Repair Elec Dist 15th Cav E Specifications.pdf
PDF 554 KB Posted
- Solicitation number
- FA4613-09-R-0016
About this file
F Circuit Specifications
View the file
Other files
| File | Type | Posted |
|---|---|---|
| CECP Responses to Ktr Questions Sep 09.doc | DOC document | |
| 09-R-0016 Electrical Distr Upgrades.doc | DOC document | |
| Bldg 250 Parking Lot Lights SOW Rev A Jul 09.docx | DOCX document | |
| Rpr Elec Dist - 15th Cav E Side Drawings.pdf | ||
| Bldg 250 Pkg Lt Lts Drawings.pdf | ||
| Repair C Ckt Specifications.pdf | ||
| Electr Submittal Logs.pdf | ||
| Electr Green Procurement Forms.pdf | ||
| Rpr Elec Dist C Ckt Drawings.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Repair Electrical Distribution – 15TH Cav & E Base Project No. GHLN 98-1059
TOC - 1
REPAIR ELECTRICAL DISTRIBUTION – 15TH CAVALRY AND EAST
BASE
Project Number GHLN 98-1059
F. E. Warren AFB, Wyoming
SPECIFICATIONS
Prepared by:
th
Civil Engineer Squadron
90 CES/CEPM
JULY 2009
TOC - 2
SPECIFICATION TABLE OF CONTENTS
DIVISION 1 - GENERAL REQUIREMENTS
01025 GENERAL REQUIREMENTS
01300 SUBMITTAL PROCEDURES
DIVISION 2 - SITE WORK
02110 CLEARING AND GRUBBING
02222 EXCAVATION, TRENCHING, AND BACKFILLING FOR UTILITIES SYSTEMS
DIVISION 3 - CONCRETE
03300 CAST-IN-PLACE STRUCTURAL CONCRETE
DIVISION 4 - MASONRY
(NOT USED)
DIVISION 5 - METALS
DIVISION 6 - WOOD AND PLASTICS
DIVISION 7 - THERMAL AND MOISTURE PROTECTION
DIVISION 8 - DOORS AND WINDOWS
DIVISION 9 - FINISHES
DIVISION 10 - SPECIALTIES
TOC - 3
DIVISION 11 EQUIPMENT
DIVISION 12 FURNISHINGS
DIVISION 13 SPECIAL CONSTRUCTION
DIVISION 14 CONVEYING SYSTEMS
DIVISION 15 - MECHANICAL
DIVISION 16 - ELECTRICAL
16370 ELECTRICAL DISTRIBUTION SYSTEM, AERIAL
16375 ELECTRICAL DISTRIBUTION SYSTEM, UNDERGROUND
16528 EXTERIOR LIGHTING
GENERAL REQUIREMENTS 01025 - 1
SECTION 0l025
GENERAL REQUIREMENTS
1 GENERAL
1.1 GENERAL
The work to be performed under this contract consists of furnishing all material, labor, and equipment, and performing all work associated with replacing the overhead distribution system ―F‖ circuit (aka 15th Cav and
East Base) with a new underground system. All existing services will be resupplied by the new underground system. The project will include but is not limited to the following principle items. Refer to the project plans for layout and configuration details:
- Removal of wooden utility poles
- Removal of overhead circuit conductors and associated terminations and hardware
- Removal of overhead transformers
- Removal of overhead service conductors
- Removal of existing street lights
- Installation of new ductbanks
- Installation of new 15 kV Cable
- Installation of new underground services
- Installation of new padmount transformers and sectionalizing cabinets
- Installation of new street lights, metal poles and arms
- Installation of ground electrodes and ground bonds
1.2 DESCRIPTION OF WORK
The work includes but is not necessarily limited to the following principle features:
1.2.1 BASIC BID
1. Replace existing overhead distribution line with a new underground distribution system as shown on the plans.
2. New medium voltage underground distribution shall be comprised of 15 kV copper EPR cable in concrete encased duct.
3. Provide new services as required.
4. Remove existing overhead distribution.
1.3 EXISTING CONDITIONS
Field verify all existing conditions, existing construction, dimensions, quantities, other pertinent requirements and suitability for the intended use prior to starting work activities. Determine special requirements or precautions required for items or structures to be renovated, removed, shored, braced or supported.
Do not obstruct or close roadways, sidewalks or exit ways without authorization.
GENERAL REQUIREMENTS 01025 - 2
1.4 HISTORIC ARTIFACTS
If historic or prehistoric deposits are encountered, stop work at that particular location and notify the Contracting Officer immediately. A
Notice to Proceed will be issued only after the find has been evaluated by a qualified archaeologist in accordance with Federal Law. No historic or prehistoric items shall be removed until the evaluation is complete.
Items remain the property of the U.S. Government. Historic or prehistoric deposits include all items made or modified by man such as bottles, bricks, foundations, metal items, arrowheads, stone tools, etc.
Individual items encountered during construction will not require a work stoppage but must be reported to the Contracting Officer. Notify 90
CES/CEVH before trenching so that trenching may be monitored. If archeological materials are found, work may be stopped until the find can be accessed.
1.5 WORKING HOURS
Normal working hours for the Contractor will be 7:30 a.m. to 4:30 p.m.
excluding Saturdays, Sundays, and Federal holidays. Notify the
Contracting Officer three days in advance if work is desired during other time periods. If Inspectors will be available, a modified work period may be authorized. If Inspectors are required to work other than their normal duty/days solely for the benefit of the Contractor, the actual cost of inspections at overtime rates will be charged to the Contractor and an adjustment made to the contract price.
1.6 DISCREPANCIES ON DRAWINGS
Drawings are based on record drawings, surveys, on-site observations and field measurements made by the Government and others.
Check and compare all Drawings immediately upon their receipt and notify the Contracting Officer of any discrepancies.
