Solicitation.doc
DOC document 249 KB Posted
- Attached to
- Repair/Replace High Temperature Hot Water Service Lines; Phase 14 Federal contract opportunity
- Solicitation number
- FA4626-14-R-0005
About this file
Solicitation
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Site_Visit.pdf | ||
| M12.1.dwf | DWF file | |
| Attch_2_Material_Submittal.xls | XLS spreadsheet | |
| Attch_3_SCHEDULE_OF_DRAWINGS.doc | DOC document | |
| Attch_7_-_Subcontractor_Consent_Form_-_10R0027.docx | DOCX document | |
| Attch_8_Base_Entery_Policy.pdf | ||
| Attch_5_Wage_Determination.docx | DOCX document | |
| Attach_1_SPECS.zip | ZIP file | |
| Attach_6_Past_Performance_Questionnaire_1.docx | DOCX document | |
| Attch_4_DWGS.zip | ZIP file |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Section B - Supplies or Services and Prices
| ITEM NO |
| SUPPLIES/SERVICES |
| QUANTITY |
| UNIT |
| UNIT PRICE |
| AMOUNT |
| 1 |
| Lot |
HTHW Service Lines Phase 14
FFP
This project is for the repair and/or replacement of High temperature Hot Water Service Lines, Phase 14 at Malmstrom AFB, Montana. Work consists of the contractor providing all labor, equipment, transportation, materials, quality control, and supervision necessary to conduct all repair and maintenance requirements throughout Malmstrom AFB, Montana in accordance with the project specifications, drawings, and blueprints. **THIS LINE ITEM IS FOR THE OVERALL PROPOSED PRICE TRANSFERRED FROM THE ESTIMATED QUANTITIES SCHEDULE B CONTINUATION SHEET, ALL FUNDS WILL BE ATTRIBUTED TO THIS LINE ITEM. AWARD WILL BE ESTIMATED QUANTITIES**
FOB: Destination
NSN: Z2NZ-RP-HTH-WATR
SIGNAL CODE: A
NET AMT
SCHEDULE B CONTINUATION SHEET
SCHEDULE B CONTINUATION SHEET
ITEM
SUPPLIES/SERVICES
EST QTY
UNIT
UNIT PRICE
EST TOTAL
0001AA
Unidentified Utility
EA
Crossings
0001AB
Replace HTHW
LT
Service Lines
0001AC
Concrete Curb
LF
Removal & Replacement
0001AD
Asphalt Cutting
LF
0001AE
Asphalt Removal
LF
& Replacement
0001AF
Seeding
LF
0001AG
Sodding
LF
0001AH
Contaminated Soil
CY
Disposal
0001AJ
Clean Fill
CY
0001AK
Concrete Sidewalk
LF
Removal & Replacement
0001AL
Pre-Cast Manhole
EA
0001AM
Project Bonding Costs
EA
TOTAL ESTIMATED PROPOSED AMOUNT
Section C - Descriptions and Specifications
DESCRIPTIONS AND SPECIFICATION
Section C – Descriptions and Specifications
DESCRIPTIONS AND SPECIFICATIONS
C-1 SPECIFICATIONS, STANDARDS AND DRAWINGS IAW FAR 11-201
Furnish all labor, materials, supervision, quality control, testing, equipment and transportation necessary to perform the work required by the drawings and specifications applicable to Malmstrom AFB, Project No. NZAS: 10-1043A, dated: December 2013 and that are identified as attachments to this solicitation in Section J hereof.
Section E - Inspection and Acceptance
INSPECTION AND ACCEPTANCE TERMS
Supplies/services will be inspected/accepted at:
| CLIN |
| INSPECT AT |
| INSPECT BY |
| ACCEPT AT |
| ACCEPT BY |
| 0001 |
| Destination |
| Government |
| Destination |
| Government |
CLAUSES INCORPORATED BY REFERENCE
| 52.246-12 |
| Inspection of Construction |
| AUG 1996 |
Section F - Deliveries or Performance
DELIVERY INFORMATION
| CLIN |
| DELIVERY DATE |
| QUANTITY |
| SHIP TO ADDRESS |
| UIC |
| 0001 |
| 120 dys. ADC |
| 1 |
| F2W3D5 341CES/CECR-BASE SRMC |
KEN MURPHY
39 78TH ST N BLDG 470
MALMSTROM AFB MT 59402
406-731-6865
FOB: Destination F2W3D5
CLAUSES INCORPORATED BY FULL TEXT
52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984)
The Contractor shall be required to (a) commence work under this contract within 10 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 120 calendar days excluding the winter exclusion period from 22 Sept to 22 May of each calendar year. The time stated for completion shall include final cleanup of the premises.
(End of clause)
CLAUSES INCORPORATED BY FULL TEXT
52.211-12 LIQUIDATED DAMAGES--CONSTRUCTION (SEP 2000)
(a) If the Contractor fails to complete the work within the time specified in the contract, the Contractor shall pay liquidated damages to the Government in the amount of $355.89 for each calendar day of delay until the work is completed or accepted.
(b) If the Government terminates the Contractor's right to proceed, liquidated damages will continue to accrue until the work is completed. These liquidated damages are in addition to excess costs of repurchase under the Termination clause.
(End of clause)
Section G - Contract Administration Data
CLAUSES INCORPORATED BY FULL TEXT
252.232-7003 ELECTRONIC SUBMISSION OF PAYMENT REQUESTS AND RECEIVING REPORTS (JUNE 2012)
(a) Definitions. As used in this clause–
(1) Contract financing payment and invoice payment have the meanings given in section 32.001 of the Federal Acquisition Regulation.
(2) Electronic form means any automated system that transmits information electronically from the initiating system to all affected systems. Facsimile, e-mail, and scanned documents are not acceptable electronic forms for submission of payment requests. However, scanned documents are acceptable when they are part of a submission of a payment request made using Wide Area WorkFlow (WAWF) or another electronic form authorized by the Contracting Officer.
(3) Payment request means any request for contract financing payment or invoice payment submitted by the Contractor under this contract.
(4) Receiving report means the data required by the clause at 252.246-7000, Material Inspection and Receiving Report.
