QA Grounds Maintenance_v2.xlsx

XLSX spreadsheet 19 KB Posted

Attached to
Grounds Maintenance Federal contract opportunity
Solicitation number
FA4626-23-Q-0001
Issued by
Department of the Air Force Global Strike Command

View the file

Other files for this federal contract opportunity

Other files attached to Grounds Maintenance, newest first.
File Type Posted
Second QA Grounds Maintenance.xlsx XLSX spreadsheet
Wage determination.pdf PDF
Amendment 001.pdf PDF
Attch 2.c. APP B_Drainage Map.pdf PDF
Attch 1_Attendance Log.pdf PDF
Site Visit Minutes.pdf PDF
Attch 2.b. Grounds Maintenance Map_rev.pdf PDF
Attch 2.c. Irrigation Control Locations 2022.pdf PDF
Attch 2 PWS.pdf PDF
Attch 1. Bid Schedule.xlsx XLSX spreadsheet
Attch 5 Grounds Maintenance QASP.pdf PDF
Attch 2.b. Grounds Maintenance Map.pdf PDF
Attch 2.A. Grounds Mx Appendix A.xlsx XLSX spreadsheet
COMBO.pdf PDF
Attch 4 Past Performance Questionnaire.docx DOCX document
Attch 3. Installation Perimeter Access Control.pdf PDF
Show all 16