Verify all dimensions and quantities shown and adequacy of available spaces prior to construction or ordering materials.
Follow dimensions marked on Drawings in lieu of scaled measurements.
1.7 DEFINITIONS
Use of certain phrases or words on the Drawings or Specifications have the following definitions:
(1)The term "replace" means remove and dispose of existing material or item and furnish and install a similar new material or item that matches both the original material and remaining adjacent materials or items.
(2)The term "reinstall" means remove existing material or item and reinstall same material or item properly aligned, plumb and secure to match existing adjacent materials or items.
(3)The terms "provide" or "furnish" mean furnish and install unless otherwise indicated.
GENERAL REQUIREMENTS 01025 - 3
1.8 SUBMITTALS
Provide submittals called for by the technical specifications to the
Contracting Office, 90 CONS/LGCI, 7505 Marne Loop, Bldg. 208, F. E.
Warren AFB, WY. 82005-2860.
SHOP DRAWINGS, PRODUCT DATA, AND OTHER SUBMITTALS: Four (4) copies, minimum. The Government will retain 3 copies and return the remainder to the Contractor, marked with action taken and corrections or modifications required. Note: Product data should include copies of manufacture's original catalog cut sheets with UL listings. Contractor shall use AF
Form 66, to track submittals, see section 1300.
Review of submittals by the Government will not be construed as a complete check, but indicates only that the submittals are in general conformance with the design concept and with the information given in the
Contract Documents. This approval shall not relieve the Contractor from responsibility for errors and omissions. The Contractor is responsible for field measurements, dimensions, design of adequate connections, details, fabrication processes, and the means, methods, techniques, and procedures of satisfactory installation per CQC requirements of this contract.
After submittals have been approved, no resubmittals for the substitution of products will be considered without an acceptable explanation from the
Contractor.
Allow sufficient time for submittal review. Advise Contracting Officer when processing time is critical to the progress of the work.
Do NOT proceed with fabrication or installation until an approved submittal has been received.
Submit PROGRESS SCHEDULE on AF FORM 3064.
1.9 NEW MATERIALS, RECYCLED MATERIALS AND HAZARDOUS MATERIALS
All materials to be installed including those concealed or covered shall be new or recycled unless otherwise indicated and of the most suitable and highest grade and type for the intended use unless otherwise indicated. They shall be produced by a manufacturer regularly engaged in manufacturing or fabricating similar products with a history of successful production acceptable to the Contracting Officer.
Under no circumstances will the Government be required to prove that an item submitted for substitution is not equal to the specified item. No substitute material or equipment shall be ordered, fabricated, shipped or processed in any manner prior to receiving the Contracting Officer's written approval. The Contractor shall assume all responsibility for additional expenses as required in any way to meet changes from the original material or equipment specified. If notice is not specified within 15 days after the general contract is awarded, then equipment and material specified shall be used.
Prohibited materials include those that contain Class 1 ozone-depleting chemicals (including CFC's, halons, carbon tetrachloride, methyl chloroform, and methyl bromide), asbestos, PCB's, lead, or other hazardous substances.
GENERAL REQUIREMENTS 01025 - 4
If any proposed usage or installation method does not comply with the recommendations or specifications, the Manufacturer shall notify the
Contracting Officer in writing.
Protect materials during delivery, storage, handling and installation per manufacturer's printed instructions. Place on blocking and cover when necessary to protect from water, dust, direct exposure to sunlight and other elements. Deliver in original containers or packaging with labels intact. Storage locations shall not interfere with work of other trades.
Maintain acceptable temperature and humidity conditions. Work areas shall be enclosed, weathertight, and heated as necessary to protect finish materials during and after installation.
Comply with guidelines and requirements of the Air Force Affirmative
Procurement Program for the purchase and use of recycled construction materials. The construction materials included under this requirement are all type of insulation and insulation board; structural fiberboard;
laminated paperboard products; ceiling tile and lay-in ceiling panels;
cement, concrete and concrete laminated paperboard products; ceiling tile and lay-in ceiling panels; cement, concrete and concrete products containing fly ash or blast-furnace slag; carpet made of polyester fiber;
floor tile containing recovered rubber or plastic; patio blocks containing recovered rubber or plastic.
The use of other products manufactured from recycled materials is encouraged. The use of recycled products is mandatory unless they are not available within a reasonable time frame, or if the cost exceeds the cost of non-recycled items or if they do not meet the technical requirements of the project, or if they are not available from at least two (2) sources so as to maintain a satisfactory level of competition.
Compile a ―Recycled Products Report‖ for the Resource Recovery and
Recycling Manager at 90 CES/CEV listing the total quantity recycled products used. Submit the report through the Contracting Officer at the end of the contract period or at the end of the calendar year, whichever comes first.
Submit a Material Safety Data Sheet (MSDS) for each chemical/compound proposed for this project to the Base Bioenvironmental Office (90
AMS/SGPB) for review and approval prior to delivery to the base. A hazardous material is defined in Federal Standard DED-STD-313C (Tables I and II). The definition of materials presenting a health hazard or physical hazard is found in 20 CFR 1910.1200(c). The Contractor must compile a "Hazardous Materials Report" for the Resource Recovery and
Recycling Manager at 90 CES/CEV listing the description of the hazardous material, brand name, part number, SSL No., unit of issue, quantity issued/used and person(s) issued to. Submit the report by the 5th of the following month through the Contracting Officer.
1.10 INDUSTRY STANDARDS
General Applicability of Standards: Applicable standards of the construction industry have the same force and effect and are made a part of the contract documents when referenced as if copied directly into contract documents, or as if published copies were bound herewith.
Reference standards referenced directly in contract documents or by governing regulations have precedence over nonreferenced standards which are recognized in industry for applicability to work.