(b) Except as provided in paragraph (c) of this clause, the Contractor shall submit payment requests and receiving reports using WAWF, in one of the following electronic formats that WAWF accepts: Electronic Data Interchange, Secure File Transfer Protocol, or World Wide Web input. Information regarding WAWF is available on the Internet at https://wawf.eb.mil/.
(c) The Contractor may submit a payment request and receiving report using other than WAWF only when–
(1) The Contracting Officer administering the contract for payment has determined, in writing, that electronic submission would be unduly burdensome to the Contractor. In such cases, the Contractor shall include a copy of the Contracting Officer's determination with each request for payment;
(2) DoD makes payment for commercial transportation services provided under a Government rate tender or a contract for transportation services using a DoD-approved electronic third party payment system or other exempted vendor payment/invoicing system (e.g., PowerTrack, Transportation Financial Management System, and Cargo and Billing System);
(3) DoD makes payment for rendered health care services using the TRICARE Encounter Data System (TEDS) as the electronic format; or
(4) When the Governmentwide commercial purchase card is used as the method of payment, only submission of the receiving report in electronic form is required.
(d) The Contractor shall submit any non-electronic payment requests using the method or methods specified in Section G of the contract.
(e) In addition to the requirements of this clause, the Contractor shall meet the requirements of the appropriate payment clauses in this contract when submitting payments requests.
(End of clause)
Section I - Contract Clauses
CLAUSES INCORPORATED BY REFERENCE
| 52.202-1 |
| Definitions |
| NOV 2013 |
| 52.203-3 |
| Gratuities |
| APR 1984 |
| 52.203-5 |
| Covenant Against Contingent Fees |
| APR 1984 |
| 52.203-6 |
| Restrictions On Subcontractor Sales To The Government |
| SEP 2006 |
| 52.203-7 |
| Anti-Kickback Procedures |
| OCT 2010 |
| 52.203-8 |
| Cancellation, Rescission, and Recovery of Funds for Illegal or Improper Activity |
| JAN 1997 |
| 52.203-10 |
| Price Or Fee Adjustment For Illegal Or Improper Activity |
| JAN 1997 |
| 52.203-12 |
| Limitation On Payments To Influence Certain Federal Transactions |
| OCT 2010 |
| 52.204-4 |
| Printed or Copied Double-Sided on Postconsumer Fiber Content Paper |
| MAY 2011 |
| 52.204-7 |
| System for Award Management |
| JUL 2013 |
| 52.204-10 |
| Reporting Executive Compensation and First-Tier Subcontract Awards |
| JUL 2013 |
| 52.209-6 |
| Protecting the Government's Interest When Subcontracting With Contractors Debarred, Suspended, or Proposed for Debarment |
| AUG 2013 |
| 52.211-18 |
| Variation in Estimated Quantity |
| APR 1984 |
| 52.215-2 |
| Audit and Records--Negotiation |
| OCT 2010 |
| 52.215-8 |
| Order of Precedence--Uniform Contract Format |
| OCT 1997 |
| 52.215-11 |
| Price Reduction for Defective Certified Cost or Pricing Data--Modifications |
| AUG 2011 |
| 52.215-21 |
| Requirements for Certified Cost or Pricing Data or Information Other Than Certified Cost or Pricing Data--Modifications |
| OCT 2010 |
| 52.219-6 |
| Notice Of Total Small Business Set-Aside |
| NOV 2011 |
| 52.219-8 |
| Utilization of Small Business Concerns |
| JUL 2013 |
| 52.219-14 |
| Limitations On Subcontracting |
| NOV 2011 |
| 52.222-1 |
| Notice To The Government Of Labor Disputes |
| FEB 1997 |
| 52.222-3 |
| Convict Labor |
| JUN 2003 |
| 52.222-4 |
| Contract Work Hours and Safety Standards Act - Overtime Compensation |
| JUL 2005 |
| 52.222-6 |
| Davis Bacon Act |
| JUL 2005 |
| 52.222-7 |
| Withholding of Funds |
| FEB 1988 |
| 52.222-8 |
| Payrolls and Basic Records |
| JUN 2010 |
| 52.222-9 |
| Apprentices and Trainees |
| JUL 2005 |
| 52.222-10 |
| Compliance with Copeland Act Requirements |
| FEB 1988 |
| 52.222-11 |
| Subcontracts (Labor Standards) |
| JUL 2005 |
| 52.222-12 |
| Contract Termination-Debarment |
| FEB 1988 |
| 52.222-13 |
| Compliance with Davis-Bacon and Related Act Regulations. |
| FEB 1988 |
| 52.222-14 |
| Disputes Concerning Labor Standards |
| FEB 1988 |
| 52.222-15 |
| Certification of Eligibility |
| FEB 1988 |
| 52.222-21 |
| Prohibition Of Segregated Facilities |
| FEB 1999 |
| 52.222-26 |
| Equal Opportunity |
| MAR 2007 |
| 52.222-27 |
| Affirmative Action Compliance Requirements for Construction |
| FEB 1999 |
| 52.222-35 |
| Equal Opportunity for Veterans |
| SEP 2010 |
| 52.222-36 |
| Affirmative Action For Workers With Disabilities |
| OCT 2010 |
| 52.222-37 |
| Employment Reports on Veterans |
| SEP 2010 |
| 52.222-50 |
| Combating Trafficking in Persons |
| FEB 2009 |
| 52.223-3 Alt I |
| Hazardous Material Identification and Material Safety Data (Jan 1997) - Alternate I |
| JUL 1985 |
| 52.223-5 Alt I |
| Pollution Prevention and Right-to-Know Information (May 2011) Alternate I |
| MAY 2011 |
| 52.223-6 |
| Drug-Free Workplace |
| MAY 2001 |
| 52.223-9 |
| Estimate of Percentage of Recovered Material Content for EPA-Designated Items |
| MAY 2008 |
| 52.223-18 |
| Encouraging Contractor Policies To Ban Text Messaging While Driving |
| AUG 2011 |
