatted and presented to the contractor.

01000 - 9 of 43 JFSD 200948 https://tsc.wes.army.mil/Products/standards/aec/default.asp

12.6. Geographic Information System (GIS) and Computer Aided Drafting and Design (CADD)

12.6.1. Deliverables for Design & Construction and Plans, Surveys & Studies Contract Services include, but are not limited to:

12.6.1.1. As-built drawings as required in paragraph 13.5 of this section.

12.6.1.2. Utility designs, plans, surveys and studies

12.6.1.3. Pavement, Grading, or Excavation plans

12.6.2. The contractor shall provide GIS deliverables in the following format:

12.6.2.1. All locational (point, line, and polygon feature(s)) data collected shall be delivered in ESRI-Arc/Info 9.3 format or latest version along with the original source files. The Geospatial files shall have an external spatial reference (.prj) file attached specifying the parameters of the coordinate system used (as provided by the government). All topologically correct geospatial data shall overlay on the installations latest orthorectified imagery provided by the government. All accuracy errors shall be reported to the contract program manager.

12.6.2.2. All graphic and non-graphic data will be collected in the format defined by the

CADD/GIS Technology Center’s Spatial Data Standards for Facilities, Infrastructure and Environment (SDSFIE) release 2.6 (or the most current version available), except where modified by the Government. This standard can be found at: http://www.sdsfie.org/SDSFIEHome/tabid/36/Default.aspx

12.6.2.3. The contractor shall provide a quality control (QC) report that must state whether all inconsistencies in the data generated were corrected, or it must detail the remaining errors by case. The contractor shall utilize a topology build and clean routine to assure that there are no overshoots or undershoots in the line work, slivers or dangles in polygons, and that there is complete closure of polygons with a maximum fuzzy tolerance value of 10-9. The quality report must identify the software (name and version) and satisfy these conditions:

12.6.2.3.1. The edges of all digitized vector data or raster imagery must exactly match digitally with those of all adjacent maps.

12.6.2.3.2. The digital representation of the common boundaries for all graphic features must be exactly the same, regardless of feature layer. Each feature within a theme must be represented by a single graphic element (e.g., polygon, line, or line string).

12.6.2.3.3. Lines and line strings which represent the same graphic element must be continuous (i.e., not broken or segmented), unless that segmentation reflects a specific visual line type. Lines or line strings representing the same type of data must not cross except at intersections.

12.6.2.3.4. Polygons must be closed (i.e., the first x- and y-coordinates must exactly match the last x- and y-coordinates). Each polygon must have a single unique centroid to which attributes (i.e., an attribute table) can be attached. Polygons of the same coverage must not overlap and must cover the area of interest completely (i.e., have no gaps in coverage).

12.6.2.3.5. All graphic elements that connect must exactly connect digitally, without overlaps or gaps.

01000 - 10 of 43 JFSD 200948 http://www.sdsfie.org/SDSFIEHome/tabid/36/Default.aspx

12.6.2.3.6. Straight lines must be represented by only the beginning and ending x- and y-coordinate points. Line strings must not cross back on themselves or be of zero length.

12.6.2.4. Feature Attributes: The contractor shall identify the classification, type, size, location, ID number, and any other necessary attributes (specified by the Government) for all surveyed, mapped, designed, or proposed features.

12.6.2.5. All symbol libraries, font libraries, text size, text format, and text placement shall be prepared in accordance with and conform to the Spatial Data Standards for Facilities, Infrastructure and Environment (SDSFIE) Release 2 (or most current available).

12.6.2.6. The contractor shall not develop new libraries without prior written approval from the Government.

12.6.2.7. The contractor shall provide metadata files for all locational data produced under this contract. The metadata file shall conform to the Federal Geographic Data Committee’s “Content Standard for Digital Geospatial Metadata, Version 2.0” (or latest version) found at:

http://www.fgdc.gov/metadata/csdgm/index_html. The output from AutoCAD 2004 or ESRI ArcGIS generator software shall be the standard format for all metadata files created under this contract. In addition, the metadata data shall be provided in ASCII text format. The digital metadata files shall be provided to the Government along with each final product deliverable, unless otherwise approved in writing by the Government.

12.6.3. The contractor shall provide CADD deliverables in the following format:

12.6.3.1. Point Features

12.6.3.1.1. Point features should be digitized as points, not graticules, symbols or icons.

12.6.3.1.2. Do not use any symbol fonts to place point features.

12.6.3.2. Line Features (including Contours)

12.6.3.2.1. Lines will be used to depict linear features.

12.6.3.2.2. Lines should not be broken for text. For ArcView/ArcInfo use, each line should be continuous within its own layer. This will ensure spatial query compatibility.

12.6.3.2.3. Lines should all be continuous, i.e. do not create dashed lines with many small line segments. Instead, a dashed line font on a continuous line may be used.

12.6.3.3. Polygon Features

12.6.3.3.1. Area features (polygons) must always close (e.g. no "C" shaped areas). For ArcView/ArcInfo use, each polygon must be closed and on its own feature.

12.6.3.4. Text Labels and Identifiers

01000 - 11 of 43 JFSD 200948 http://www.fgdc.gov/metadata/csdgm/index_html

12.6.3.4.1. Text Labels are not required for any features

12.6.3.4.2. At a minimum, basic feature identifiers for roads and buildings as listed in the Spatial Data Standards will be used

12.6.3.5. All graphic and non-graphic data will be collected in the format defined by the CADD/GIS Technology Center’s Spatial Data Standards for Facilities, Infrastructure and Environment (SDSFIE) release 2.600 (or the most current version available), except where modified by the Government. This standard can be found at: http://www.sdsfie.org/SDSFIEHome/tabid/36/Default.aspx

12.6.4. The survey data shall be collected in the following matter:

12.6.4.1. The contractor shall use Global Positioning Systems (GPS) for field data collection at an accuracy level in accordance with “Geospatial Positioning Accuracy Standards, Part 3: National Standard for Spatial Data Accuracy,” published by the Federal Geographic Data Committee (FGDC), dated July 1998. This standards document can be found at http://www.fgdc.gov/standards/projects/FGDC-standards-projects/accuracy/part3/chapter3

12.6.4.2. All Survey data collected shall be provided to the Government in a digital format with an attached Survey Report identifying survey method, equipment list, calibration documentation, survey layout, description of control points, control diagrams, and field survey data.

12.6.4.3. A Survey Control Database (consisting of a survey marker database and a survey traverse database) will be produced for all survey control points established under this contract, and delivered in a .dbf or ASCII comma-delimited format.

12.6.4.4. The contractor shall use survey grade GPS, at an accuracy level of +/- 2cm., when appropriate, to collect data to be overlaid onto the installation’s orthophotograph and/or base map.

12.6.5. The coordinate system shall be set up in the following matter:

12.6.5.1. All survey measurements and established coordinates shall be measured in feet, and sub-units of feet. The coordinate system for all survey data will be the North Dakota State Plane Coordinate System (North). The vertical datum will be North American Vertical Datum 1988 (NAVD 88). The horizontal datum will be North American Datum 1983 (NAD 83).