GENERAL REQUIREMENTS 01025 - 5
Nonreferenced standards recognized in the construction industry are hereby defined, except as otherwise limited in contract documents, to have direct applicability to the work and will be so enforced for performance of the work.
Publication Dates in effect are as of date of contract documents.
1.11 BUILDING CODES, LAWS, AND REGULATIONS
Comply with the the latest editions of the LIFE SAFETY CODE, UNIFORM
BUILDING CODE, UNIFORM MECHANICAL CODE, UNIFORM PLUMBING CODE and the
NATIONAL ELECTRICAL CODE.
Comply with the UNIFORM FEDERAL ACCESSIBILITY STANDARDS (UFAS).
Comply with the AMERICANS WITH DISABILITIES ACT OF 1990 (ADA).
Comply with the latest adopted FEDERAL, STATE, and LOCAL LAWS and
REGULATIONS that apply to this project.
1.12 SAFETY STANDARDS
Comply with requirement of the BASE SAFETY OFFICER for the protection of
Air Force Personnel and Property.
Comply with the rules, regulations, standards and requirements of the
DEPT. OF DEFENSE (DOD), WYOMING DEPT. OF ENVIRONMENTAL QUALITY (DEQ), EPA
AND OSHA regarding disturbing, removing and disposing of HAZARDOUS
MATERIALS; ASBESTOS, LEAD-BASED PAINTS, PIGEON DROPPINGS and OTHER
HAZARDOUS MATERIALS.
Comply with CORPS OF ENGINEERS SAFETY & HEALTH REQUIREMENTS MANUAL EM
385-l-l (Oct 1992), OSHA STANDARDS, and other applicable rules, regulations, standards and requirements regarding WORKER SAFETY.
Comply with WYOMING OCCUPATIONAL HEALTH AND SAFTEY RULES AND REGULATIONS
FOR CONSTRUCTION.
1.13 WORK SITE ACCESS
Coordinate access to the Base and Project Facility for personnel and equipment with the Contracting Officer.
1.14 STORAGE, STAGING AND PARKING
When space is available at the project site, it may be used for the
Contractor's storage, staging and parking areas. When no space is available at the project site or when additional space is required, it will be designated by the Contracting Officer.
No sodded or landscaped areas or exitways shall be used for storage, staging, or parking.
1.15 TEMPORARY FUELING FACILITY
It is preferred that a mobile fuel service be used for fueling vehicles and equipment. However, if the contractor desires to use a temporary fueling tank, the following conditions must be met.
GENERAL REQUIREMENTS 01025 - 6
Temporary fueling tanks must be vaulted to contain any leaks OR must have a secondary containment basin below the tank built per 90 CES/CEV requirements. Tank must have an alarm that activates when tank has reached 90% full. Tank shall also have a spill catchment box at fuel fill pipe to catch any spills and drain them back into the tank. Maximum tank size is 1,000 gallons. Valve must be locked in closed position except during fueling operations. Tank shall have signage indicating type of fuel and that it is "flammable".
Temporary storage of motor oils and hydraulic fluids must have secondary containment.
Contractor shall be responsible for proper clean-up of any spills.
Coordinate with and provide appropriate documentation to 90 CES/CEV.
If used, the contractor shall remove temporary fueling facility upon completion of project and shall sample area to verify site is free of fuels, oils, and any other fluids that were stored at the facility.
Provide documentation certifying that the site is clean to 90 CES/CECV.
1.16 TEMPORARY UTILITIES
The Government will furnish utilities (water, gas, electricity) to the
Contractor when available at no cost from existing points of connections with-in 500 feet of the staging area. All costs of making connections and extensions shall be paid by the Contractor. If no utilities are available with-in 500 feet of the staging area, the contractor shall provide the necessary utilities at no cost to the government.
1.17 TEMPORARY SANITARY FACILITIES
Provide portable self-contained sanitary toilets at a location determined by the Contracting Officer or Authorized Representative (COAR)
1.18 TEMPORARY FIRE PROTECTION
Provide and maintain temporary fire extinguishers as determined adequate by the Base Fire Department.
1.19 FIELD OFFICE AND TELEPHONE
No Field Office is required.
1.20 PROJECT SIGN
No project sign is required.
1.21 PROJECT COORDINATION, SUPERVISION AND CONSTRUCTION METHODS
The contractor shall provide a competent superintendent for the project.
Each Subcontractor shall maintain a competent foreman or representative on the job when work is in progress. Together they shall cooperate and be responsible for the proper and timely layout, coordination, erection and completion of the work.
Each trade shall lay out and install its work at such time and manner to avoid delay or interference with other work. Anticipate and resolve conflicts before work begins. Submit questions to the Contracting
GENERAL REQUIREMENTS 01025 - 7
Officer or authorized representative for resolution before proceeding with the work in question.
The Contractor is solely responsible for construction means, methods, techniques, sequences, procedures, fabrication processes, safety precautions, safety programs and other necessary precautions during construction.
1.22 FIELD ENGINEERING
The General Contractor shall do construction staking and establish horizontal and vertical control elevations for construction including earthwork, paving, and concrete forming.
1.23 QUALITY CONTROL AND INSPECTION
The General Contractor shall employ and pay a testing laboratory
(approved by the Government) to perform field sampling, quality control testing and to submit test reports required by the technical specifications during construction.
The Contractor shall ensure that all work has been inspected by a
Government Inspector prior to concealment.
1.24 BARRICADES, FENCING, WARNING SIGNS AND RELATED DEVICES
Erect barricades, safety barriers, barrels, fencing, signs, warning lights, flagging, flag persons and devices as appropriate to control traffic and to warn and protect the workmen, users, occupants and the public. Comply with latest edition of MANUAL ON UNIFORM TRAFFIC CONTROL
DEVICES.