| 52.225-13 |
| Restrictions on Certain Foreign Purchases |
| JUN 2008 |
| 52.225-25 |
| Prohibition on Contracting with Entities Engaging in Certain Activities or Transactions Relating to Iran-- Representation and Certifications. |
| DEC 2012 |
| 52.227-1 |
| Authorization and Consent |
| DEC 2007 |
| 52.227-2 |
| Notice And Assistance Regarding Patent And Copyright Infringement |
| DEC 2007 |
| 52.227-4 |
| Patent Indemnity-Construction Contracts |
| DEC 2007 |
| 52.228-2 |
| Additional Bond Security |
| OCT 1997 |
| 52.228-11 |
| Pledges Of Assets |
| JAN 2012 |
| 52.228-12 |
| Prospective Subcontractor Requests for Bonds |
| OCT 1995 |
| 52.228-14 |
| Irrevocable Letter of Credit |
| DEC 1999 |
| 52.228-15 |
| Performance and Payment Bonds--Construction |
| OCT 2010 |
| 52.229-3 |
| Federal, State And Local Taxes |
| FEB 2013 |
| 52.232-5 |
| Payments under Fixed-Price Construction Contracts |
| SEP 2002 |
| 52.232-17 |
| Interest |
| OCT 2010 |
| 52.232-18 |
| Availability Of Funds |
| APR 1984 |
| 52.232-23 |
| Assignment Of Claims |
| JAN 1986 |
| 52.232-27 |
| Prompt Payment for Construction Contracts |
| JUL 2013 |
| 52.232-33 |
| Payment by Electronic Funds Transfer--System for Award Management |
| JUL 2013 |
| 52.233-1 |
| Disputes |
| JUL 2002 |
| 52.233-3 |
| Protest After Award |
| AUG 1996 |
| 52.233-4 |
| Applicable Law for Breach of Contract Claim |
| OCT 2004 |
| 52.236-2 |
| Differing Site Conditions |
| APR 1984 |
| 52.236-3 |
| Site Investigation and Conditions Affecting the Work |
| APR 1984 |
| 52.236-5 |
| Material and Workmanship |
| APR 1984 |
| 52.236-6 |
| Superintendence by the Contractor |
| APR 1984 |
| 52.236-7 |
| Permits and Responsibilities |
| NOV 1991 |
| 52.236-8 |
| Other Contracts |
| APR 1984 |
| 52.236-9 |
| Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements |
| APR 1984 |
| 52.236-10 |
| Operations and Storage Areas |
| APR 1984 |
| 52.236-11 |
| Use and Possession Prior to Completion |
| APR 1984 |
| 52.236-12 |
| Cleaning Up |
| APR 1984 |
| 52.236-13 |
| Accident Prevention |
| NOV 1991 |
| 52.236-14 |
| Availability and Use of Utility Services |
| APR 1984 |
| 52.236-15 |
| Schedules for Construction Contracts |
| APR 1984 |
| 52.236-17 |
| Layout of Work |
| APR 1984 |
| 52.236-21 Alt I |
| Specifications and Drawings for Construction (Feb 1997) - Alternate I |
| APR 1984 |
| 52.236-26 |
| Preconstruction Conference |
| FEB 1995 |
| 52.242-13 |
| Bankruptcy |
| JUL 1995 |
| 52.242-14 |
| Suspension of Work |
| APR 1984 |
| 52.243-4 |
| Changes |
| JUN 2007 |
| 52.244-5 |
| Competition In Subcontracting |
| DEC 1996 |
| 52.244-6 |
| Subcontracts for Commercial Items |
| JUL 2013 |
| 52.246-21 |
| Warranty of Construction |
| MAR 1994 |
| 52.248-3 |
| Value Engineering-Construction |
| OCT 2010 |
| 52.249-2 Alt I |
| Termination for Convenience of the Government (Fixed-Price) (Apr 2012) - Alternate I |
| SEP 1996 |
| 52.249-10 |
| Default (Fixed-Price Construction) |
| APR 1984 |
| 52.253-1 |
| Computer Generated Forms |
| JAN 1991 |
| 252.203-7001 |
| Prohibition On Persons Convicted of Fraud or Other Defense-Contract-Related Felonies |
| DEC 2008 |
| 252.204-7003 |
| Control Of Government Personnel Work Product |
| APR 1992 |
| 252.204-7004 Alt A |
| System for Award Management Alternate A |
| MAY 2013 |
| 252.209-7004 |
| Subcontracting With Firms That Are Owned or Controlled By The Government of a Terrorist Country |
| DEC 2006 |
| 252.215-7000 |
| Pricing Adjustments |
| DEC 2012 |
| 252.223-7001 |
| Hazard Warning Labels |
| DEC 1991 |
| 252.223-7006 |
| Prohibition On Storage And Disposal Of Toxic And Hazardous Materials |
| APR 2012 |
| 252.225-7012 |
| Preference For Certain Domestic Commodities |
| FEB 2013 |
| 252.226-7001 |
| Utilization of Indian Organizations and Indian-Owned Economic Enterprises, and Native Hawaiian Small Business Concerns |
| SEP 2004 |
| 252.227-7033 |
| Rights in Shop Drawings |
| APR 1966 |
| 252.232-7010 |
| Levies on Contract Payments |
| DEC 2006 |
| 252.236-7000 |
| Modification Proposals-Price Breakdown |
| DEC 1991 |
| 252.236-7006 |
| Cost Limitation |
| JAN 1997 |
| 252.243-7001 |
| Pricing Of Contract Modifications |
| DEC 1991 |
| 252.243-7002 |
| Requests for Equitable Adjustment |
| DEC 2012 |
| 252.247-7024 |
| Notification Of Transportation Of Supplies By Sea |
| MAR 2000 |
52.223-11 OZONE-DEPLETING SUBSTANCES (MAY 2001)
(a) Definition. Ozone-depleting substance, as used in this clause, means any substance the Environmental Protection Agency designates in 40 CFR part 82 as--
(1) Class I, including, but not limited to, chlorofluorocarbons, halons, carbon tetrachloride, and methyl chloroform; or
(2) Class II, including, but not limited to, hydrochlorofluorocarbons.
(b) The Contractor shall label products which contain or are manufactured with ozone-depleting substances in the manner and to the extent required by 42 U.S.C. 7671j (b), (c), and (d) and 40 CFR Part 82, Subpart E, as follows:
“WARNING: Contains (or manufactured with, if applicable), a substance(s) which harm(s) public health and environment by destroying ozone in the upper atmosphere.”----------------------------
The Contractor shall insert the name of the substance(s).
