FA4608-12-R-0005 RFP.pdf
PDF 425 KB Posted
- Attached to
- Demolish Lemay Auditorium
- Solicitation number
- FA4608-12-R-0005
About this file
Solicitation - RFP
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Site - Auditorium Demo.pdf | ||
| B7227 Site - Utilities.pdf | ||
| Questions from Site Visit.docx | DOCX document | |
| Site Image - Auditorium.PNG | PNG image | |
| B7227 Site - Utilities.pdf | ||
| Site Image - Auditorium.PNG | PNG image | |
| Questions from Site Visit.docx | DOCX document | |
| Site - Auditorium Demo.pdf | ||
| Sign In Sheet.pdf | ||
| Attachment 5 - Insurance.pdf | ||
| Attachment 6 - AFI 32-1001.pdf | ||
| Attachment 2 - Environmental.pdf | ||
| Attachment 4 - AF66.pdf | ||
| Attachment 7- Asbestos Report.pdf | ||
| Attachment 3 - BAFBI 33-2.pdf | ||
| Attachment 1- Wage Determination.pdf |
Show all 16
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
The Contractor w ill demolish bldg 7227, LeMay Auditorium and restore the site to match the surrounding area per the attached statement of w ork and applicable codes and standards.
This requirement is set-aside for Economically Disadvantaged Women Ow ned Small Businesses (EDWOSB) in accordance w ith Federal
Acquisition Regulation 19.5 and FAR 19.15.
In accordance w ith FAR 36.204(c) Magnitude of Construction Projects, the price range of this project is anticipated to be betw een $100,000 and $250,000.
Site Visit: A pre-bid site visit w ill be held on March 22, 2012 at 8:00am. Interested parties must be at the 2d Contracting Squadron, Bldg 5441, 41 Vandenberg Avenue, Barksdale AFB, LA at this time. This site visit w ill be held in conjunction w ith three other similar projects. Please call
Jeffery Hairston at (318) 456-6739 for information on obtaining entry to the base.
Notice to Offerors: Funds are not presently available for this effort. No aw ard w ill be made under this solicitation until funds are available.
The Government reserves the right to cancel this solicitation, either before or after the closing date. In the event the Government cancels this solicitation, the Government has no obligation to reimburse an offeror for any costs.
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS
NEGOTIATED
12-Mar-2012
(RFP)
(IFB)
X
CALL:
Demolish Lemay Auditorium
B. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)
See Item 7
2. TYPE OF SOLICITATION
SEALED BID
3. DATE ISSUED
9. FOR INFORMATION A. NAME
SOLICITATION
NSN 7540-01-155-3212 1442-101 STANDARD FORM 1442 (REV. 4-85)
Prescribed by GSA
FAR (48 CFR) 53.236-1(e)
11. The Contractor shall begin performance w ithin _______30 calendar days and complete it w ithin ________210 calendar days after receiving aw ard, X notice to proceed. This performance period is mandatory, X negotiable. (See _________________________FAR 52.211-10
12 A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If "YES," indicate within how many calendar days after award in Item 12B.)
X YES NO
13. ADDITIONAL SOLICITATION REQUIREMENTS:
A. Sealed offers in original and __________1 copies to perform the w ork required are due at the place specif ied in Item 8 by ___________ local time ______________11 Apr 2012 (date). If this is a sealed bid solicitation, offers must be publicly opened at that time.
shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.
B. An offer guarantee is, X is not required.
C. All offers are subject to the (1) w ork requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
D. Offers providing less than _______210 calendar days for Government acceptance after the date offers are due w ill not be considered and w ill be rejected.
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair)
1. SOLICITATION NO.
IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.