All roads, sidewalks, and walkways shall be open during winter exclusion periods.
Building parking lots must accessible. Open trenches which block access must have proper foot bridges constructed.
1.25 PROTECTION OF PROPERTY
Protect existing facilities, all materials and equipment to be incorporated therein, completed work, site improvements, trees, landscaping, utilities, public ways and other facilities. Promptly remedy all damage or loss thereto resulting from demolition or construction activities or operations under this contract and restore to equivalent original conditions.
When indicated on the drawings, protect trees to remain with a temporary
6-ft. high fence not less than 5 feet from the trunks.
1.26 SPECIAL ALTERATION AND RENOVATION REQUIREMENTS
Cut, move, remove, modify or prepare existing items, surfaces and finishes as necessary for completion of alteration and renovation work.
Minimize damage to other work.
Make smooth, even and neat transitions between new and existing work.
GENERAL REQUIREMENTS 01025 - 8
Patch, repair, restore or replace disturbed or damaged surfaces and finishes to match original conditions in texture and appearance. When adjacent surfaces and finishes cannot be matched, refinish entire surface to nearest intersection.
Reinstall materials, equipment or items that are disturbed or removed temporarily. Comply with workmanship and other applicable provisions of technical specification sections for comparable new work. Use new screws and other fastening devices.
1.27 SPECIAL REQUIREMENTS FOR SITE UTILITIES
Place a color-coded plastic warning tape at least 4" wide within the trench above all buried utility lines. A continuous printed inscription on the tape shall describe the specific utility:
RED Electric.
YELLOW Gas, oil, dangerous material.
ORANGE Communications.
BLUE Water.
GREEN Sewer.
1.28 UTILITY SERVICE INTERRUPTIONS AND ROAD CLOSINGS
Notify the Government in writing at least two (2) weeks prior to the interruption of utility or communication services to or within the project site or to facilities used by others. No outage shall exceed four (4) hours. The Government will coordinate the time and duration of all outages with the Using Agency and others.
Roads may be closed one lane at a time with vehicular traffic allowed to pass through the construction area. If an entire street is to be closed notify the Government in writing at least two (2)weeks prior to the closing.
1.29 CONFINED SPACE ENTRY
Comply with OSHA (20 CFR 1910.146) and AFOSH STD 91-25 (Nov. 1994) for confined space entry. Manholes, vaults, tunnels and certain pits and other spaces with limited openings for entry/exit or with limited space and not meant for human habitation are considered confined spaces. All are to be considered "permit-required confined spaces" until they have been determined to be "non-permit-required confined spaces".
Prior to entry the Contractor shall notify and coordinate with the Base
Fire Dept. and Bioenvironmental Agencies. Assume all emergency rescue responsibilities.
Contractor shall maintain a confined space program without reliance on AF personnel or services except that coordination shall be made with
Bioenvironmental Services (BES) to obtain known hazard information and base instituted precautions or procedures. The Contractor shall notify
BES of any problem encountered. The contractor permitting process shall provide for entry of necessary AF personnel.
1.30 DIGGING PERMITS AND EXCAVATION
A ―Digging Permit: is required for all types of excavation, digging, and borings regardless of depth. Requests are submitted via the government
Construction Inspector to 90 CES Customer Service in bldg 318. Permit
GENERAL REQUIREMENTS 01025 - 9
requests should be submitted no more than 14 calendar days prior to the planned excavation date. Permits must be renewed every 30 days. Permits are processed using an Air Force Form 103.
The contractor is responsible for providing the following to the government Contract Inspector when planning an excavation.
1. A drawing of the area of digging.
2. State the purpose of the digging.
3. Provide name, phone number, and organization of the contractor point of contact.
4. Indicate the required start date.
5. Physically mark the actual digging site with white paint or flags.
For trench excavation paint or flags at intervals necessary to clearly identify the trench lines is required. For large areas such as parking lots the perimeter of the area to be excavated should be clearly defined with white paint or flags.
Customer Service will hand carry the AF FORM 103 to the appropriate agencies on base for coordination. These agencies include:
Electric Shop Communications Squadron
Heat Plant Engineering Flight
Utilities Shop ATT Cable Television
Environmental Flight U.S. WEST Communications
Pavements & Equipment Shop Cheyenne Light, Fuel, and Power
Cathodic Protection Shop Cheyenne Board of Public Utilities
EMCS (Alarms) Shop Grounds Maintenance Quality
Assurance
Security Police Evaluator
Wing Safety BNSF (if within Railroad right-of-way)
Areas, which are clear of utilities, will simply be annotated ―Clear‖ and signed by the locator. Areas, which do have utilities, will be annotated
―Utilities in area – call ext. to coordinate an on-site locate with the requestor‖, and will be highlighted in fluorescent yellow. The
Contract Inspector will coordinate on-site with each shop highlighted and get the locator’s signature. Once all required areas are signed, the
Contract Inspector will return the permit to Customer Service, building
318, for approval signature. Once this is accomplished, the permit is valid and excavation may begin. The contractor will not begin excavation until an approved digging permit is received from the Contract Inspector.
Notify the Contract Inspector prior to digging. If ground water is encountered, suspend digging and notify the Contract Inspector.
Exploratory digging by hand or vacuum is required within 5 feet of marked underground utilities. Hand digging or vacuum excavation is required when crossing underground utilities. If digging is required parallel and within 10 feet of an existing utility, exploratory digging must be performed by hand or vacuum excavation until the location of the utility is physically confirmed. After the location is physically confirmed digging may be performed by machine.