(End of clause)
52.225-9 BUY AMERICAN ACT—CONSTRUCTION MATERIALS (SEP 2010)
(a) Definitions. As used in this clause--
Commercially available off-the-shelf (COTS) item—
(1) Means any item of supply (including construction material) that is--
(i) A commercial item (as defined in paragraph (1) of the definition at FAR 2.101);
(ii) Sold in substantial quantities in the commercial marketplace; and
(iii) Offered to the Government, under a contract or subcontract at any tier, without modification, in the same form in which it is sold in the commercial marketplace; and
(2) Does not include bulk cargo, as defined in section 3 of the Shipping Act of 1984 (46 U.S.C. App. 1702), such as agricultural products and petroleum products.
Component means an article, material, or supply incorporated directly into a construction material.
Construction material means an article, material, or supply brought to the construction site by the Contractor or a subcontractor for incorporation into the building or work. The term also includes an item brought to the site preassembled from articles, materials, or supplies. However, emergency life safety systems, such as emergency lighting, fire alarm, and audio evacuation systems, that are discrete systems incorporated into a public building or work and that are produced as complete systems, are evaluated as a single and distinct construction material regardless of when or how the individual parts or components of those systems are delivered to the construction site. Materials purchased directly by the Government are supplies, not construction material.
Cost of components means--
(1) For components purchased by the Contractor, the acquisition cost, including transportation costs to the place of incorporation into the construction material (whether or not such costs are paid to a domestic firm), and any applicable duty (whether or not a duty-free entry certificate is issued); or
(2) For components manufactured by the Contractor, all costs associated with the manufacture of the component, including transportation costs as described in paragraph (1) of this definition, plus allocable overhead costs, but excluding profit. Cost of components does not include any costs associated with the manufacture of the construction material.
Domestic construction material means--
(1) An unmanufactured construction material mined or produced in the United States;
(2) A construction material manufactured in the United States, if--
(i) The cost of its components mined, produced, or manufactured in the United States exceeds 50 percent of the cost of all its components. Components of foreign origin of the same class or kind for which nonavailability determinations have been made are treated as domestic; or
(ii) The construction material is a COTS item.
Foreign construction material means a construction material other than a domestic construction material.
United States means the 50 States, the District of Columbia, and outlying areas.
(b) Domestic preference.
(1) This clause implements the Buy American Act (41 U.S.C. 10a-10d) by providing a preference for domestic construction material. In accordance with 41 U.S.C. 431, the component test of the Buy American Act is waived for construction material that is a COTS item (See FAR 12.505(a)(2)). The Contractor shall use only domestic construction material in performing this contract, except as provided in paragraphs (b)(2) and (b)(3) of this clause.
(2) This requirement does not apply to information technology that is a commercial item or to the construction materials or components listed by the Government as follows:
(3) The Contracting Officer may add other foreign construction material to the list in paragraph (b)(2) of this clause if the Government determines that
(i) The cost of domestic construction material would be unreasonable. The cost of a particular domestic construction material subject to the requirements of the Buy American Act is unreasonable when the cost of such material exceeds the cost of foreign material by more than 6 percent;
(ii) The application of the restriction of the Buy American Act to a particular construction material would be impracticable or inconsistent with the public interest; or
(iii) The construction material is not mined, produced, or manufactured in the United States in sufficient and reasonably available commercial quantities of a satisfactory quality.
(c) Request for determination of inapplicability of the Buy American Act. (1)(i) Any Contractor request to use foreign construction material in accordance with paragraph (b)(3) of this clause shall include adequate information for Government evaluation of the request, including--
(A) A description of the foreign and domestic construction materials;
(B) Unit of measure;
(C) Quantity;
(D) Price;
(E) Time of delivery or availability;
(F) Location of the construction project;
(G) Name and address of the proposed supplier; and
(H) A detailed justification of the reason for use of foreign construction materials cited in accordance with paragraph (b)(3) of this clause.
(ii) A request based on unreasonable cost shall include a reasonable survey of the market and a completed price comparison table in the format in paragraph (d) of this clause.
(iii) The price of construction material shall include all delivery costs to the construction site and any applicable duty (whether or not a duty-free certificate may be issued).
(iv) Any Contractor request for a determination submitted after contract award shall explain why the Contractor could not reasonably foresee the need for such determination and could not have requested the determination before contract award. If the Contractor does not submit a satisfactory explanation, the Contracting Officer need not make a determination.
(2) If the Government determines after contract award that an exception to the Buy American Act applies and the Contracting Officer and the Contractor negotiate adequate consideration, the Contracting Officer will modify the contract to allow use of the foreign construction material. However, when the basis for the exception is the unreasonable price of a domestic construction material, adequate consideration is not less than the differential established in paragraph (b)(3)(i) of this clause.
(3) Unless the Government determines that an exception to the Buy American Act applies, use of foreign construction material is noncompliant with the Buy American Act.
(d) Data. To permit evaluation of requests under paragraph (c) of this clause based on unreasonable cost, the Contractor shall include the following information and any applicable supporting data based on the survey of suppliers:
Foreign and Domestic Construction Materials Price Comparison
Construction material description Unit of measure Quantity Price (dollars) \1\
Item 1
Foreign construction material
Domestic construction material
Item 2
Foreign construction material
Domestic construction material
Include all delivery costs to the construction site and any applicable duty (whether or not a duty-free entry certificate is issued).
List name, address, telephone number, and contact for suppliers surveyed. Attach copy of response; if oral, attach summary.
Include other applicable supporting information.
(End of clause)
CLAUSES INCORPORATED BY FULL TEXT
52.225-10 NOTICE OF BUY AMERICAN ACT REQUIREMENT--CONSTRUCTION MATERIALS (FEB 2009)
(a) Definitions. “Commercially available off-the-shelf (COTS) item,” “construction material,” “domestic construction material,” and “foreign construction material,” as used in this provision, are defined in the clause of this solicitation entitled “Buy American Act--Construction Materials” (Federal Acquisition Regulation (FAR) clause 52.225-9).
(b) Requests for determinations of inapplicability. An offeror requesting a determination regarding the inapplicability of the Buy American Act should submit the request to the Contracting Officer in time to allow a determination before submission of offers. The offeror shall include the information and applicable supporting data required by paragraphs (c) and (d) of the clause at FAR 52.225-9 in the request. If an offeror has not requested a determination regarding the inapplicability of the Buy American Act before submitting its offer, or has not received a response to a previous request, the offeror shall include the information and supporting data in the offer.