4. CONTRACT NO.
7. ISSUED BY CODE
2 CONS/LGC - FA4608
41 VANDENBERG AVE
BARKSDALE AFB LA 71110-2079
FA4608
PAGE OF PAGES
1 OF
CODE
(Title, identifying no., date):
12B. CALENDAR DAYS
03:00 PM (hour)
Sealed envelopes containing offers
5. REQUISITION/PURCHASE REQUEST NO. 6. PROJECT NO.
AWUB 11-0040
8. ADDRESS OFFER TO (If Other Than Item 7)
318-456-3294FAX:TEL: 318-456-2113 TEL: FAX:
FA4608-12-R-0005 41
20B. SIGNATURE
(REV. 4-85)STANDARD FORM 1442 BACK
TO SIGN
NSN 7540-01-155-3212
SOLICITATION, OFFER, AND AWARD (Continued)
(Construction, Alteration, or Repair)
CODE FACILITY CODE
17. The offeror agrees to perform the w ork required at the prices specif ied below in strict accordance w ith the terms of this solicitation, if this offer is accepted by the Government in w riting w ithin ________ calendar days after the date offers are due.
the minimum requirements stated in Item 13D. Failure to insert any number means the offeror accepts the minimum in Item 13D.)
AMOUNTS SEE SCHEDULE OF PRICES
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AMENDMENT NO.
DATE
20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN
OFFER (Type or print)
AWARD (To be completed by Government)
21. ITEMS ACCEPTED:
22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM
(4 copies unless otherwise specified)
CODE
(Insert any number equal to or greater than
20C. OFFER DATE
25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
10 U.S.C. 2304(c) 41 U.S.C. 253(c)
CODE27. PAYMENT WILL BE MADE BY:26. ADMINISTERED BY
(Include ZIP Code)14. NAME AND ADDRESS OF OFFEROR 15. TELEPHONE NO. (Include area code)
See Item 14
(Include only if different than Item 14)16. REMITTANCE ADDRESS
30B. SIGNATURE
29. AWARD (Contractor is not required to sign this document.)
document and return _______ copies to issuing office.) Contractor agrees Your of f er on this solicitation, is hereby accepted as to the items listed. This award con-to f urnish and deliv er all items or perf orm all work, requisitions identif ied summates the contract, which consists of (a) the Gov ernment solicitation and on this f orm and any continuation sheets f or the consideration stated in this y our of f er, and (b) this contract award. No f urther contractual document is contract. The rights and obligations of the parties to this contract shall be necessary .
gov erned by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certif ications, and specif ications or incorporated by ref er-ence in or attached to this contract.
30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31A. NAME OF CONTRACTING OFFICER (Type or print)
30C. DATE
(Type or print)
TEL: EMAIL:
31B. UNITED STATES OF AMERICA 31C. AWARD DATE
BY
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
(Contractor is required to sign this28. NEGOTIATED AGREEMENT
(M ust be fully completed by offeror)OFFER
FA4608-12-R-0005
Section B - Supplies or Services and Prices
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0001 1 Lot
AWUB 11-0040, DEMO LEMAY AUDITORIUM
FFP
The contractor shall provide all labor, materials, equipment, supervision and transportation necessary to accomplish AWUB 11-0040, Demolish LeMay
Auditorium in accordance with Statment of Work attached herein. WO# A51218
FOB: Destination
NSN: P400-12-DEM-ADTM
SIGNAL CODE: A
NET AMT
Section C - Descriptions and Specifications
STATEMENT OF WORK
Statement of Work for
AWUB 11-0040: Demolish LeMay Auditorium, B7227
Project shall include the furnishing of all materials, labor, and equipment necessary for the complete demolition of buildings and associated pavements to include all equipment remaining inside and outside the building. Complete the design to perform demolition as indicated on drawings in accordance with UFC 1-200-01 General Building Requirements which includes the latest editions of the International Building Code, Architectural Barriers Act, and NFPA Life
Safety Code. All required work shall be accomplished in accordance with the Barksdale AFB
Design Compatibility Guidelines (DCG).
Building 7227 consists of 4,533 square feet.
1. The building tested positive for asbestos containing materials. The Asbestos Inspection
Assessment Report is listed as Attachment 7 to the RFP. An asbestos abatement shall be accomplished by a licensed asbestos abatement contractor trained in the proper removal and disposal of the material encountered per State and Federal regulations. State notification and disposal form shall be forward to the base at the completion of abatement.
2. Contractor shall obtain a 2 CES Digging Permit (AF Form 103) prior to beginning work.
See attachment for approximate locations of utilities.