1.31 DEQ PERMITS FOR SITEWORK AND UTILITIES
Comply with National Pollutant Discharge Elimination System (NPDES) regulations and obtain a NPDES Permit from the Wyoming Department of
Environmental Quality (DEQ) prior to the start of construction when the
GENERAL REQUIREMENTS 01025 - 10
area of the construction site or disturbed area is five (5) acres or more. NPDES regulations regulate storm water runoff. POC for submitting permit application is 90 CES / CEV, Bldg. 367, (307) 775-2213 or 775-
4359. The contractor shall prevent erosion through the use of silt fences, revegitation, etc, even if an NPDES Permit isn’t needed.
1.32 NUCLEAR DEVICES AND RADIOACTIVE MATERIALS
Comply with AFI 40-201 (July 1994), Managing Radioactive Materials in the
USAF, regarding posting Notices to Workers, proper use of equipment and other requirements therein.
Submit written request on company letter head to Base Environmental
Engineering Services (90 AMS / SGPB, Attention: Base Radiation
Protection Officer) prior to bringing onto the Base or using any nuclear devices or radioactive materials. Include description, location and estimated dates of proposed activities; applicable specification pages;
copy of current NRC or Agreement State license; name, address and telephone number of responsible local representative and radiation safety officer (RSO) named on the license; and an acknowledgment that the RSO can make periodic checks to ensure Contractor compliance and suspend operations deemed unsafe.
1.33 WELDING, CUTTING AND BRAZING PERMITS
A permit is required for any welding, torch cutting, sweating, brazing or similar operation using an open flame. Make application on AF Form 592 through the Base Fire Department (90 CES / CEFT), Bldg. 324. Permits must be renewed each month. Fire extinguishers must be on hand during these operations.
Comply with AFOSH STD 91-25 (Nov. 1994).
1.34 SPILL PREVENTION AND RESPONSE
Develop a plan for spill prevention and for spill detection, reporting, containment, cleanup and disposal. The Base Fire Department and the
Environmental Flight shall be immediatly notified when a spill occurs so proper reporting and cleanup can be accomplished. A spill resulting in generating a hazardous waste must be properly disposed. Manifesting of hazardous waste must be signed by a proper authority in the Environmental
Flight IAW Federal State and local laws addressing EPA, DOT, and OSHA requirements.All workers shall be familiar with this plan.
Submit copy of this plan to the Base Contracting Officer on AF Form 3000 for approval. Copies of all disposal manifests (hazardous and non-hazardous) shall be returned to Environmental in 35 days.
1.35 DISPOSAL AND CLEANUP
Remove all debris, waste and surplus materials from the immediate work areas each day and from the premises at suitable intervals. Disposal shall be at an off-Base location at an established landfill or other site approved for the type of material being removed. Burning or burial at the project site are not acceptable disposal methods.
Upon completion of the project, leave site and streets in a clean, sanitary, odor-free, acceptable condition, ready for operation .
GENERAL REQUIREMENTS 01025 - 11
Hose down and broom all concrete slabs, walks, and paved areas.
Rake clean other exterior ground surfaces.
1.36 SYSTEM DEMONSTRATION AND TRAINING
Each Installer of equipment and systems shall meet with Government personnel (Project Inspector, Engineer, User and Maintenance Personnel) and provide complete instructions and demonstrations regarding proper operation including start-up and shut-down, safety procedures, adjustments and maintenance. This service shall be provided by manufacturer's representatives if installers lack sufficient information or experience.
1.37 RECORD DRAWINGS
Upon completion, submit to the Contracting Officer a complete set of clean, undamaged record (as-built) drawings. Mark a set of the contract blueprints in a neat orderly manner as the work progress, showing changes in installation or project conditions including those changes resulting from amendments and contract modifications. Use waterproof red pen or pencil. Give particular attention to concealed elements that would be difficult to measure and record at a later date. Give dimensions to fixed points. As-Builts shall include civil, architectural, structural, mechanical and electrical actual conditions.
1.38 MATERIAL AND EQUIPMENT DISPOSAL
All equipment and material removed by the Contractor shall become the property of the Contractor and be disposed of off base. Oil Filled
Switches shall be disposed in accordance with IAW EPA guidelines, PCB sample test reports are available from the Base Civil Engineer.
1.39 MILITARY REAL PROPERTY INVENTORY
At the conclusion of the project the contractor shall compile and furnish a DDForm 1354, "Transfer and Acceptance of Military Real Property"; to the contracting officer indicating all cost and quantity data of materials and systems furnished and installed. Blank DD Form 1354's and instructions will be furnished to the contractor.
1.40 TRENCHING AND TUNNELING REQUIRMENTS
Avoid trenching near trees to minimize root damage. Where possible, stay beyond the drip line of trees but in no case shall trenching be closer than 15 ft. from center of large trees (36‖ diameter or larger measured at 4 ft. above the ground), 12 ft. from 24‖ to 36‖ diameter trees, 10 ft.
from 18‖ to 24‖ diameter trees, 8 ft. from 12‖ to 18‖ diameter trees, and
6 ft. from trees under 12‖ in diameter.
In general, stop trenching when roots 2 inches or larger are encountered.
When roots 2 inches or larger are accidentally severed, make a sharp cut with a hand saw a couple of inches beyond the ragged end.
If necessary, tunneling at least 24 inches below the surface and away from the trunk as far as possible shall be used instead of trenching in order to comply with the above requirements.
GENERAL REQUIREMENTS 01025 - 12
2 PRODUCTS (NOT APPLICABLE)
3 EXECUTION (NOT APPLICABLE)
SUBMITTAL PROCEDURES 01300 - 1
SECTION 01300
SUBMITTAL PROCEDURES
1.1 APPROVED SUBMITTALS
The Contracting Officer's approval of submittals shall not be construed as a complete check, but will indicate only that the general method of construction, materials, detailing and other information are satisfactory. Approval will not relieve the Contractor of the responsibility for any error which may exist, as the Contractor under the
Contractor's Quality Control (CQC) requirements of this contract is responsible for dimensions, the design of adequate connections and details, and the satisfactory construction of all work. After submittals have been approved by the Contracting Officer, no resubmittal for the purpose of substituting materials or equipment will be considered unless accompanied by an explanation of why a substitution is necessary.
