PERFORMANCE WORK STATEMENT

FOR FAIRCHILD AFB WA

VERTICAL TRANSPORTATION EQUIPMENT

MAINTENANCE, REPAIR, & INSPECTION

SERVICES

23 SEPTEMBER 2019

FA462020QA200

Attachment 1 Draft PWS

PERFORMANCE WORK STATEMENT (PWS) FOR

VERTICAL TRANSPORTATION EQUIPMENT MAINTENANCE, REPAIR, &

INSPECTION SERVICES

1. DESCRIPTION OF SERVICES. The Contractor shall provide all management, tools, supplies, equipment, parts and labor necessary to maintain, repair, and inspect the real property vertical transportation equipment (VTE) at Fairchild AFB WA in a manner that will ensure continuous and safe operation (full maintenance and repair with the exception of the exclusions listed in paragraph 2 below). The VTE and their locations will be listed in Appendix B. NOTE:

The term “VTE” in this Performance Work Statement (PWS) includes all equipment listed in Appendix B: freight and passenger elevators, escalators, and may include wheelchair/stair lifts, dock levelers, and dumbwaiters.

1.1. This full maintenance contract signifies a VTE service provider (Contractor) takes total service responsibility for the equipment identified in the contract. Except those services covered in paragraph 2 below, the monthly fixed price includes all inspections, maintenance, repairs, including replaceing lights, and routine and emergency service calls. This contract allows the Government to budget total yearly costs and eliminates concerns relating to individual parts repair or replacement invoicing. The Contractor assumes all responsibility and determines the amount of service visits and types of service required to keep the VTE operating safely and within the performance objectives of paragraph 6.

1.2. Work conducted on VTE will be in accordance with the American Society of Mechanical Engineers (ASME) A17.1-2016 (or applicable code for year VTE put in service) Safety Code for Elevators and Escalators (ASME A17.1); ANSI/ASME A17.2-2014, Guide for Inspection of Elevators, Escalators, and Moving Walks (applicable to equipment); A17.3-2015, Safety Code for Existing Elevators and Escalators (applicable to equipment); National Fire Protection Association Standards (NFPA); Unified Facilities Criteria (UFC) 3-600-01; Fire Protection Engineering for Facilities, Occupational Safety and Health Administration (OSHA) Standards and the recommendations of the original equipment manufacturer (OEM).

2. EXCLUDED SERVICES. The following are not covered in the full maintenance service arrangement and are considered over and above services:

2.1. Alterations (a.k.a., modernizations) are not covered in the full maintenance service arrangement. (See Paragraph 3.2)

2.2. Acts by parties other than the Contractor of vandalism, abuse, negligence, damage resulting from rescue and recovery operations, acts of God (including damage resulting from emergency power generator power spikes and low quality) are not included in the contract.

2.3. Additional items excluded in the full maintenance coverage are cosmetic, construction, ancillary components of the VTE system including the finishing, repairing or replacement of the cab enclosure, ceiling frames, hoistway door panels, door frames, sills, car flooring, floor covering, main line power switches, main power breaker(s), hydraulic elevator jack outer housing, buried piping, smoke and fire sensors, fire service reports, main communication feeders to controller, security systems, batteries for emergency lighting and lowering that are not solely dedicated to the VTE, air conditioners, and heaters.

2.4. Routine cleaning and refinishing of the interior of cars and the exterior of the hoistway doors and frames is not included in the basic full maintenance service.

2.5. In the event that the Contractor encounters an item of work included in paragraph 2.1 through 2.4, the Contractor will report the situation to the Contracting Officer’s Representative (COR).

The report will include the work location, a detailed scope of the required work, justification for Contractor determination that the work was not included in the contract, and an itemized cost estimate (including time to repair, all required parts and a breakdown of labor hours). NOTE:

Any part, component or assembly unavailable from the manufacturer due to obsolescence, remains the Contractor’s responsibility to obtain an engineered equivalent product from a commercial source.

3. DEFINITIONS:

3.1. Maintenance, Repair and Replacement. Maintenance, repair and replacement are on existing VTE and included in the contract scope of services. All maintenance, repair and replacement of damaged, broken, or worn parts are to be done in a manner that ensures that the equipment may be operated safely. Maintenance, repair and replacement are actions to restore equipment to a state in which it may safely perform its required operations as installed in accordance with the manufacturer’s recommendations. See ASME A17.1 for requirements.

