Attachment 1 - Statement of Work.pdf

PDF 1 MB Posted

Attached to
Gate Valve Frame Replacement
Solicitation number
FA460826QS053
Issued by

About this file

This is a Statement of Work/Specifications for a repair project at Barksdale Air Force Base, Louisiana. The contract involves replacement of corroded components in a water control gate valve structure at Flag Lake, located at the Natural Resources Office, 6141 Range Road, Barksdale AFB, LA 71110. Specifically, the contractor must replace two vertical frame pieces and one horizontal brace, drill and fit bolt holes in the existing top headrail to attach to the new vertical braces, and remove and reattach an electric motor-driven gate actuator during the process. The government will provide all replacement materials, including the vertical frame rails, horizontal brace, and connecting hardware as specified by the manufacturer. The valve serves critical functions: it allows Flag Lake to be lowered below spillway capacity to promote organic debris decay during summer months and assists spillway operations during extreme high-water events.

The contractor is responsible for unbolting the old frame from the concrete headwall, installing new components in accordance with gate manufacturer specifications, and ensuring the gate operates freely through a complete functional cycle from full open to full close with proper sealing. The contractor must maintain a neat and safe work site, remove all tools, equipment, staging materials, and residual debris upon completion, and restore the job site and surrounding areas to a condition equal to or better than the existing condition. The contractor bears sole responsibility for lawful off-base disposal of all demolished materials, specifically three pieces of removed corroded steel angle iron, and may not use government dumpsters or base waste receptacles. Final acceptance is contingent upon successful completion of a joint operational check conducted with the government Point of Contact, demonstrating complete, uninhibited functional operation without binding, followed by verification of full site cleanup.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK/SPECIFICATIONS

FOR REPLACEMENT OF FLAG LAKE GATE VALVE FRAME STRUCTURE

Natural Resources Office 6141 Range Road, Barksdale AFB, LA 71110

BACKGROUND: The existing water control gate valve at Flag Lake has a frame that is corroded to the point that the gate will not slide up and down the frame without hanging up. This contract is to have two vertical frame pieces and one horizontal brace replaced and some additional drilling and fitment of the top headrail to those same vertical pieces. Natural Resources Office, 6141 Range Road, Barksdale AFB, LA 71110.

JUSTIFICATION: This valve allows the lowering of Flag Lake below the minimal amount capable by utilization of the lake spillway.

Periodically the lake needs to be lowered during the summer to promote decay of organic debris on the bottom of the lake shoreline.

This valve is the only way that can be accomplished.

Additionally, it is utilized during extreme high-water events to lower the lake back to normal pool level, assisting the spillway.

DESCRIPTION: This project involves replacing two rusted vertical frame pieces and one horizontal brace of the original gate valve structure. The primary connection of the gate valve to the existing concrete headwall occurs at the lower section of these frame pieces.

The old frame will have to be unbolted from the headwall, new components replaced and then the structure with the new components installed will have to be reattached to the headwall in accordance with gate manufacturers specifications. Upon completion the gate should be fully functional, opening and closing freely from proper sealing at closure to fully open. The existing top headrail has been replaced previously, and several bolt holes will need to be drilled to properly attach the headrail to the new vertical braces. In addition, there is an existing electric motor driven gate actuator mounted to the headrail that will need to be removed and reattached during this process.

MATERIALS: The replacement vertical frame rails and the horizontal brace will be provided by the government, including connecting hardware as provided by the manufacturer.

SITE CLEANUP: Site Condition: The Contractor shall maintain the work site in a neat, safe, and orderly manner always. Upon completion of all mechanical work, the Contractor shall remove all tools, equipment, staging materials, and residual debris. The job site, surrounding shoreline, and access pathways must be restored to a condition equal to or better than the existing condition at project commencement.

WASTE DISPOSAL: The Contractor shall be solely responsible for the complete removal and lawful off-base disposal of all demolished materials resulting from the frame replacement, specifically including three (3) pieces of removed, corroded steel angle iron. The Contractor shall not utilize Government dumpsters or base waste receptacles for disposal.

INSPECTION, OPERATIONAL CHECK AND ACCEPTANCE: Formal Inspection: Upon completion of the gate valve frame installation, the Contractor shall notify the designated Government Point of Contact (POC) to schedule a formal on-site inspection.

a. Operational Check (Ops Check): Final Government acceptance is contingent upon a successful joint operational test conducted in the presence of the Government POC. The Contractor shall demonstrate a complete, uninhibited functional cycle (full open and full close) of the gate valve mechanism to ensure proper alignment, structural rigidity, and smooth manual or mechanical operation without binding.

b. Acceptance: The Government POC will issue formal acceptance only after the successful operational check and verification of full site cleanup.

FA460826QS053

Attachment 1

1 September 2026