1.2 DISAPPROVED SUBMITTALS
The Contractor shall make all corrections required by the Contracting
Officer and promptly furnish a corrected submittal in the form and number of copies specified for the initial submittal.
1.3 WITHHOLDING OF PAYMENT
Payment for materials incorporated in the work will not be made if required approvals have not been obtained.
3 EXECUTION
3.1 GENERAL
The Contractor shall make submittals as required by the specifications.
The Contracting Officer may request submittals in addition to those specified when deemed necessary to adequately describe the work covered in the respective sections. Units of weights and measures used on all submittals shall be the same as those used in the contract drawings.
Each submittal shall be complete and in sufficient detail to allow ready determination of compliance with contract requirements. Prior to submittal, all items shall be checked and approved by the Contractor's
Quality Control (CQC) representative and each item shall be stamped, signed, and dated by the CQC representative indicating action taken.
Proposed deviations from the contract requirements shall be clearly identified. Submittals shall include items such as: Contractor's, manufacturer's, or fabricator's drawings; descriptive literature including (but not limited to) catalog cuts, diagrams, operating charts or curves; test reports; test cylinders; samples; O&M manuals (including parts list); certifications; warranties; and other such required submittals. Submittals requiring Government approval shall be scheduled and made prior to the acquisition of the material or equipment covered thereby. Samples remaining upon completion of the work shall be picked
SUBMITTAL PROCEDURES 01300 - 2
up and disposed of in accordance with manufacturer's Material Safety Data
Sheets (MSDS) and in compliance with existing laws and regulations.
3.2 SUBMITTAL REGISTER (AF FORM 66)
At the end of this section is one set of AF Form 66 listing items of equipment and materials for which submittals are required by the specifications; this list may not be all inclusive and additional submittals may be required. The Contractor shall complete and submit the forms to the Contracting Officer for approval within 15 calendar days after Notice to Proceed or at the direction of the Contracting Officer.
The approved submittal register will become the scheduling document and will be used to control submittals throughout the life of the contract.
The submittal register and the progress schedules shall be coordinated.
3.3 SCHEDULING
Submittals covering component items forming a system or items that are interrelated shall be scheduled to be coordinated and submitted concurrently. Certifications to be submitted with the pertinent drawings shall be so scheduled. Adequate time (a minimum of 15 calendar days exclusive of mailing time) shall be allowed and shown on the register for review and approval. No delay damages or time extensions will be allowed for time lost in late submittals.
3.4 SUBMITTAL PROCEDURE
3.4.1 Deviations
For submittals which include a proposed deviation requested by the
Contractor, the reason for the deviation shall be annotated on the submittal. The Government reserves the right to rescind inadvertent approval of submittals containing unnoted deviations.
3.5 CONTROL OF SUBMITTALS
The Contractor shall carefully control his procurement operations to ensure that each individual submittal is made on or before the Contractor scheduled submittal date shown on the approved "Submittal Register."
3.6 GOVERNMENT APPROVED SUBMITTALS
Upon completion of review of submittals requiring Government approval, the submittals will be identified as having received approval by being so stamped and dated. Three copies of the submittal will be retained by the
Contracting Officer and the remainder of the submittals will be returned to the Contractor.
CLEARING AND GRUBBING 02110 - 1
SECTION 02110
CLEARING AND GRUBBING
1.1 REFERENCES (NOT APPLICABLE)
1.2 DEFINITIONS
1.2.1 Clearing
Clearing shall consist of the felling, trimming, and cutting of trees into sections and the satisfactory disposal of the trees and other vegetation designated for removal, including down timber, snags, brush, and rubbish occurring in the areas to be cleared.
1.2.2 Grubbing
Grubbing shall consist of the removal and disposal of stumps, roots larger than 3 inches in diameter, matted roots, and subsurface organic material from the designated grubbing areas.
3.1 CLEARING
Brush, and other vegetation in areas to be cleared shall be cut off flush minimum of 12" below the and/or finished ground surface, except such trees and vegetation as may be indicated or directed to be left standing.
Trees designated to be left standing within the cleared areas shall be trimmed of dead branches 1-1/2 inches or more in diameter and shall be trimmed of all branches the heights indicated or directed. Limbs and branches to be trimmed shall be neatly cut close to the bole of the tree or main branches. Trees and vegetation to be left standing shall be protected from damage incident to clearing, grubbing, and construction operations by the erection of barriers or by such other means as the circumstances require.
3.2 GRUBBING
Material to be grubbed, together with logs and other organic or metallic debris not suitable for foundation purposes, shall be removed to a depth of not less than 18 inches below the original surface level of the ground in areas indicated to be grubbed and in areas indicated as construction areas under this contract, such as areas for buildings, and areas to be paved. Depressions made by grubbing shall be filled with suitable material and compacted to make the surface conform with the original adjacent surface of the ground.
CLEARING AND GRUBBING 02110 - 2
3.3 DISPOSAL OF MATERIALS
3.3.1 Materials Other Than Salable Timber
Brush, rotten wood, and other refuse from the clearing and grubbing operations shall be disposed of outside the limits of Government-controlled land at the Contractor's responsibility..
EXCAVATION, TRENCHING, AND BACKFILLING FOR UTILITIES SYSTEMS 02222 - 1
SECTION 02222
EXCAVATION, TRENCHING, AND BACKFILLING FOR UTILITIES SYSTEMS
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to in the text by basic designation only.
