Attch1_SOW.pdf
PDF 895 KB Posted
- Attached to
- Heat Plant Boiler Repair
- Solicitation number
- FA4626-18-R-0009
About this file
Attachment 1 - Statement of Work
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Amendment_0001.pdf | ||
| Q&A_Doc1.pdf | ||
| Attch5__Past_Performance_Questionaire.pdf | ||
| Attch4_SpecialContractRequirements.pdf | ||
| Attch2_WageDeterm_MT67.pdf | ||
| FA4626-18-R-0009.pdf | ||
| Attch3_InstallationPerimeterAccess.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Attachment 1
STATEMENT OF WORK
ROOF AND CROSSOVER TUBE
REPAIR
6 February 2018
1.1 GENERAL REQUIREMENTS
Provide all items, articles, materials, operations, or methods listed, mentioned or scheduled on the drawings and/or as specified herein, including all labor, materials, equipment, and incidentals necessary and required for completion of the scope of this project.
1.2 UTILITIES
All reasonable quantities of utilities will be made available from existing utilities to the
Contractor without charge. Any temporary connection or lines that may be required will be installed, maintained, and removed by the Contractor at his own expense and in such a manner satisfactory to the Contracting Officer. Removal of such connections or lines will be accomplished prior to final acceptance of the construction. The Contractor shall provide any necessary portable power.
1.3 SAFETY
The Contractor shall comply with all existing Occupational Safety and Health Act (OSHA) standards of safety at all times in the performance of this contract. Hazards to the safe use of the premises due to the Contractor's work and/or equipment shall be suitably marked at all times.
Pedestrian and vehicle traffic ways shall be kept clear and unobstructed.
1.3 CONTRACTOR VEHICLES AND EQUIPMENT
The Contractor shall provide all vehicles and equipment necessary to accomplish the contract work. Power equipment shall be equipped with safety and noise limiting devices. The equipment shall be in a safe and efficient operating condition. The Contractor shall not park vehicles in the project area during non-working hours. A designated parking area for vehicles and equipment will be provided. Vehicles will not be allowed on lawns or sidewalks without prior written approval. All equipment will be clearly marked with the Company name.
Truckload Limits: The following load limits shall apply to all contractor-operated equipment on this project:
April I to June I 350 #/inch width of tire
All Other Times 400 #/inch width of tire
FA4626-18-R-0009
1.4 CONTINUED USE OF FACILITIES:
Building, structures, facilities, and utilities will continue in use by the Government during this contract. The Contractor shall notify Contracting when a no-work condition will occur for more than one day by the Contractor or sub-contractors (except weekends and federal holidays).
1 .5 CONSTRUCTION NEAR UTILITY SYSTEMS
All contractors shall be responsible for processing their own Work Clearance Request (AF
Form I 03), commonly known as a "Digging Permit," and coordinating with Government inspectors as required. It is also the sole responsibility of the Contractor to make all requests for locates and marking by the private sector. Note that private companies supply numerous utilities and services on Malmstrom Air Force Base. AF Form 103 does not address coordination with private companies. Requests for locates by private firms shall be performed by the contractor in accordance with State of Montana and Federal regulations. The
Contractor is responsible for obtaining all coordination signatures for the permit. The approved permit shall be valid for a period not to exceed 90 calendar days. TO THE MAXIMUM
EXTENT POSSIBLE, ELIM INATE PERMANENT MARKINGS ON PAVEMENT AND
CURBS. The contractor shall be responsible for maintaining all utility markings. Location marks shall be removed after 14 calendar days if not used. All markings shall be accomplished with water-based chalk (Aervoe Pacific Inc. 1-800-227-0196 or equal). No paints will be used. Detailed permit procedures and guidelines shall be provided to the contractor during the
Pre-performance Conference. Digging within three feet of buried communications cables, environmental monitoring wells, electrical cables, irrigation systems, and gas lines shall be performed by hand digging until the utility is exposed. The Project Inspector shall be notified three days prior to digging within a three-foot area near this utility. A representative from communications (Telco) must be present during excavation of Communications Cables. The cable piping routes must be marked prior to excavation in the area. The Contractor shall be held responsible for any damage to a marked or identified utility by excavation procedures.