(c) Evaluation of offers. (1) The Government will evaluate an offer requesting exception to the requirements of the Buy American Act, based on claimed unreasonable cost of domestic construction material, by adding to the offered price the appropriate percentage of the cost of such foreign construction material, as specified in paragraph (b)(3)(i) of the clause at FAR 52.225-9.
(2) If evaluation results in a tie between an offeror that requested the substitution of foreign construction material based on unreasonable cost and an offeror that did not request an exception, the Contracting Officer will award to the offeror that did not request an exception based on unreasonable cost.
(d) Alternate offers.
(1) When an offer includes foreign construction material not listed by the Government in this solicitation in paragraph (b)(2) of the clause at FAR 52.225-9, the offeror also may submit an alternate offer based on use of equivalent domestic construction material.
(2) If an alternate offer is submitted, the offeror shall submit a separate Standard Form 1442 for the alternate offer, and a separate price comparison table prepared in accordance with paragraphs (c) and (d) of the clause at FAR 52.225-9 for the offer that is based on the use of any foreign construction material for which the Government has not yet determined an exception applies.
(3) If the Government determines that a particular exception requested in accordance with paragraph (c) of the clause at FAR 52.225-9 does not apply, the Government will evaluate only those offers based on use of the equivalent domestic construction material, and the offeror shall be required to furnish such domestic construction material. An offer based on use of the foreign construction material for which an exception was requested--
(i) Will be rejected as nonresponsive if this acquisition is conducted by sealed bidding; or
(ii) May be accepted if revised during negotiations.
(End of provision)
CLAUSES INCORPORATED BY FULL TEXT
52.228-5 INSURANCE--WORK ON A GOVERNMENT INSTALLATION (JAN 1997)
(a) The Contractor shall, at its own expense, provide and maintain during the entire performance of this contract, at least the kinds and minimum amounts of insurance required in the Schedule or elsewhere in the contract.
(b) Before commencing work under this contract, the Contractor shall notify the Contracting Officer in writing that the required insurance has been obtained. The policies evidencing required insurance shall contain an endorsement to the effect that any cancellation or any material change adversely affecting the Government's interest shall not be effective (1) for such period as the laws of the State in which this contract is to be performed prescribe, or (2) until 30 days after the insurer or the Contractor gives written notice to the Contracting Officer, whichever period is longer.
(c) The Contractor shall insert the substance of this clause, including this paragraph (c), in subcontracts under this contract that require work on a Government installation and shall require subcontractors to provide and maintain the insurance required in the Schedule or elsewhere in the contract. The Contractor shall maintain a copy of all subcontractors' proofs of required insurance, and shall make copies available to the Contracting Officer upon request.
(End of clause)
CLAUSES INCORPORATED BY FULL TEXT
52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)
This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es):
http://Farsite.hill.af.mil http://www.acq.osd.mil/dpap/dars/dfars/index.htm (End of clause)
CLAUSES INCORPORATED BY FULL TEXT
52.252-6 AUTHORIZED DEVIATIONS IN CLAUSES (APR 1984)
(a) The use in this solicitation or contract of any Federal Acquisition Regulation (48 CFR Chapter 1) clause with an authorized deviation is indicated by the addition of "(DEVIATION)" after the date of the clause.
(b) The use in this solicitation or contract of any DoD Supplement (48 CFR Chapter 2) clause with an authorized deviation is indicated by the addition of "(DEVIATION)" after the name of the regulation.
(End of clause)
CLAUSES INCORPORATED BY FULL TEXT
252.236-7001 CONTRACT DRAWINGS AND SPECIFICATIONS (AUG 2000)
(a) The Government will provide to the Contractor, without charge, one set of contract drawings and specifications, except publications incorporated into the technical provisions by reference, in electronic or paper media as chosen by the Contracting Officer.
(b) The Contractor shall--
(1) Check all drawings furnished immediately upon receipt;
(2) Compare all drawings and verify the figures before laying out the work;
(3) Promptly notify the Contracting Officer of any discrepancies;
(4) Be responsible for any errors that might have been avoided by complying with this paragraph (b); and
(5) Reproduce and print contract drawings and specifications as needed.
(c) In general--
(1) Large-scale drawings shall govern small-scale drawings; and
(2) The Contractor shall follow figures marked on drawings in preference to scale measurements.
(d) Omissions from the drawings or specifications or the misdescription of details of work that are manifestly necessary to carry out the intent of the drawings and specifications, or that are customarily performed, shall not relieve the Contractor from performing such omitted or misdescribed details of the work. The Contractor shall perform such details as if fully and correctly set forth and described in the drawings and specifications.
(e) The work shall conform to the specifications and the contract drawings identified on the following index of drawings:
SCHEDULE OF DRAWINGS
C1.1
COVER SHEET
C1.2
LEGEND, ABBREVIATIONS, NOTES & SCHEDULES
C2.1
HTHW DISTRIBUTION MAP
M5.1
BUILDINGS 1460, 3080, & 3081
M12.1
BUILDING 1450
M16.1
HTHW DETAILS
M17.1
HTHW DETAILS
M17.2
HTHW DETAILS
M17.3
MANHOLE DETAILS
M17.4
MANHOLE DETAILS
M17.5 FORCE PROTECTION & DRAINAGE DETAILS
(End of clause)
OMBUDSMAN (NOV 2012)
(a) An ombudsman has been appointed to hear and facilitate the resolution of concerns from offerors, potential offerors, and others for this acquisition. When requested, the ombudsman will maintain strict confidentiality as to the source of the concern. The existence of the ombudsman does not affect the authority of the program manager, contracting officer, or source selection official. Further, the ombudsman does not participate in the evaluation of proposals, the source selection process, or the adjudication of protests or formal contract disputes. The ombudsman may refer the interested party to another official who can resolve the concern.
(b) Before consulting with an ombudsman, interested parties must first address their concerns, issues, disagreements, and/or recommendations to the contracting officer for resolution. Consulting an ombudsman does not alter or postpone the timelines for any other processes (e.g., agency level bid protests, GAO bid protests, requests for debriefings, employee-employer actions, contests of OMB Circular A-76 competition performance decisions).
