preproposal site visit.doc

DOC document 56 KB Posted

Attached to
RECOVERY-- NZAS061001F - Repair High Temp Hot Water Service Lines
Solicitation number
FA4626-09-R-0019
Issued by

View the file

Other files

File Type Posted
Wage Det MT1, 5-8-09.pdf PDF
Recovery Act - 09-R-0019, Amend 0002.pdf PDF
HTHW Svc Lines Submittal Sch_Atch 2.xls XLS spreadsheet
Past Performance Survey_Atch 6.docx DOCX document
Wage Determination_Atch 5.docx DOCX document
DWGS_ Atch 4.zip ZIP file
FA4626-09-R-0019, Amendment 0001.doc DOC document
Cover sheets.docx DOCX document
Sol FA4626-09-R-0019, HTHW Ph7.doc DOC document
SPECS_Atch 1.zip ZIP file
SCHEDULE OF DRAWINGS_Atch 3.doc DOC document
Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

5 May 2009

MEMORANDUM FOR RECORD

FROM: 341 Comptroller/Contracting Squadron

7015 Goddard Drive, Bldg 145

Malmstrom AFB, MT 59402 SUBJECT: Pre-Proposal Site Visit FA4626-09-R-0019 (Repair/Replace HTHW Phase 7)

1. A pre-proposal site visit was conducted on 4 May 2009 at 1:00 pm for the above identified solicitation. At this time no questions have been submitted in writing to this contracting office. If written questions are submitted they will be answered in writing and posted at this web-site. Currently there are two amendments posted. A briefing was conducted at building 145 concerning the date proposals are due, past performance, and the basic terms of the solicitation. A visit of the all three sites where construction is proposed to be commenced was conducted.

2. Those in attendance for the above pre-proposal site visit were the following:

Mr. Dustin Ogden 341st CES, Engineer/Technical Representative

Mr. Cheney Lorenz 341st CES, Technical Representative/Inspector

Mr. Guy Huestis Falls Construction

Mr. John Engebretsen James Talcott Construction

Mr. Aaron Wall James Talcott Construction

Mr. Jack McBroom United Electric

Mr. Rich Budde New Mechanical

Mr. Mitch Swaggert New Mechanical

Mr. Jim Ramsey Geranios Enterprise

Mr. Mark Jefferson 341CCS-Contracting Officer

3. The closing date for this solicitation (proposal due date) remains the same as 20 May 2009 at 2:00 pm Mountain Standard Time.

//signed//

MARK D. JEFFERSON

Contracting Officer