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

Grounds Maintenance FA4626 - 23 - Q - 0001
Questions and Answers
Question #QuestionAnswer
1Is this replacing an existing contract in place for another 5 years or is this a new scope/package that is not currently being performed?This is replacing the existing contract. The solicitation utilizes a full order approach rather than definitized maintenance areas. The overall requirement is similar.
2Could you please provide the name of the invumbent for this project, the contract # and POP of the award, and award amount? Are the requirements of this solicitation the same/similar to that of the current contract?The incumbent is Byrd Enterprises Unlimited, Inc. The base contract is FA462619DA001. This contract had a base year with three option years which were all ordering periods in the amount of $2,955,990.68. Any further contract or task order information can be found on SAM.gov.
3Can the subcontractor’s past performance be evaluated in place of the prime?The subcontractor's past performance may be evaluated if the prime is a small business and proposes a teaming arraingment with a first-tier small business subcontractor. Teaming arraingements must fully comply with FAR Subpart 9.6.
4Is the contractor responsible for all equipment purchases or is it subsidized?Per PWS paragraph 1, the contractor is responsible for, including but not limited to, all equipment purchases.
5PWS says contractor damage is repaired within 15 days, sometimes product or items are hard to get. Is this something that can be worked out with the COR if delays are needed?In general, the 15 day deadline is reasonable and expected but the contractor can work with the COR as needed attributable to the ongoing supply chain issues.
6How will tickets be issues for leaf cleanup?Please reference paragraph 1.1.9 of the Performance Work Statement.
7Is there a preferred process on edging sidewalk grass? Hard edge or by trimmer?Please reference paragraph 1.1.4 of the Performance Work Statement.
8Are rodents included with pest management?No, they are not. Please reference paragraph 1.1.11 of the Performance Work Statement.
9Is all of Perimeter Fence accessible by mowers?Yes, they are accessible by mower.
1010th Ave No, separate contractor to mow? Who is responsible for damage?If this is in reference to the line of demarcation between privatized housing and government property, it is the fence and/or block wall. Each party bears their own liabilities with regards to damage.
11One-hour response time is it as the same as duty and non-duty hours?Per paragraph 1.8.2 of the Performance Work Statement, response shall occur during the Duty Day schedule. Only water breaks or malfunctioning irrigation will need to occur at any time or day in accordance with paragraph 1.1.7.2 of the Performance Work Statement.
12BLDG 145 the only area of hand watering?Yes, this is the only hand watering location.
13How will tickets or work request after verbal be sent? Email or a program?These will be submitted via E-Mail.
14In 1.1.6 weed control, Improved or areas outside of improved too?Weed control is only in improved areas.
15For irrigation is the contractor responsible for main supply valves? Who replaces damaged main valves?IAW PWS paragraph 1.1.7.2, the contractor is responsible after the backflow. Damaged main valves are replaced by the government.
16Are locates for irrigation to be done year-round or just during growing season?Locates are required year-round.
17Are there as-builts for the irrigation systems, if not, who is responsible for mismarked lines and unknown installation?Some irrigation as-builts are available. See PWS paragraph 1.1.7.4 for irrigation identification requirements. Mismarked lines and unknown installation apply to the prime construction contractor in performance of their contract.
18Per the PWS, backflow repairs say 15 days, according to ASSE it is 5 working days? Any clarification?IAW PWS paragraph 1.1.7.2, the contractor is responsible for testing the backflow preventers but not for repairs to the backflow preventers.
19What are the expectations of tagging backflows after winterized?IAW PWS paragraph 1.1.7.5, the contractor shall tag the irrigation system shut off valve with the following information: "system winterized," the date, and who it was performed by. Repairs to the irrigation equipment must be accomplished prior to winterization.
20How to dispose of dead animals?IAW PWS paragraph 1.1.8.1, the contractor shall contact pest management and public health within 10 business days after contract award to get instructions on the protocols for handling dead animals.
21Stumping after tree removal, PWS states one day, is that after dig permit approval or one day after tree is removed?Referencing PWS paragraph 1.8.1.4 this will be completed after tree removal.
22Are there semi-improved for mowing maps? Road-way mowing?A map will be provided at the time of task order issuance deliniating order values. Offerors are reminded, the map was provided for reference and subject to change.
23What is the base solid management plans in regard to leaf removal?Referencing PWS paragraph 3.6 there is no area for the contractor to leave yard/tree waste on base. The contractor shall be responsible for removing any yard/tree waste from the base.
24Is there a preferred type of turf for sod renovation?Referencing PWS paragraph 1.1.13, local varities will suffice to meet the standard.
25Are there available maps for rock beds that are expected to be maintained?The Government is not in posession of a map to that degree of detail. Rock beds are located within the improved grounds around facilities.
26Is there already an approved herbicide list for the base? What is the process of getting something added?Referencing PWS paragraph 4.4.3, all pesticides must be approved prior to use by the Command Entomologist if not on the base approved list. Send this list with the intended uses to the Contracting Officer.
27Is there mapping for the service ditches?Please see Amendement 001 attaching 2.c. Appendix B Drainage Map.
28Referenced WD is 2015-5391, Revision No.: 17, dated 07/21/2022. Should this be updated to reflect the newest version 18, dated 12.27.22? And/or the newest iterationPlease see Amendement 001.
29The Clin Structure reflects base year clins for all 5 years. When it should reflect option year clins for their respective years.This basic contract is an indefinite delivery contract containing an ordering period. Periods of performance will be issued at the task order level.