(c) If resolution cannot be made by the contracting officer, the interested party may contact the Center/MAJCOM ombudsman, HQ AF Global Strike Command/AFICA/KG, 66 Kenney Ave, Ste 233, Barksdate AFB, LA 71110, 318-456-6336.. Concerns, issues, disagreements, and recommendations that cannot be resolved at the Center/MAJCOM/DRU/AFISRA ombudsman level, may be brought by the interested party for further consideration to the Air Force ombudsman, Associate Deputy Assistant Secretary (ADAS) (Contracting), SAF/AQC, 1060 Air Force Pentagon, Washington DC 20330-1060, phone number (571) 256-2395, facsimile number (571) 256-2431.
(d) The ombudsman has no authority to render a decision that binds the agency.
(e) Do not contact the ombudsman to request copies of the solicitation, verify offer due date, or clarify technical requirements. Such inquiries shall be directed to the Contracting Officer.
(End of clause)
5352.242-9000 CONTRACTOR ACCESS TO AIR FORCE INSTALLATIONS (AUG 2007)
(a) The contractor shall obtain base identification and vehicle passes for all contractor personnel who make frequent visits to or perform work on the Air Force installation(s) cited in the contract. Contractor personnel are required to wear or prominently display installation identification badges or contractor-furnished, contractor identification badges while visiting or performing work on the installation.
(b) The contractor shall submit a written request on company letterhead to the contracting officer listing the following: contract number, location of work site, start and stop dates, and names of employees and subcontractor employees needing access to the base. The letter will also specify the individual(s) authorized to sign for a request for base identification credentials or vehicle passes. The contracting officer will endorse the request and forward it to the issuing base pass and registration office or security police for processing. When reporting to the registration office, the authorized contractor individual(s) should provide a valid driver’s license, current vehicle registration, and valid vehicle insurance certificate, in order to obtain a vehicle pass.
(c) During performance of the contract, the contractor shall be responsible for obtaining required identification for newly assigned personnel and for prompt return of credentials and vehicle passes for any employee who no longer requires access to the work site.
(d) When work under this contract requires unescorted entry to controlled or restricted areas, the contractor shall comply with AFI 31-101, Volume 1, The Air Force Installation Security Program, and AFI 31-501, Personnel Security Program Management, as applicable.
(e) Upon completion or termination of the contract or expiration of the identification passes, the prime contractor shall ensure that all base identification passes issued to employees and subcontractor employees are returned to the issuing office.
(f) Failure to comply with these requirements may result in withholding of final payment.
(End of clause)
MALM I-2 General Insurance Requirements
(a) Workers’ compensation and employer’s liability. Contractors are required to comply with applicable Federal and State workers’ compensation and occupational disease statutes. If occupational diseases are not compensable under those statutes, they shall be covered under the employer’s liability section of the insurance policy, except when contract operations are so commingled with a contractor’s commercial operations that it would not be practical to require this coverage. Employer’s liability coverage of at least $1,000,000 shall be required, except in States with exclusive or monopolistic funds that do not permit workers’ compensation to be written by private carriers. (See 28.305(c) for treatment of contracts subject to the Defense Base Act.)
(b) General liability.
(1) The contracting officer shall require bodily injury liability insurance coverage written on the comprehensive form of policy of at least $1,000,000 per occurrence.
(2) Property damage liability insurance shall be required only in special circumstances as determined by the agency.
(c) Company Owned Automobile liability. The contracting officer shall require automobile liability insurance written on the comprehensive form of policy. The policy shall provide for bodily injury and property damage liability covering the operation of all automobiles used in connection with performing the contract. Policies covering automobiles operated in the United States shall provide coverage of at least $500,000 per person and $1,000,000 per occurrence for bodily injury and $50,000 per occurrence for property damage. The amount of liability coverage on other policies shall be commensurate with any legal requirements of the locality and sufficient to meet normal and customary claims.
Section J - List of Documents, Exhibits and Other Attachments
LIST OF DOCUMENTS, EXHIBITS
Section J - List of Documents, Exhibits and Other Attachments
LIST OF DOCUMENTS
SECTION J
LIST OF ATTACHMENTS
ITEM NUMBER
SPECIFICATIONS, STANDARDS AND/OR ATTACHMENTS
Attach 1 Technical Specifications, Repair High Temperature Hot Water Service Lines, Phase 14, Malmstrom AFB, MT. Project Number NZAS 10-1043A, Cover page through Section 16120 dated December 2013.
Attach 2
Submittal Schedule, dated December 2013 page SS1 thru SS4
Attach 3
Schedule of Drawings, page 1 of 1
Attach 4
Drawings, pages C1.1 through M17.5
Attach 5
Wage Determination MT140067 dated 3 January 2014 pages 1 through 11 Attach 6
Past Performance Questionnaire, pages 1 through 4
Attach 7
Subcontractor Consent Form, pages 1 and 2
Attach 8
Installation Perimeter Access Control Letter dated 3 Feb 2012 NOTE!! IT IS THE RESPONSIBILITY OF THE OFFEROR TO SEND THE PAST PERFORMANCE QUESTIONNAIRE TO THE PREVIOUS CUSTOMERS WHICH THE OFFEROR HAS PROVIDED CONSTRUCTION SERVICES DURING THE PAST FIVE YEARS. THE CUSTOMER MUST COMPLETE THE QUESTIONNAIRE, THEN SEND THE COMPLETED QUESTIONNAIRE TO THE FOLLOWING ADDRESS NO LATER THAN THE CLOSING DATE OF THE SOLICITATION.
341 CONTRACTING SQUADRON
ATTN: Mark Jefferson
7015 Goddard Drive
Malmstrom AFB, MT 59402-6863
THE COMPLETED QUESTIONNAIRE MUST CONTAIN THE CUSTOMERS FULL NAME, ADDRESS, TELEPHONE NUMBER, TYPE OF CONSTRCTION WORK THAT WAS PERFORMED AND THE DATE THE WORK WAS COMPLETED.