3.2 Alteration. An alteration is also on existing VTE but is not included under the full maintenance service arrangement. Alteration/modernization will be covered on an over and above Contract Line Item or it may result in a modification to the contract. The typical alteration results in a betterment to the safe operation of the equipment. In the case of elevators, when an alteration is made, all affected safety requirements must be complied with. All work as part of an alteration is required to comply with specific requirements of the current ASME A17.1 Code edition. See ASME A17.1 for requirements.

4. MAINTENANCE AND INSPECTION SERVICES:

4.1. The Contractor with the CO/COR (or representative) shall determine the working order and condition of all VTE listed in Appendix B within thirty (30) calendar days of contract award. The Government will either replace missing items or repair all items not in working order or serviceable condition, or the CO will direct the Contractor to replace the missing items, accomplish the repair, and reimburse the Contractor in accordance with the contract. The CO will give instructions for situations where a unit requires a level of repair potentially constituting alteration as described by paragraph 3. The Contractor and the CO shall certify their agreement as to the working order of the equipment. All repair work shall be in accordance with standard commercial practices using only new parts of equal quality specified by the VTE manufacturer in effecting repairs (substitution of a different component is only permitted where it is equivalent to that which was tested, as determined by the certifying agency).

4.2. The Contractor shall develop and submit to the Government an annual written Maintenance Control Program (MCP) for each VTE within thirty (30) calendar days after contract award to cover the basic contract and any option periods. The MCP shall, at a minimum, include required inspections, timelines for inspections and maintenance to be performed. The Contractor shall perform inspections and maintenance of all VTE in accordance with the MCP. The MCP shall ensure compliance with all minimum code requirements.

4.3. The Contractor shall perform maintenance in accordance with the MCP to ensure reliable and continuous safe operation. The maintenance work shall be in accordance with commercial practices or manufacturer’s specifications, if available, and shall be intended to maintain the VTE in safe and reliable operating condition. The MCP is required to specify appropriate intervals for specific maintenance items.

4.4. Cleaning of equipment spaces and daily cleanup of job sites in conjunction with maintenance, inspections and tests, and repairs are required.

4.5. The Contractor shall perform necessary inspections and tests as required under ASME A17.1 Appendix N, using a Qualified Elevator Inspector (QEI). The first annual test shall include the five-(5)-year test for all traction and roped hydraulic elevators regardless of due date. The three-

(3) - year test shall be scheduled in conjunction with the annual test two years later from the first annual test. Annual safety inspection test certificates will be displayed in the cab of the elevator.

The certificate will show the month the test was completed and when the next test is due. Copies will be provided to the building facility manager and COR.

4.6. The Government may perform inspections of the VTE at no cost to the Contractor for purposes of capital asset management and quality assurance. If discrepancies are discovered during these inspections, the Contractor will be notified in writing of any determination and may be responsible for the corrective actions.

4.7. The Contractor shall prepare and submit a written report within two (2) business days of work.

The report shall identify each VTE, the location, maintenance work performed, repairs needed, date of inspection, name of inspector, and overall condition of the VTE.

4.8. The Contractor shall maintain a copy of all current VTE inspection documentation, along with an index indicating the location, date inspected, and date of the next required inspection having provided the original to the CO/COR. The index and copies of certificates shall be delivered to the CO/COR upon request; however, no later than one (1) business day of a request to review.

4.9. The Contractor will coordinate within 30 days after award with the Fairchild AFB Fire Department to ensure that the Fire Department has all the fire keys for elevators located on Fairchild AFB WA.

5. REPAIR SERVICE CALLS. Contractor shall provide service calls (routine and emergency) under the full maintenance service agreement at no additional charge. All repair work shall be done in accordance with standard commercial practices. Contractor shall repair and replace components of the VTE at no additional cost to the Government. When a component in a labeled product is replaced, it must be replaced with an identical component manufactured under the original labeling service (certifying agency). Substitution of a different component is only permitted where it is equivalent to that which was tested, as determined by the certifying agency.

The parts used for replacement are required to comply with all the requirements that the old parts originally complied with. The Unified Facilities Guide Specifications (UFGS) and the UFC will be used to benchmark acceptable replacement components. See UFGS 14 21 00. 00 20 Electric Traction Elevators, UFGS 14 21 13 Electric Traction Freight Elevators, UFGS 14 21 23 Electric Traction Passenger Elevators, and UFGS 14 2 00 Hydraulic Elevators for guidance.

