This document is a Statement of Work (SOW) for a carpet replacement project at the Dining Facility (DFAC) in Building 408 at McConnell Air Force Base in Kansas. The contractor shall remove and dispose of the existing carpet tiles and rubber base, and furnish and install new carpet tiles, rubber cove base, and transitions. The work must comply with the Air Force Carpet Program, including using specific carpet selections and installation requirements. The contractor must be certified and provide samples for approval prior to installation. The performance period is not to exceed 14 days, and work shall be performed during overnight hours or on weekends. The government will move furniture, but the contractor is responsible for all other aspects of the project, including cleaning and ensuring proper door operation after installation.

The related federal contract opportunity is a Request for Quotation (RFQ) for the DFAC Carpet Replacement project at McConnell AFB, with a Solicitation Number of FA462124Q0044. The contract will be a Firm Fixed Price based on Lowest Price Technically Acceptable, under NAICS code 314110 with a size standard of 1,500 employees. The Department of the Air Force Air Mobility Command is the issuing agency.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK

Carpet Replacement

Bldg. 408 Dining Facility June 2024

McConnell AFB, Kansas

GENERAL:

The contractor shall provide all personnel, equipment, tools, supplies, materials, supervision, and transportation necessary to:

1. Remove and dispose of indicated existing carpet tiles and transitions.

2. Remove indicated portions of existing rubber base from wall.

3. Furnish and install new carpet, rubber cove base and transitions.

4. Remove old carpet tile adhesive and perform floor prep as necessary to ensure carpet tiles adhere properly to subfloor.

5. Contractor shall verify all dimensions and measurements.

6. Contractor shall submit physical samples of carpet, transitions, cove base, carpet manufacturer’s technical data, and carpet installation instructions to customer prior to installation.

PERFORMANCE REQUIREMENTS:

Air Force Carpet Program: All carpet installation shall comply with the Air Force Carpet Program (https://usaf.dps.mil/sites/aficc/afcc/aficc/affcc/sitecollectiondocuments/carpet/carpethomepage.aspx), using the carpet ordering guide and one of the seven contracts awarded for materials. The AF Carpet program includes modular carpet tiles, roll goods, walk-off tiles, and adhesives. Installation will be managed by local installers.

Measurements: The contractor shall be responsible for measuring and verifying the area and perimeter of all spaces receiving carpet, cove base and floor transitions.

Bldg.

Demo

Installation

Carpet Tiles Cove base Carpet Tiles Cove base Transitions

SF LF SY LF EA

408 Dining

Facility 4300 350

480SY +15%

extra tiles 350 As necessary

Table 1. Carpet Demo & Installation measurements https://usaf.dps.mil/sites/aficc/afcc/aficc/affcc/sitecollectiondocuments/carpet/carpethomepage.aspx

Product Data: Submit 2 copies of manufacturer's full technical data and installation instructions for the carpet, cove base and transition selections. Contractor shall submit physical samples to customer for approval prior to installation.

Requirements:

1. Furniture. Furniture will be moved by government personnel.

2. Carpet Selections. The contractor shall contact and work with one of the vendors listed below to choose one of the 7 carpet choices listed in Table 1. The points of contact are listed on pages 4 and 5. The product shall be the moisture proof thermoplastic hard or thermoset backing option with a maximum thickness no greater than 0.250”

Tier 1 C-Type Contract Vendors Carpet Selection Installation Milliken FA8003-23-C-0008 City Proper –

Underground – UDG119 Flatiron

Brick Ashlar

Engineered Floors FA8003-23-C-0004 Fracture Plaid 7587 2872 Ticking

Brick Ashlar

Mohawk FA8003-23-C-0003 BT437 Shaded lines Sketch Effect 989 Charcoal Quick Silver

Interface Americas FA8003-23-C-0005 Open Air 403 106727 Black

Bentley Mills FA8003-23-C-0009 Redux 6GCR-P

4RXT40221K

Mannington FA8003-23-C-0006 Paper collection – Style:

Crinkled Paper – Carbon 15223

Tarkett FA8003-23-C-007 Electric Edit 11616 Direct Current 22405

Table 1. Carpet Selections

3. Carpet Removal and Disposal. In accordance with EPA guidelines to reduce land filling, provide for carpet and carpet installation waste handling in the project’s overall waste management plan. When feasible, all carpet and carpet installation waste disposal should require a certification that the products were not deposited in a landfill. There are carpet reclamation centers in most major cities. Other sources for carpet reclamation can be found by contacting the carpet manufacturer/provider for their reclamation/recycling options. Also see Carpet America Recovery Effort (CARE) at https://carpetrecovery.org/recovery-effort/collector-finder-map/.

a. Carpet: The contractor shall remove and dispose of carpet indicated on floor plans without disturbing the surface underneath.

b. Cove base and Transitions: The contractor shall remove and dispose of existing rubber base in rooms receiving new carpet.

4. Installation:

a. Contractor Qualifications: All work shall be performed by Certified Floor covering Installers (International Certified Floor covering Installer Association) or manufacturer’s approved installers. Foremen on the jobsite shall be “Certified C-II Minimum.”

b. Warranty: For warranties to be valid, all carpet shall be installed in accordance with the installation guidelines set forth by the manufacturer and/or the minimum guidelines set forth in CRI 104-2002, Standard for Installation Specification of Commercial Carpet, and CRI 105-2002, Standard for Installation of Residential Carpet.

c. Samples: The contractor shall inform the contracting office which carpet is selected for installation and provide a sample.

d. Carpet: The contractor shall work with one of the vendors listed under General Information and install the carpet choice (or approved equal) in the areas indicated.

e. Cove base: Install resilient rubber cove base, (0.080” thick, 4” high, Flexco, or approved equal) in areas where carpet has existing rubber cove base installed. Color to be determined. Contractor shall provide samples of cove base in a complimentary color once carpet is decided.

f. Transitions: The contractor shall install transitions in all areas where there is a change in floor type or carpet height. Transitions shall match or compliment cove base. Color to be determined. Contractor shall provide samples of transitions in a complimentary color once carpet is decided.

g. Additional material: The contractor shall provide 15% of extra carpet tiles above the amount installed. These will be given to the customer.

5. Doors: After carpet installation is complete, the contractor shall ensure that any doors affected by the project can open and close properly.

6. Cleaning: After carpet and installation is complete and prior to furniture reinstallation, the contractor shall remove all debris, scraps, and any other foreign matter. Contractor shall remove any spots or adhesive from the carpet or adjoining surfaces, to include walls, clip any protruding face yarn and vacuum the entire work area to leave a clean and professional site.

PERFORMANCE PERIOD: Shall not exceed 14 days from receipt of all material.

WORK HOURS: Work shall be performed during overnight hour 6:00pm to 4:00am throughout the week Monday thru Friday or anytime on weekend days Saturday and Sunday.

VACATING ROOMS: Furniture will be moved and returned by government personnel after installation is complete. All computers, personal items and easily broken items will be the responsibility of Government personnel. A POC will be assigned to coordinate scheduling and relocations.

Vendor POCs:

Milliken Contract #: FA8003-23-C-008 Web: www.millikenfloors.com POC: Timothy Bagg Phone: (704) 617-1329 Email: timothy.bagg@Milliken.com

Engineered Floors Contract #: FA8003-23-C-0004 Web: www.jjflooringgroup.com POC: Debra Ramsay Phone: (800) 241-4585 Email: contract.team@engineeredfloors.com

Mohawk Contract #: FA8003-23-C-0003 Web: www.mohawkgroup.com POC: Annaleigh Warmack Phone: (706) 459-4965 Email annaleigh_warmack@mohawkind.com

Interface Americas Contract #: FA8003-23-C-0005 Web: www.interface.com/US/en-US/homepage POC: Interface Customer Service Phone: (800)-634-6032 Email: orders@interface.com

Bentley Mills Contract #: FA8003-23-C-0009 Web: www.bentleymills.com POC: Carolyn Drummond Phone: (859) 536-7846 Email: Carolyn.drummond@bentleymills.com

Mannington Contract #: FA8003-23-C-0006 Web: www.manningtoncommercial.com

POC: Jody Steger Phone: (703) 489-5698 Email: Jody.steger@mannington.com

Tarkett Contract #: FA8003-23-C-007 Web: www.commercial.tarkett.com POC: Jamie Collins Phone: (757) 810-8893 Email: Jamie.collins@tarkett.com