Section K - Representations, Certifications and Other Statements of Offerors
CLAUSES INCORPORATED BY REFERENCE
| 52.236-28 |
| Preparation of Proposals--Construction |
| OCT 1997 |
52.204-8 ANNUAL REPRESENTATIONS AND CERTIFICATIONS (JULY 2013)
(a)(1) The North American Industry Classification System (NAICS) code for this acquisition is 238220.
(2) The small business size standard is $14,000,000.00.
(3) The small business size standard for a concern which submits an offer in its own name, other than on a construction or service contract, but which proposes to furnish a product which it did not itself manufacture, is 500 employees.
(b)(1) If the provision at 52.204-7, Central Contractor Registration, is included in this solicitation, paragraph (d) of this provision applies.
(2) If the provision at 52.204-7 is not included in this solicitation, and the offeror is currently registered in CCR, and has completed the ORCA electronically, the offeror may choose to use paragraph (d) of this provision instead of completing the corresponding individual representations and certifications in the solicitation. The offeror shall indicate which option applies by checking one of the following boxes:
( ) Paragraph (d) applies.
( ) Paragraph (d) does not apply and the offeror has completed the individual representations and certifications in the solicitation.
(c)(1) The following representations or certifications in ORCA are applicable to this solicitation as indicated:
(i) 52.203-2, Certificate of Independent Price Determination. This provision applies to solicitations when a firm-fixed-price contract or fixed-price contract with economic price adjustment is contemplated, unless--
(A) The acquisition is to be made under the simplified acquisition procedures in Part 13;
(B) The solicitation is a request for technical proposals under two-step sealed bidding procedures; or
(C) The solicitation is for utility services for which rates are set by law or regulation.
(ii) 52.203-11, Certification and Disclosure Regarding Payments to Influence Certain Federal Transactions. This provision applies to solicitations expected to exceed $150,000.
(iii) 52.204-3, Taxpayer Identification. This provision applies to solicitations that do not include the provision at 52.204-7, Central Contractor Registration.
(iv) 52.204-5, Women-Owned Business (Other Than Small Business).This provision applies to solicitations that--
(A) Are not set aside for small business concerns;
(B) Exceed the simplified acquisition threshold; and
(C) Are for contracts that will be performed in the United States or its outlying areas.
(v) 52.209-2, Prohibition on Contracting with Inverted Domestic Corporations--Representation. This provision applies to solicitations using funds appropriated in fiscal years 2008, 2009, 2010, or 2012.
(vi) 52.209-5, Certification Regarding Responsibility Matters. This provision applies to solicitations where the contract value is expected to exceed the simplified acquisition threshold.
(vii) 52.223-5, Pollution Prevention and Right-to-Know Information (May 2011) (E.O. 13423) (Applies to services performed on Federal facilities).
(viii) 52.215-6, Place of Performance. This provision applies to solicitations unless the place of performance is specified by the Government.
(ix) 52.219-1, Small Business Program Representations (Basic & Alternate I). This provision applies to solicitations when the contract will be performed in the United States or its outlying areas.
(A) The basic provision applies when the solicitations are issued by other than DoD, NASA, and the Coast Guard.
(B) The provision with its Alternate I applies to solicitations issued by DoD, NASA, or the Coast Guard.
(x) 52.219-2, Equal Low Bids. This provision applies to solicitations when contracting by sealed bidding and the contract will be performed in the United States or its outlying areas.
(xi) 52.222-22, Previous Contracts and Compliance Reports. This provision applies to solicitations that include the clause at 52.222-26, Equal Opportunity.
(xii) 52.222-25, Affirmative Action Compliance. This provision applies to solicitations, other than those for construction, when the solicitation includes the clause at 52.222-26, Equal Opportunity.
(xiii) 52.222-38, Compliance with Veterans' Employment Reporting Requirements. This provision applies to solicitations when it is anticipated the contract award will exceed the simplified acquisition threshold and the contract is not for acquisition of commercial items.
(xiv) 52.223-1, Biobased Product Certification. This provision applies to solicitations that require the delivery or specify the use of USDA-designated items; or include the clause at 52.223-2, Affirmative Procurement of Biobased Products Under Service and Construction Contracts.
(xv) 52.223-4, Recovered Material Certification. This provision applies to solicitations that are for, or specify the use of, EPA-designated items.
(xvi) 52.225-2, Buy American Act Certificate. This provision applies to solicitations containing the clause at 52.225-1.
(xvii) 52.225-4, Buy American Act--Free Trade Agreements--Israeli Trade Act Certificate. (Basic, Alternates I, II, and III.) This provision applies to solicitations containing the clause at 52.225-3.
(A) If the acquisition value is less than $25,000, the basic provision applies.
(B) If the acquisition value is $25,000 or more but is less than $50,000, the provision with its Alternate I applies.
(C) If the acquisition value is $50,000 or more but is less than $77,494, the provision with its Alternate II applies.
(D) If the acquisition value is $77,494 or more but is less than $100,000, the provision with its Alternate III applies.
(xviii) 52.225-6, Trade Agreements Certificate. This provision applies to solicitations containing the clause at 52.225-5.
(xix) 52.225-20, Prohibition on Conducting Restricted Business Operations in Sudan--Certification. This provision applies to all solicitations.
(xx) 52.225-25, Prohibition on Contracting with Entities Engaging in Certain Activities or Transactions Relating to Iran--Representation and Certifications. This provision applies to all solicitations.
(xxi) 52.226-2, Historically Black College or University and Minority Institution Representation. This provision applies to--
(A) Solicitations for research, studies, supplies, or services of the type normally acquired from higher educational institutions; and
(B) For DoD, NASA, and Coast Guard acquisitions, solicitations that contain the clause at 52.219-23, Notice of Price Evaluation Adjustment for Small Disadvantaged Business Concerns.
(2) The following certifications are applicable as indicated by the Contracting Officer:
(Contracting Officer check as appropriate.)
(i) 52.219-22, Small Disadvantaged Business Status.
(A) Basic.
(B) Alternate I.
(ii) 52.222-18, Certification Regarding Knowledge of Child Labor for Listed End Products.
(iii) 52.222-48, Exemption from Application of the Service Contract Act to Contracts for Maintenance, Calibration, or Repair of Certain Equipment Certification.
(iv) 52.222-52, Exemption from Application of the Service Contract Act to Contracts for Certain Services–Certification.