AMERICAN SOCIETY FOR TESTING AND MATERIALS (ASTM)
ASTM D 422 (1963; R 1990) Particle-Size Analysis of
Soils
ASTM D 1556 (1990) Density and Unit Weight of Soil in
Place by the Sand-Cone Method
ASTM D 1557 (1991) Laboratory Compaction
Characteristics of Soil Using Modified
Effort (56,000 ft-lbf/cu. ft. (2,700 kN-m/cu. m.))
ASTM D 2487 (1993) Classification of Soils for
Engineering Purposes (Unified Soil
Classification System
ASTM D 3017 (1988; R 1993) Water Content of Soil and
Rock in Place by Nuclear Methods (Shallow
Depth)
ASTM D 2922 (1991) Density of Soil and Soil-Aggregate in Place by Nuclear Methods (Shallow
Depth)
1.1.1 Select Granular Material
Select granular material shall be measured in place as the actual cubic yards replacing wet or unstable material in trench bottoms. The unit price shall include furnishing and placing the granular material, excavation and disposal of unsatisfactory material, and additional requirements for sheeting and bracing, pumping, bailing, cleaning, and other incidentals necessary to complete the work. Payment for select granular material shall be made in addition to the bid price for trench excavation.
1.2 DEFINITIONS
1.2.1 Degree of Compaction
Degree of compaction shall be expressed as a percentage of the maximum density obtained by the test procedure presented in ASTM D 1557.
EXCAVATION, TRENCHING, AND BACKFILLING FOR UTILITIES SYSTEMS 02222 - 2
1.3 SUBMITTALS
Government approval is required for all submittals. The following shall be submitted in accordance with Section 01025GENERAL REQUIREMENTS:
Field Density Tests. Testing of Backfill Materials.
Copies of all laboratory and field test reports within 24 hours of the completion of the test.
Warning and Identification Tape
1.4 UTILITIES
Movement of construction machinery and equipment over pipes and utilities during construction shall be at the Contractor's risk. For work immediately adjacent to or for excavations exposing a utility or other buried obstruction, use hand or light equipment excavation. Start hand or light equipment excavation on each side of the indicated obstruction and continue until the obstruction is uncovered or until clearance for the new grade is assured. Support uncovered lines or other existing work affected by the contract excavation until approval for backfill is granted by the Contracting Officer. Report damage to utility lines or subsurface construction immediately to the Contracting Officer.
2 PRODUCTS
2.1 MATERIALS
2.1.1 Satisfactory Materials
Satisfactory materials shall consist of any material classified by ASTM D
2487 as GW, GP, and SW.
2.1.2 Unsatisfactory Materials
Unsatisfactory materials shall be materials that do not comply with the requirements for satisfactory materials. Unsatisfactory materials include but are not limited to those materials containing roots and other organic matter, trash, debris, frozen materials and stones larger than
3inches, and materials classified in ASTM D 2487, as PT, OH, and OL.
Unsatisfactory materials also include man-made fills, refuse, or backfills from previous construction.
2.1.3 Cohesionless and Cohesive Materials
Cohesionless materials shall include materials classified in ASTM D 2487 as GW, GP, SW, and SP. Cohesive materials include materials classified as GC, SC, ML, CL, MH, and CH. Materials classified as GM and SM will be identified as cohesionless only when the fines are nonplastic.
2.1.4 Rock
Rock shall consist of boulders measuring 1/2 cubic yard or more and materials that cannot be removed without systematic drilling and blasting such as rock material in ledges, bedded deposits, unstratified masses and conglomerate deposits, and below ground concrete or masonry structures, exceeding 1/2 cubic yard in volume, except that pavements will not be considered as rock.
EXCAVATION, TRENCHING, AND BACKFILLING FOR UTILITIES SYSTEMS 02222 - 3
2.1.5 Unyielding Material
Unyielding material shall consist of rock and gravelly soils with stones greater than 3 inches in any dimension or as defined by the pipe manufacturer, whichever is smaller.
2.1.6 Unstable Material
Unstable material shall consist of materials too wet to properly support the utility pipe, conduit, or appurtenant structure.
2.1.7 Select Granular Material
Select granular material shall consist of well-graded sand, gravel, crushed gravel, crushed stone or crushed slag composed of hard, tough and durable particles, and shall contain not more than 10 percent by weight of material passing a No. 200 mesh sieve and no less than 95 percent by weight passing the l inch sieve. The maximum allowable aggregate size shall be 1inches, or the maximum size recommended by the pipe
2.1.8 Initial Backfill Material
Initial backfill shall consist of select granular material or satisfactory materials free from rocks 3 inches or larger in any dimension or free from rocks of such size as recommended by the pipe
2.1.9 Plastic Marking Tape
Plastic marking tape shall be acid and alkali-resistant polyethylene film, 6 inches wide with minimum thickness of 0.004 inch. Tape shall have a minimum strength of 1750 psi lengthwise and 1500 psi crosswise.
The tape shall be manufactured with integral wires, foil backing or other means to enable detection by a metal detector when the tape is buried up to 3 feet deep. The tape shall be of a type specifically manufactured for marking and locating underground utilities. The metallic core of the tape shall be encased in a protective jacket or provided with other means to protect it from corrosion. Tape color shall be as specified in TABLE
1 and shall bear a continuous printed inscription describing the specific utility.
TABLE 1. Tape Color
Red: Electric
Orange: Telephone, Telegraph, Television, Police, and Fire Communications
3.1 EXCAVATION
Excavation shall be performed to the lines and grades indicated. Rock excavation shall include removal and disposition of material defined as rock in paragraph MATERIALS. Earth excavation shall include removal and disposal of material not classified as rock excavation. During excavation, material satisfactory for backfilling shall be stockpiled in an orderly manner at a distance from the banks of the trench equal to 1/2
EXCAVATION, TRENCHING, AND BACKFILLING FOR UTILITIES SYSTEMS 02222 - 4
the depth of the excavation, but in no instance closer than 2 feet.