30It was stated during the site visit that the provided site map (Attch 2.b) was interactive however it is not, is the government able to provide an updated interactive one as intended?Attachment 2.b. has been reuploaded with Amendment 001. If issues persist, please contact the Contracting Officer and Administrator immediate. The Government will email or utilize DODSafe to provide a copy upon request.
31What was the total contract value and length/number of years of the incumbent contract?Please reference question two above.
32Does contractor need back flow licenses?The Contractor is required to have a backflow license.
33What is the age of the irrigation system? What shape is the system currently in?The irrigation system has been operational since 1986. It is in an operable and functional state.
34Will the government provide Irrigation Maps?The map has been reuploaded with Amendment 001. The irrigation locations are marked with green hatch color.
35Historically, how many digging permits/ year is needed for the requirements in the PWS?It varies anywhere between 15 to upwards of 60 dig permits per year.
36Does contractor need a Tree Trimming Powerline Certification?No, this certification is not required.
37Is there a designated location on base to unload trees and debris? If not, what is the nearest location to dispose?No, please reference question 23 above.
38Is the mixing of herbicides allowed on base?No, this is not allowed. Please reference paragraph 4.4.3.2 of the Performance Work Statement.
39Does the government provide Fuel Tanks?No, these are not provided by the Government.
40How close is the contractor supposed to maintain around construction flags?Please keep a stand-off minimum of six inches and a maximum of 12 inches.
41Will the Grounds at the Base be in compliance upon award/contractor ramp-up?Yes, the grounds on base will be in compliance at time of award.
42Was the award amount posted in SAM for the incumbent contract for a four-year period or a five-year period?See question two above.
43What is the period of performance for this contract?The period of performance will be at the task order level not to exceed 12-months.
44Is the CE plow damage sidewalk clean up included in the in the improvement CLIN?Yes, this will be included in the improvement CLIN.
45Is the grounds ktr responsible for any snow removal?No, not for the installation. Please reference PWS paragraph 3 regarding the required facility maintenance.
46Will a map with the base acreage and irrigation lines be provided to ktrs?Please see question 34 above.
47Is CPARS used for validation? Will the Government look into different systems and contact references for past performance?Yes, CPARS may be used for validation. Please let your references know that they will be contacted. CPARS must clearly show a deliniation of work accomplished under this solicitation.
48Do we need to schedule with the Air Field Manager to work in the BASH?Yes, you will need to schedule and coordinate this work with the Air Field Manager.
49Do we need separate workers for the WSA?No, you can use any workers you so choose. Please reference PWS paragraph 4.8 for security requirements.
50Is the WSA a set location with a set amount of work?Yes. The work within the WSA will be definitive and will be the same every time.
51What is the acreage of the ditches?See question 27 above.
52Are consumables such as sprinklerheads reimbursable?See paragraph 1.1.7.2 in the Performance Work Statement. The contractor shall maintain irrigation systems. Maintenance includes but is not limited to draining and charging systems, replacing damaged or broken control devices and sprinkler heads, and repair of ruptured pipes. CLIN 0005 is established for consumables and repairs to the irrigation system.
53Was spring cleanup included in the previous iteration of this contract?No.
54How many irrigation systems are there? How many backflow devices is the contractor responsible for and their respective sizes?There are roughly 74 irrigation systems with 76 backflows on base. The backflows are between 1 and 3 inches and are reduced pressure or pressure vaccuum breaker types.
55What license is required for Pest Control ?See PWS paragraph 4.5 in the Performance Work Statement.
56What is the process for repair of government provided facilities? i.e.. Garage door repair, Heat issues. Broken locks etc.. What is an acceptable time frame for repairs to be completed?You will submit a work request and there is not an official timeline at the moment.
57What is the process for other contractors removing flags from dig permits? What is the expected time frame of completion?This will need to be coordinated with the Contracting Officer Representative of the contract utilizing the flags for dig permits. The timeframe will depend on the coordination and work being conducted by the contract utilizing the flags.
58Can we create a teaming agreement with a Service-Disabled Veteran-Owned Small Business in order to stay elligible for award?Teaming arraingements may be accepted and must fully comply with FAR Subpart 9.6. Please be cognizant of FAR 52.219-27 Notice of Service-Disabled Veteran-Owned Small Business Set-Aside, which is included in this solicitation.
59Are the requirements of this solicitation the same/like that of the current contract?See question one above.
60Will the Government consider a request for noncompetitive procurement for Total Small Business, Veteran-Owned Small Business, Women-Owned Small Business, Black American Owned, Service-Disabled Veteran Owned, Veteran Owned, EDWOSB, Women Owned?No.
61On the bid schedule, line item 0002 has an annual quantity of 3,339 acres. This appears to only include the improved irrigated acreage. The improved non-irrigated acreage would add ~9,400 annual acres. Is the quantity intended to exclude the improved non-irrigated acreage? If so, where is this acreage accounted for in the bid schedule?The maximum number of improved acres is 477 each month. The 3,339 acres is 477 by 7 months annually. This maximum includes both irrigated and non-irrigated areas. There is no separate line or number for improved, non-irrigated acreage.

&"Times New Roman,Regular"&P of &N

Sheet2

remove draft stamp
topr may 4th 3 pm
questions due by the 27th of April
Wage Determination
Skim through TOPR

File details come from the government source that posted it. Updated .