Attachment 2 Submittal Schedule
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| MEECN_Vault_Questions_-_8-20-14.pdf | ||
| MEECN_Vault_Questions_-_8-19-14.pdf | ||
| Pre_-Preposal_Conference_Minutes.pdf | ||
| Drawings.zip | ZIP file | |
| Specs.zip | ZIP file | |
| Attch_3_Schedule_of_Drawings.docx | DOCX document | |
| Attch_5_Wage_Determination.pdf | ||
| Attch_6_Base_Entry_Policy_Letter.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| SCHEDULE OF MATERIALS SUBMITTALS | Project Number | Project Title: | Solicitation/Contract No. | ||||||||||||||||||
| NZAS 15-0038 | Construct MEECN Vault | FA4626-14-R-0030 | |||||||||||||||||||
| TO BE COMPLETED BY PROJECT ENGINEER | TO BE COMPLETED BY CONTRACTOR/ADMINISTRATOR | ||||||||||||||||||||
| Number of Copies Required | |||||||||||||||||||||
| LINE NUMBER | ITEM OR DESCRIPTION OF ITEM, CONTRACT REFERENCE, TYPE OF SUBMITTAL | CERTIFICATION OF COMPLIANCE | SHOP DRAWINGS | SAMPLES | COLOR SELECTION | MANUFACTURER'S RECOMMENDATIONS | MANUFACTURER'S WARRANTY | CATALOG DATA | OPERATING INSTRUCTIONS | NOTIFICATION | OTHER | REQUIRED SUBMISSION DATE (BY CONTRACTOR) | DATE RECEIVED IN CONTRACTING | DATE TO CIVIL ENGINEERING | RETURN SUSPENSE DATE | SUBMITTAL NUMBERS | DATE CONTRACTOR NOTIFIED | CONTRACTOR RESUBMITTAL | FINAL APPROVAL | REMARKS | |
| APPROVED | DIS- APPROVED | ||||||||||||||||||||
| 1 | As-Built Field Drawings 01000 3.5 | 4 | PTFA | ||||||||||||||||||
| 2 | Operating and Maintenance Instructions 01000 3.7 | 4 | PTFA | ||||||||||||||||||
| 3 | Shop Drawings 01000 3.10 as Required by Technical Specifications | 4 | PTSW | ||||||||||||||||||
| 4 | Start of Work Notification 01000 3.11 | 4 | PTSW | ||||||||||||||||||
| 5 | Notice of Final Inspection 01000 3.12 | 1 | PTFA | ||||||||||||||||||
| 6 | Utility Outage Notices 01000 3.14 | 1 | PTO | ||||||||||||||||||
| 7 | Submittals 01000 3.15 | 1 | PTSW | ||||||||||||||||||
| 8 | Quality Control Plan 01000 3.18.2 | 1 | PTSW | ||||||||||||||||||
| 9 | Quality Control Records 01000 3.18.4 | 4 | PTFA | ||||||||||||||||||
| 10 | 1354 Checklist (Property Inventory Checklist) 01000 3.19 | 4 | PTSW | ||||||||||||||||||
| 11 | Identification of Employees 01001 1.1.A | 1 | PTSW | ||||||||||||||||||
| 12 | Asbestos Report / Removal Plan 24110 | 4 | PTSW | ||||||||||||||||||
| 13 | Carpet Sample 096813 | 4 | PTSW | ||||||||||||||||||
| 14 | Manufacturer's Literature, Vault Door, 110200 | 4 | PTSW | ||||||||||||||||||
| 15 | Test and Balance Report, HVAC, 230593 | 4 | PTFI | ||||||||||||||||||
| 16 | Light Fixtures, 265100 | 4 | PTSW | ||||||||||||||||||
| 17 | Plans and Literature, Intrusion Detection System, 281600 | 4 | PTSW | ||||||||||||||||||
| 18 | Fire Alarm Devices Literature 283111 | 4 | PTSW | ||||||||||||||||||
| Schedule of Abbreviations: | |||||||||||||||||||||
| D - Days | PSW - Prior to Start Work | PFI - Prior to Final Inspection | |||||||||||||||||||
| AFI - After Final Inspection | BBCW - Before Beginning Concrete Work | PPC - Prior to Project Completion | |||||||||||||||||||
| ANP - After Notice to Proceed | BD - Before Delivery | PT - Prior to Testing | |||||||||||||||||||
| ATT - After Test is Taken | PBC - Prior to Beginning Construction |
&L&"Times New Roman,Regular"&12Attachment 2&C&"Times New Roman,Regular"&12Title&R&"Times New Roman,Regular"&12FA4626-14-R-0030 &L&"Times New Roman,Regular"&12This list is not all inclusive. If needed, additional items may be added.
AF Form 66 &D&C&"Times New Roman,Regular"&12
SS-&P
REQUIRED TECHNICAL SUBMITTALS