5.1. Routine Calls. Service calls will be classified as routine when the work or adjustments do not qualify as an emergency call.

5.1.1. In the event that an elevator, dumbwaiter, handicapped lift, or chairlift fails or malfunctions, the contractor shall be notified by the COR.

5.1.2. The Contractor shall respond in-person to the VTE and begin work on routine service calls at no additional cost to the Government within three (3) business days after receipt of the call on regular scheduled work days/hours.

5.1.3. The Contractor shall report to the work location, survey the repair, and provide the CO/COR an estimate of time and cost of repairs not covered in the full maintenance service contract, but necessary to bring the VTE back to operation. The Contractor shall commence repair work after notification from the CO/COR. The Contractor shall prepare and submit to the CO/COR a written report within two business days after the repair. The report shall include the date and time of the service call, the location of the VTE, the repairs performed, and the name of the technician performing the repairs.

5.2. Emergency Calls. Emergency calls are defined as calls made for services when a VTE system fails and constitutes a danger to personnel; threatens to damage properties; or threatens to disrupt activity, operations, and/or training missions.

5.2.1. In the event that an elevator, dumbwaiter, handicapped lift, or chairlift fails or malfunctions, the contractor shall be notified by the COR

5.2.2. The Contractor shall respond in person to the VTE and begin work on emergency service calls within (1) business day after receipt of the call.

5.2.3. The Contractor shall report to the work location, survey the repair, and provide base contracting an estimate of time to repair and cost of repairs not covered in the basic full maintenance service contract but necessary to bring the VTE back to operation. The Contractor shall commence repair work after notification from the CO/COR. The Contractor shall prepare and submit to the CO/COR a written report within two business days after the emergency repair.

The report shall include the date and time of the service call, the location of the VTE, the repairs performed, and the name of the technician performing the repairs.

6. SERVICES SUMMARY.

The Government will evaluate the Contractor performance in accordance with the following criteria. Performance evaluations will be rendered in one or more Government databases for that purpose.

Performance Objective PWS Paragraph

Performance Threshold

Remedy

1. Written Maintenance Control Program (MCP) for each VTE for all equipment.

MCP identifies all maintenance intervals to include safety inspections.

4 MCP in accordance with ASME A17.1 delivered to CO in 30 calendar days of contract award.

Re-perform within 3 Business Days

2. VTE Service Availability 4 VTE availability is 95%.

Calculation = ((sum of all VTE * # days in service during the selected month for each VTE) / (# VTE * # days in the selected month)).

Re-perform within 1 Business Day

3. Repair Service Call Routine – Response Time.

Response to routine calls within time specified in paragraph 5.1.2.

5 Response to routine service calls are on-time 100% of the time on a monthly basis.

Emergency Call:

Re-perform within 1 Business Day

Routine Call: Re-perform within 2 Business Days

4. Repair Service Call Emergency – Response Time.

Response to emergency calls within time specified in paragraph 5.2.2.

5 Response to emergency service calls are on-time 100% of the time on a monthly basis.

Re-perform same day

5. Service Call Repairs – Repair Quality.

Repairs are of high quality resulting in reduced call backs.

5 Only two call backs of the same problem (same instance) each month.

Contrator identifies and corrects unreliable parts or repair methods

CONTINUED ON NEXT PAGE

Performance Objective PWS

Paragraph Performance Threshold

Remedy

5. Inspection – MCP Adherence 4.2,4.3 Conducts Inspection

IAW MCP 100%

Any deviation or revisions must have CO Approval

6. Preventative Maintenance - MCP Adherence

4.7., 5.1.3, 5.2.3.

Preventative maintenance performed to MCP 100% of time.

Re-perform within 1 Business Day

7. Reporting including annual inspection certificates

2, 4, 5 Submit reports in a manner consistent with PWS 100% of the time.

Re-perform within 1 Business Day

7. GOVERNMENT FURNISHED PROPERTY AND SERVICES. The Government does not anticipate providing any government furnished property (GFP). All reasonable quantities of utilities will be available to the contractor without charge. Any temporary lines and connections that may be required shall be installed, maintained and removed by the contractor at his expense and in a manner satisfactory to the COR.