3. Coordinate all utility removal and outages with proper base agencies at least seven (7) business days prior to performing the work. Also, notify the 2d Civil Engineer Technical
Support at least seven (7) business days prior to covering capped utilities, so they can mark for location and depth for base GEOBASE files.
4. Demolish and remove all existing partitions, walls, roof, HVAC systems, electrical systems, plumbing fixtures, and any remaining miscellaneous equipment. Generally, all utilities servicing the buildings shall be removed back to the source.
5. Electrical, base telecommunications (contact 2d Communications Sq) and commercial telephone service (contact AT&T), and cable TV services (contact 2d Communications Sq) will be terminated at the poles or as otherwise directed. See below for additional
Communications requirements.
6. Sanitary sewer lines, domestic water lines, fire protection lines, mechanical chilled water supply and return lines, and gas lines shall be cut and capped at the main or cut and capped at valves near mains as directed by 2d Civil Engineer personnel.
7. Demolish and remove existing floor slabs, walkways, and concrete landings and stairs to include all footings, piers, reinforcement material and supports or any other objects used to support the building. Remove all exterior equipment foundations and pads.
8. Demolish and remove all existing landscape and hardscape around the perimeter of the buildings to include, but not limited to trees, shrubs, pavers, and loose stone. Contracting
Officer’s Representative shall designate landscaping to remain during demolition prior to starting work. Designated landscape shall be protected from damage by Contractor.
9. Provide and install backfill material to restored land area to match contour and condition of adjacent areas. Compact in proper lifts as required preventing settling of area. Match contour of land around so as not to create water-pooling problems or inhibit the proper draining of surrounding land areas. The top six-inch layer of all fill areas shall be sifted topsoil suitable for grass placement.
10. Hydro-seed and fertilize with Bermuda/rye mix or Centipede/rye mix depending on the season to completely cover all exposed bare dirt areas and any grass damaged by the contractor. Contractor shall water and maintain seeded area until rooting takes place and replacing any areas that die or does not take properly. Government will determine when seeded area has properly taken and watering can be stopped by the Contractor.
11. Contractor shall be responsible for installing and maintaining erosion control to prevent debris and mud from washing down into the storm drains and natural swales. Contractor shall also be responsible for maintaining the existing base roadways free of mud and debris during demolition and hauling procedures. Contractor shall ensure safety of base personnel during demolition and shall clearly mark the site using cones, barricades, warning tape, construction fence, or any other object suitable for such use.
12. Demolition Materials: All demolition materials under this contract become property of the
Contractor and must be removed completely from the Base. All materials, equipment, supplies left in the building or demolished at beginning of work shall become property of the Contractor. Burial of demolition debris on-site shall not be allowed.
13. Acceptance of completed work will be based on its conformance to the contract.
Nonconforming work will be rejected. The Air Force is not obligated to accept nonconforming work at a reduced price. The contractor shall start correction of rejected work within 10 calendar days after receipt of the rejection notice.
14. It will be the Contractor’s responsibility to visit the site and become familiar with the facilities to be demolished and include all work and equipment required in the bid. It is the
Government’s desire that the end result of this contract be a clean fully restored site with all evidence of prior construction or facility location removed.
15. Upon completion of project, instruct base personnel on the location that utilities were cut off and capped for future reference.
16. The contractor will be responsible for and incur any and all labor and material costs required to repair any damages to government facilities that occurred during and as result of demolition operations under this contract. This damage will be identified as separate from the condition of the facilities as identified during the initial inspection. The damage will be identified, but not limited, to the following items.
a. Government gas, water, waste, and electric transmission and distribution systems.
b. Adjacent occupant personal property.
c. Existing trees.
d. Roadways and Parking Areas.
16. Additional Information
a. The contractor will begin work not earlier than 7:30 am each workday. Work will not be performed later than 6:00 pm.
b. Inspections will be conducted by the Contracting Officer and /or Contracting Officer’s
Representative and the contractor’s manager.
c. All discrepancies, if any, will be noted on provided drawings.
d. If Work is in a Restricted High Security Area, special security actions and precautions will be required as directed by the Contracting Officer’s Representative.
Communications Requirements:
Include a two week lead time to have communications cables cleared from building.