(v) 52.223-9, with its Alternate I, Estimate of Percentage of Recovered Material Content for EPA–Designated Products (Alternate I only).
(vi) 52.227-6, Royalty Information.
(A) Basic.
(B) Alternate I.
(vii) 52.227-15, Representation of Limited Rights Data and Restricted Computer Software.
(d) The offeror has completed the annual representations and certifications electronically via the Online Representations and Certifications Application (ORCA) website accessed through https://www.acquisition.gov. After reviewing the ORCA database information, the offeror verifies by submission of the offer that the representations and certifications currently posted electronically that apply to this solicitation as indicated in paragraph (c) of this provision have been entered or updated within the last 12 months, are current, accurate, complete, and applicable to this solicitation (including the business size standard applicable to the NAICS code referenced for this solicitation), as of the date of this offer and are incorporated in this offer by reference (see FAR 4.1201); except for the changes identified below [offeror to insert changes, identifying change by clause number, title, date]. These amended representation(s) and/or certification(s) are also incorporated in this offer and are current, accurate, and complete as of the date of this offer.
FAR Clause Title Date Change
Any changes provided by the offeror are applicable to this solicitation only, and do not result in an update to the representations and certifications posted on SAM.
(End of provision)
Section L - Instructions, Conditions and Notices to Bidders
CLAUSES INCORPORATED BY REFERENCE
| 52.211-6 |
| Brand Name or Equal |
| AUG 1999 |
| 52.215-1 |
| Instructions to Offerors--Competitive Acquisition |
| JAN 2004 |
52.216-1 TYPE OF CONTRACT (APR 1984)
The Government contemplates award of a Firm Fixed Price contract resulting from this solicitation.
(End of provision)
52.222-23 NOTICE OF REQUIREMENT FOR AFFIRMATIVE ACTION TO ENSURE EQUAL EMPLOYMENT OPPORTUNITY FOR CONSTRUCTION (FEB 1999)
(a) The offeror's attention is called to the Equal Opportunity clause and the Affirmative Action Compliance Requirements for Construction clause of this solicitation.
(b) The goals for minority and female participation, expressed in percentage terms for the Contractor's aggregate workforce in each trade on all construction work in the covered area, are as follows:
| Goals for minority participation for each trade |
| Goals for female participation for each trade |
| 3.2% |
| 6.9% |
These goals are applicable to all the Contractor's construction work performed in the covered area. If the Contractor performs construction work in a geographical area located outside of the covered area, the Contractor shall apply the goals established for the geographical area where the work is actually performed. Goals are published periodically in the Federal Register in notice form, and these notices may be obtained from any Office of Federal Contract Compliance Programs office.
(c) The Contractor's compliance with Executive Order 11246, as amended, and the regulations in 41 CFR 60-4 shall be based on (1) its implementation of the Equal Opportunity clause, (2) specific affirmative action obligations required by the clause entitled "Affirmative Action Compliance Requirements for Construction,'' and (3) its efforts to meet the goals. The hours of minority and female employment and training must be substantially uniform throughout the length of the contract, and in each trade. The Contractor shall make a good faith effort to employ minorities and women evenly on each of its projects. The transfer of minority or female employees or trainees from Contractor to Contractor, or from project to project, for the sole purpose of meeting the Contractor's goals shall be a violation of the contract, Executive Order 11246, as amended, and the regulations in 41 CFR 60-4. Compliance with the goals will be measured against the total work hours performed.
(d) The Contractor shall provide written notification to the Deputy Assistant Secretary for Federal Contract Compliance, U.S. Department of Labor, within 10 working days following award of any construction subcontract in excess of $10,000 at any tier for construction work under the contract resulting from this solicitation. The notification shall list the --
(1) Name, address, and telephone number of the subcontractor;
(2) Employer's identification number of the subcontractor;
(3) Estimated dollar amount of the subcontract;
(4) Estimated starting and completion dates of the subcontract; and
(5) Geographical area in which the subcontract is to be performed.
(e) As used in this Notice, and in any contract resulting from this solicitation, the "covered area" is Malmstrom AFB, Great Falls, MT in the County of Cascade.
(End of provision)
52.233-2 SERVICE OF PROTEST (SEP 2006)
(a) Protests, as defined in section 33.101 of the Federal Acquisition Regulation, that are filed directly with an agency, and copies of any protests that are filed with the Government Accountability Office (GAO), shall be served on the Contracting Officer (addressed as follows) by obtaining written and dated acknowledgment of receipt from Mark Jefferson, 7015 Goddard Drive, Bldg 145, Malmstrom AFB, MT 59402
(b) The copy of any protest shall be received in the office designated above within one day of filing a protest with the GAO.
(End of provision)
52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) – ALTERNATE I (FEB 1995)
(a) The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigations and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, offerors or quoters are urged and expected to inspect the site where the work will be performed.
(b) An organized site visit has been scheduled for--
26 February 2014 at 1:30 pm Mountain Time
(c) Participants will meet at--
Contracting Office, 7015 Goddard Drive, Bldg 145, Malmstrom AFB, MT 59402
(End of provision)
52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998)
This solicitation incorporates one or more solicitation provisions by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. The offeror is cautioned that the listed provisions may include blocks that must be completed by the offeror and submitted with its quotation or offer. In lieu of submitting the full text of those provisions, the offeror may identify the provision by paragraph identifier and provide the appropriate information with its quotation or offer. Also, the full text of a solicitation provision may be accessed electronically at this/these address(es):
http://www.acqw.osd.mil/dpap/dars/dfars/index.htm http://farsite.hill.af.mil (End of provision)
52.252-5 AUTHORIZED DEVIATIONS IN PROVISIONS (APR 1984)
(a) The use in this solicitation of any Federal Acquisition Regulation (48 CFR Chapter 1) provision with an authorized deviation is indicated by the addition of"(DEVIATION)" after the date of the provision.
(b) The use in this solicitation of any DoD FAR Supplement (48 CFR Chapter 2) provision with an authorized deviation is indicated by the addition of "(DEVIATION)" after the name of the regulation.
(End of provision)
L-1-PPT_Rev 8 Aug 11
PROPOSAL PREPARATION INSTRUCTIONS
A. To assure timely and equitable evaluation of proposals, offerors must follow the instructions contained herein.