8. GENERAL INFORMATION.

8.1. QUALITY CONTROL. Contractor shall develop and maintain a quality control program (QCP) to ensure maintenance and repair services are performed in accordance with ANSI/ASME A17 and other applicable standards and codes. The Contractor shall develop and implement procedures to eliminate reoccurrence of once identified/repaired defects. As a minimum, the Contractor shall develop quality control procedures that address the areas identified in Paragraph 6, Service Summary. The QCP shall demonstrate how the Contractor ensures quality performance during the contract period of performance. The Contractor shall maintain the QCP throughout the period of performance of the contract. The CO will be provided updates to the QCP as they occur during the period of performance. The QCP will identify the procedures in writing for inspections, individual responsible, VTE MCP, and the location of all inspection records and key control logs which will always be available to the government upon request. The QCP will have the inspection forms and records which will be used for the service. The Contractor will identify to the CO/COR the responsible quality control inspector to notify in case of customer complaints.

8.2. QUALITY ASSURANCE. The Government will periodically evaluate the Contractor’s performance in accordance with the Quality Assurance Surveillance Plan.

8.3. HOURS OF OPERATION. Hours of Operation. The contractor shall VTE maintenance services during normal duty hours which are 0730-1630, Mondays through Fridays, excluding federal holidays, unless otherwise required in the contract or approved by the CO. The contractor is not required to provide service on federal holidays, except in emergency situations. Federal holidays are as follows:

New Year’s Day - 1 January Labor Day - 1st Monday in September Martin Luther King Day - 3rd Monday in January Columbus Day - 2nd Monday in October Washington’s Birthday - 3rd Monday in February Veteran’s Day - 11 November Memorial Day - last Monday in May Thanksgiving Day - 4th Thursday in November Independence Day - 4 July Christmas Day - 25 December

8.4. SECURITY REQUIREMENTS. All contractor or contractor employees’ vehicles used for the performance of this contract shall comply with all local, state and federal regulations. In addition, all vehicles described above must be registered through the Security Police Squadron, Pass and Registration and will comply with Fairchild AFB directives. After award of contract, the contractor shall request through the COR, CO and Security Forces to be issued base passes and identification badges for their employees and work vehicles.

8.5. CONTINUATION OF ESSENTIAL DEPARTMENT OF DEFENSE SERVICES

DURING CRISIS DECLARED BY THE NATIONAL COMMAND AUTHORITY OR

OVERSEAS COMBATANT COMMANDER. This service does not meet the criteria for continuation of performance during a crisis.

8.6. SPECIAL QUALIFICATIONS. The Contractor will be licensed by the State in which the work is conducted to provide the services specified in this contract. All work will be performed by personnel who are trained and qualified for the systems and equipment. Contractor personnel shall be certified by appropriate federal and state regulatory agencies to meet federal and local certification requirements (documentation provided to CO/COR upon request) in maintenance of

VTE.

8.7. SCHEDULE COORDINATION. The Contractor shall be responsible for coordinating all phases of his/her operations with the appropriate base personnel through the CO/COR. The facilities shall remain in operation while the Contractor is working, and it is up to the Contractor to coordinate around the normal activities of the facility.

8.8. Base Closures. Work scheduled but not accomplished because of base closure due to weather, exercises, or actual alert, will be accomplished as soon as possible after reopening the base.

8.9. Contractor/Employee Base Pass and Identification, Special Clearances and Vehicle Passes.

All documentation needed for base passes shall be submitted at the Pre-Performance Conference.

8.10. ENVIRONMENTALLY PREFERABLE PURCHASING. In order to comply with federally mandated environmental preference programs and Department of Defense (DOD) “Sustainable Procurement Program” (SPP) policy, Fairchild AFB requires the use of environmentally preferable products and services. These program elements include: recovered material products, energy and water efficient products, alternative fuels and fuel efficiency, bio-based products, products which are non-ozone depleting or are non-toxic or less toxic alternatives and environmentally preferable products. These program elements are described on the Fed Center website at https://www.fedcenter.gov/programs/buygreen/. The Green Procurement Compilation website

FA462020QA200

https://www.fedcenter.gov/programs/buygreen/

(http://sftool.gov/greenprocurement) provides a comprehensive green purchasing resource and identifies all product types covered by mandatory federal environmental programs.