Excavated material not required or not satisfactory for backfill shall be removed from the site . Grading shall be done as may be necessary to prevent surface water from flowing into the excavation, and any water accumulating therein shall be removed to maintain the stability of the bottom and sides of the excavation. Unauthorized overexcavation shall be backfilled in accordance with paragraph BACKFILLING AND COMPACTION at no additional cost to the Government.
3.1.1 Trench Excavation
The trench shall be excavated as recommended by the manufacturer of the pipe to be installed. Trench walls below the top of the ductbank shall be sloped, or made vertical, and of such width as recommended in the manufacturer's installation manual. Where no manufacturer's installation manual is available, trench walls shall be made vertical. Trench walls more than 5 feet high shall be shored, cut back to a stable slope, or provided with equivalent means of protection for employees who may be exposed to moving ground or cave in. Vertical trench walls more than 3 feet high shall be shored. Trench walls which are cut back shall be excavated to at least the angle of repose of the soil. Special attention shall be given to slopes which may be adversely affected by weather or moisture content. The trench width below the top of pipe shall not exceed 24 inches plus pipe outside diameter (O.D.) for pipes of less than
24 inches inside diameter and shall not exceed 36 inches plus pipe outside diameter for sizes larger than 24 inches inside diameter. Where recommended trench widths are exceeded, redesign, stronger pipe, or special installation procedures shall be utilized by the Contractor. The cost of redesign, stronger pipe, or special installation procedures shall be borne by the Contractor without any additional cost to the Government.
3.1.1.1 Bottom Preparation
The bottoms of trenches shall be accurately graded to provide uniform bearing and support for the bottom quadrant of each section of the ductbank.
3.1.1.2 Removal of Unyielding Material
Where overdepth is not indicated and unyielding material is encountered in the bottom of the trench, such material shall be removed 6 inches below the required grade and replaced with suitable materials as provided in paragraph BACKFILLING AND COMPACTION.
3.1.1.3 Removal of Unstable Material
Where unstable material is encountered in the bottom of the trench, such material shall be removed to the depth directed and replaced to the proper grade with select granular material as provided in paragraph
BACKFILLING AND COMPACTION. When removal of unstable material is required due to the fault or neglect of the Contractor in his performance of the work, the resulting material shall be excavated and replaced by the Contractor without additional cost to the Government.
3.1.1.4 Excavation for Appurtenances
Excavation for manholes or similar structures shall be sufficient to leave at least 12 inches clear between the outer structure surfaces and the face of the excavation or support members. Rock shall be cleaned of loose debris and cut to a firm surface either level, stepped, or
EXCAVATION, TRENCHING, AND BACKFILLING FOR UTILITIES SYSTEMS 02222 - 5
serrated, as shown or as directed. Loose disintegrated rock and thin strata shall be removed. Removal of unstable material shall be as specified above. When concrete or masonry is to be placed in an excavated area, special care shall be taken not to disturb the bottom of the excavation. Excavation to the final grade level shall not be made until just before the concrete or masonry is to be placed.
3.1.1.5 Jacking, Boring, and Tunneling
Unless otherwise indicated, excavation shall be by open cut except that sections of a trench indicated to be jacked, bored, or tunneled
3.1.1.6 Stockpiles
Stockpiles of satisfactory, unsatisfactory and wasted materials shall be placed and graded as specified. Stockpiles shall be kept in a neat and well drained condition, giving due consideration to drainage at all times. The ground surface at stockpile locations shall be cleared, grubbed, and sealed by rubber-tired equipment, excavated satisfactory and unsatisfactory materials shall be separately stockpiled. Stockpiles of satisfactory materials shall be protected from contamination which may destroy the quality and fitness of the stockpiled material. If the
Contractor fails to protect the stockpiles, and any material becomes unsatisfactory, such material shall be removed and replaced with satisfactory material from approved sources at no additional cost to the
Government. Locations of stockpiles of satisfactory materials shall be subject to prior approval of the Contracting Officer.
3.2 BACKFILLING AND COMPACTION
Backfill material shall consist of satisfactory material, select granular material, or initial backfill material as required. Backfill shall be placed in layers not exceeding 6 inches loose thickness for compaction by hand operated machine compactors, and 8 inches loose thickness for other than hand operated machines, unless otherwise specified. Each layer shall be compacted to at least 95 percent maximum density for cohesionless soils and 90 percent maximum density for cohesive soils, unless otherwise specified.
3.2.1 Trench Backfill
Trenches shall be backfilled to the grade shown. The trench shall not be backfilled until all specified tests are performed.
3.2.1.1 Replacement of Unyielding Material
Unyielding material removed from the bottom of the trench shall be replaced with select granular material or initial backfill material.
3.2.1.2 Replacement of Unstable Material
Unstable material removed from the bottom of the trench or excavation shall be replaced with select granular material placed in layers not exceeding 6 inches loose thickness.
3.2.1.3 Bedding and Initial Backfill
Bedding shall be of the type and thickness shown. Initial backfill material shall be placed and compacted with approved tampers to a height
EXCAVATION, TRENCHING, AND BACKFILLING FOR UTILITIES SYSTEMS 02222 - 6
of at least one foot above the ductbank. The backfill shall be brought up evenly on both sides of the ductbank for the full length of the ductbank. Care shall be taken to ensure thorough compaction of the fill along sides and immediately on top of ductbank.
3.2.1.4 Final Backfill
The remainder of the trench, except for special materials for roadways, railroads and airfields, shall be filled with satisfactory material.
Backfill material shall be placed and compacted as follows:
a. Roadways: Water flooding or jetting methods of compaction will not be permitted.
b. Sidewalks, Turfed or Seeded Areas and Miscellaneous Areas:
Backfill shall be deposited in…