Once the utility is exposed, mechanical excavation may be used if there is no chance of damage occurring to the cable or piping system. The contractor is responsible for marking all excavations he will do, three (3) work days prior to needing existing utilities marked by the government.
1 .6 WORK SCHEDULE
Working hours for the Contractor will normally be between the hours of 7:45 a.m. and 4:15 p.m. excluding Saturdays, Sundays, and Federal Holidays. If the Contractor desires to work during periods other than above, additional government inspection forces may be required.
The Contractor must notify the Contracting Officer three days in advance of his/her intention to work during other periods to allow assignment of additional inspection forces when the
Contracting Officer determines that they are reasonably available. If such force is reasonably available, the Contracting Officer may authorize the Contractor to perform work during periods other than normal duty hours/days. However, if inspectors are required to perform in excess of their normal duty hours/days solely for the benefit of the Contractor, the adjustments to the contract price may be made periodically as directed by the Contracting Officer.
1.7 ANTI-TERRORISM (AT) AWARENESS TRAINING.
In accordance with AFI 10-245, Antiterrorism (AT), the Government will ensure that AT level-1 awareness training is offered to all contractors. The objective of the training is to provide personnel with requisite knowledge necessary to remain vigilant enable employment of AT tactics, techniques, and procedures.
2.0 GENERATOR 3 FURNACE ROOF AND CROSSOVER TUBES REPAIR
2.1 SUMMARY OF WORK:
The contractor shall provide all, labor equipment and materials to replace 93 roof tubes and 93 crossover tubes in combustion chamber of the High Temperature Water Generator #3. Tubes will be manufactured per manufacture specifications EXCEPT MINIMUM TUBE WALL
THICKNESS WILL BE MODIFIED FROM .109 TO .120. Roof tubes will be connected 2 feet down the front wall and rolled, welded and rolled again into header per manufactured specifications. Crossover tubes will be connected at the butt weld of the previous rear wall repair and rolled, welded, and rolled again into header per manufactured specifications. All tiles, block, insulation, sheeting, and tuyeres (tuyeres will be saved and reused) will be removed and replaced according to manufacturer specifications. Contractor shall dispose of all materials removed during repair to include tiles, block, insulation, sheeting, and tubes. Contractor shall provide all documentation and inspections as required by State and Federal requirements.
2.2 GENERATOR SPECIFICATIONS:
Mfg: International Boiler Works
Identification Number: TJW-VC-85
Type: Water Tube
Serial: 14892
NB#: 16135
Output/Hour: 85 MMBTU
Max PSI: 500 PSI
Tubes: 1.5” OD, SA-178-A .120 min wall boiler tubing
2.3 EXECUTION:
2.3.1 Remove all tube header plugs.
2.3.2 Remove and dispose of all existing insulation, sheeting, refractory and tubes required.
2.3.3 Manufacture 93 roof tubes per specifications except minimum tube wall thickness will be modified from .109 to .120 and deliver to job site.
2.3.4 Manufacture 93 crossover tubes per manufacture specifications except minimum tube wall thickness will be modified from .109 to .120 and delivered to job site.
2.3.5 Install 93 roof tubes 2-feet down the front wall per manufacture specifications (rolled, seal welded and rerolled into header).
2.3.6 Install 93 crossover tubes to the butt weld of the previous rear wall repair per manufacture specifications (rolled, seal welded and rerolled into header).
2.3.7 Install tube header plugs.
2.3.8 Hydrostatic test and file all required documentation for repair as required by Federal and
State requirements.
2.3.9 Replace all insulation, sheeting and refractory per manufacture specifications.
3.0 GOVERNMENT SUPPORT
3.1 Government Materials Supplied: Header plugs and gaskets.
3.2 The government will be responsible for removal of all auxiliary equipment that would impede the execution of the contractor. Testing requirements will be assisted by the government.
4.0 PERIOD OF PERFORMANCE
4.1 The contractor shall have all required work and tests completed no later than 120 calendar days from the issuance of the Notice to Proceed.
File details come from the government source that posted it.