8.10.1. PRODUCTS AND MATERIALS. If it is determined that if a product does not meet Government performance requirements, the contractor shall submit a proposed alternative that would meet the performance requirements with the lowest environmental impact for evaluation and acceptance. Products that fall under the Environmental Protection Agency (EPA) Comprehensive Procurement Guidelines (CPG) (https://www.epa.gov/smm/comprehensive-procurement-guideline-cpg-program) shall meet the minimum recovered (recycled) content. Bio-based products shall meet the requirements of the biobased product listing from the United States Department of Agriculture (USDA) (http://www.biopreferred.gov/).

The contractor shall purchase and use Energy Star or other energy-efficient items listed on the Department of Energy’s Federal Energy Management Program (FEMP) Product Energy Efficiency Recommendations product list.

Supplements or amendments to listed publications from any organizational level may be issued during the life of the contract.

Before implementing any change that results from amendments to these listed publications that will result in a change to the contract price, the contractor shall submit to the Contracting Officer a price proposal within 30 calendar days following receipt of the change. An equitable adjustment (increase or decrease) shall be negotiated.

8.11. CONTRACTOR HAZARDOUS MATERIALS. In accordance with AFI 32-7086, Hazardous Materials Management, 4 Feb 15, a hazardous material includes all items covered under EPCRA tracking requirements, the OSHA HAZCOM standard, and all Class I and II Ozone Depleting Substances. The Contractor shall be responsible for the proper storage, management, and disposal of any hazardous material brought on Base for contractor use.

8.12. HAZARDOUS MATERIAL STORAGE. For any single hazardous material stored on-site in a quantity equal to or exceeding 55-gallons at any time, the contractor shall provide secondary containment for the entire quantity of that hazardous material. Hazardous material shall be stored within a locked secure area not accessible to the base populace after hours. All containers of hazardous material shall be clearly and properly labeled; closed when not in use; and stored in an upright, secure position.

8.13. HAZARDOUS MATERIAL AUTHORIZATION. The Contractor shall submit to the COR, prior to using hazardous materials (HAZMAT), a Contractor Hazardous Material Work Sheet and corresponding Safety Data Sheet (SDS) for each hazardous material to be brought onto the base during the performance of the contract. This work sheet and SDS shall be completed for each and every hazardous material to be used by the Contractor. If during the course of the contract, items not previously identified are to be brought on the base, the Contractor shall submit a Work Sheet and SDS for approval prior to bringing the HAZMAT onto the base.

8.14. HAZARDOUS MATERIAL USAGE. Within seven calendar days of the end of every month, the Contractor shall submit to COR, the quantities of each hazardous material actually used on the base during the month, utilizing and annotating the government-provided chemical authorization list. List can be obtained from 92 CES/CEIE via the COR. This information should be included in the monthly report described above.

8.15. HAZARDOUS MATERIAL REMOVAL. No hazardous material shall be left on-site at the end of a contract.

8.16. COSTS OR FINES. Any costs or fines levied against the installation due to the contractor’s failure to comply with applicable Federal, State, or local laws shall be borne by the contractor.

8.17. CONTRACTOR/EMPLOYEE BASE PASS AND IDENTIFICATION, SPECIAL CLEARANCES AND

VEHICLE PASSES. All documentation needed for base passes shall be submitted at the Pre-Performance Conference. Due to the nature of the work only US nationals or verified Green Card holders are eligible to enter FAFB and all personnel must have a pictured ID that is compliant with the REAL ID Act of 2005 . Due to the sensitive nature of the mission executed in the following buildings; Bldgs. 1204, 2005, 2007, 2090, 2097, 2245, and 2187 all contractors performing on this contract must be U.S. Citizens.

http://sftool.gov/greenprocurement https://www.epa.gov/smm/comprehensive-procurement-guideline-cpg-program http://www.biopreferred.gov/

8.18. COMPLIANCE WITH LAWS AND REGULATIONS. The contractor shall be knowledgeable of and comply with all applicable Federal, State, and local laws, regulations, and requirements regarding environmental protection. In the event environmental laws/regulations/requirements change the term of this contract, the contractor shall comply with such law/regulation as changed. If there is an increase or decrease in cost as a result of the change, the contractor shall immediately inform the CO.

8.19. WEAPONS, FIREARMS, AND AMMUNITION. Contractor employees are prohibited from possessing weapons, firearms, or ammunition, on themselves or within their contractor-owned or privately-owned vehicle while on FAFB.

8.20. REPORTING REQUIREMENTS. Contractor personnel shall report any information or circumstances of which they are aware may pose a threat to the security of DoD personnel, Contractor personnel, resources, and classified or unclassified defense information.to the Law Enforcement (LE) Desk at (509) 247-5494.

8.21. PHYSICAL SECURITY. The contractor shall be responsible for safeguarding all Government property and controlled forms provided for contractor use. At the end of each work period, all government facilities, equipment, and materials shall be secured.

8.22. PERSONNEL APPEARANCE. Contractor personnel shall present a neat appearance.

Contractor personnel shall be easily recognizable while on the installation in conjunction with this contract. This shall be accomplished through the wear of distinctive clothing, bearing the company name or logo that is visible at all times. The coloring or design of the items selected should be such that identifies personnel easily and quickly for reasons of safety and personal protection.

8.23. KEY CONTROL. The contractor shall establish and implement methods of making sure all keys/combinations issued to the contractor by the government are not lost or misplaced and are not used by unauthorized persons. The contractor shall not duplicate any keys issued by the government.

The contractor shall immediately report to the COR or CO any occurrences of lost or duplicated keys. In the event keys, other than master keys, are lost or duplicated, the contractor may be required, upon written direction of the CO, to re-key or replace the affected lock or locks at cost to the government. The government may, however, at its option, replace the affected lock or locks or, at its option perform re-keying and deduct the cost of such from the monthly payment due the contractor.

In the event a master key is lost or duplicated, the government shall replace all locks and keys for that system at the contractor’s expense.

8.24. RESTRICTIONS. The Government is authorized to restrict the employment under the contract of any Contractor employee or prospective Contractor employee, who is identified as a potential threat to the health, safety, security, general wellbeing, or operational mission of the installation and its population.

8.25. NON-PERSONAL SERVICES AND/OR INHERENTLY GOVERNMENTAL SERVICES. The Government will neither supervise contractor employees nor control the method by which the contractor performs the required tasks. It shall be the responsibility of the contractor to manage its employees and to guard against any actions that are of the nature of personal services, or give the perception of personal services. If the contractor feels that any actions constitute, or are perceived to constitute personal services, it shall be the contractor's responsibility to notify the CO immediately. These services shall not be used to perform work of a policy/decision making or management nature, (e.g., inherently governmental functions). All decisions relative to programs supported by the contractor shall be the sole responsibility of the government.

APPENDICES.

A. Include VTE Equipment Listing

Performance Work Statement for Vertical Transportation Equipment Maintenance, Repair and Inspection Services Appendix A

Item Type of VTE Location of VTE/Stops Manufacturer

Capacity

(LBS)

S/N# Year

Installed

Geared Passenger

Bldg 1204, Air Traffic Control Tower 8 Stops

Schindler Haughton, 1984

1200 lbs

18359

Selective/Collective Hydraulic Passenger

Bldg 1252, Survival Inn Billeting 3 Stops

Millar

3500 lbs

61643

Bldg 2005, 2 Stops

Dover

2500 lbs

EG3760

Bldg 2007, 92

OSS

EJ3118

Bldg 2090, 92 ARS, Squadron Operations

EJ3118

Bldg 2097, 92

AMXS

2 Stops

Montgomery

KONE

90039

Hydraulic Rotary

Bldg 2245, 92

CPTS, 92/141 CS

Montgomery

KONE, 1988

60250

Bldg 2380, Education Center/Library

EK8957

Bldg 2045, Logistics Readiness Sq

Schindler

866A365H02

Hydraulic Cargo

Bldg 2045, Logistics Readiness SQ

ACUA

11400

EY4890

11 Traction Cargo

Bldg 2187 92

ARW HQ

2 stops

ThyssenKrupp Synergy 85S

3000 lbs

P-1 CBU275

Bldg 12 68 SERE

HQ

2 Stops Schindler

Bldg 12 68 SERE

HQ

2 Stops ThyssenKrupp

EBU975

Bldg 2379 Fittness Center 2 Stops ThyssenKrupp

EAT590

Bldg 4400, Army Reserve Center

ThyssenKrupp Tac-20

EY4890

PERFORMANCE WORK STATEMENT

File details come from the government source that posted it.