The contractor shall provide 2d Communications Squadron (2CS) the following:
1 Each 6.5‖ x 28‖ Stainless Splice Closure part# 8006367
3 Each 3M HIGH GEL FOIL Closed Mixing Pouch REENTERABLE ENCAP Part# 8882-3000/F
2 Each 3M HIGH GEL FOIL Closed Mixing Pouch REENTERABLE ENCAP Part# 8882-1500/F
The contractor shall remove redundant copper cable from the area, once 2 CS identifies what is redundant. Any redundant copper cable will be clearly marked.
If you have any questions or concerns please contact:
Allen Plavny or Greg McCallie
318-456-6617 318-456-4840
Cell, 318-208-2133 Cell, 318-208-2136
End of Statement of Work
Section E - Inspection and Acceptance
INSPECTION AND ACCEPTANCE TERMS
Supplies/services will be inspected/accepted at:
CLIN INSPECT AT INSPECT BY ACCEPT AT ACCEPT BY
0001 Destination Government Destination Government
CLAUSES INCORPORATED BY REFERENCE
52.246-12 Inspection of Construction AUG 1996
Section F - Deliveries or Performance
DELIVERY INFORMATION
CLIN DELIVERY DATE QUANTITY SHIP TO ADDRESS UIC
0001 210 Calendar Days after issuance of Notice to
Proceed
1 2 MSG/CES/CERF - F1G3A2
334 DAVIS AVE W
STE 300
BARKSDALE AFB LA 71110
FOB: Destination
F1G3A2
PERFORMANCE
F-800 NOTICE TO PROCEED
NOTICE TO PROCEED will be issued within 30 calendar days after award of contract. Award date shall be established as the date of mailing or otherwise furnishing a property executed award document to the successful offeror.
F-801 WORK SCHEDULE
Working hours for the contractor will normally be between the hours of 7:30 a.m. and 6 p.m. excluding Saturdays, Sundays and Federal Holidays (New Year’s Day, Birthday of Martin Luther King, Jr., Presidents Day, Memorial
Day, Independence Day, Labor Day, Columbus Day, Veteran’s Day, Thanksgiving Day and Christmas Day). If the contractor desires to work during periods other than above, additional government inspection forces may be required. The contractor must notify the contracting officer three days in advance of his/her intention to work during other periods to allow assignment of additional inspection forces when the conracting officer determines they are reasonably available. If such force is reasonably available, the contracting officer may authorize the contractor to perform work during periods other than normal duty hours/days, however, if inpsections are requried to perform in excess of their normal duty hours/days solely for the benefit of the contractor, the actual cost of inspection at overtime rates will be charged to the contractor. These adjustments to the contract price may be made periodically as directed by the contracting officer.
Section G - Contract Administration Data
CONTRACT ADMINISTRATION
ADMINISTRATIVE DATA
(a) Following award, this contract will be administered by the 2d Contracting Squadron. The name, address, telephone number, and fax number of the Contracting Officer and Administrator are as follows:
CO: Marla J. Poirier
41 Vandenberg Ave
Barksdale AFB LA 71110-2079
Phone: 318-456-6833
Fax: 318-456-3294
E-mail: marla.poirier@us.af.mil
Admin: Jeffery D. Hairston
Phone: 318-456-6739
Fax: 318-456-3294
E-mail: jeffery.hairston@us.af.mil
(b) The Contracting Officer (CO), is the only person authorized to approve changes or modify any of the requirements under this contract and notwithstanding any provisions contained elsewhere in this contract, the said authority remains solely in the CO. In the event the Contractor effects any such change at the direction of any person other than the CO, the change will be considered to have been made without authority and no adjustment will be made in the contract price to cover any increase in costs incurred as a result thereof.
252.232-7003 Electronic Submission of Payment Requests and Receiving
Reports
MAR 2008
mailto:marla.poirier@us.af.mil
Section H - Special Contract Requirements
SPECIAL CONTRACT REQUIREMENTS
H-109. REQUIRED INSURANCE
(IAW FAR 28.306(b) and FAR 52.228-5)
Reference FAR clause entitled "Insurance..." the Contractor shall, at its own expense, procure and thereafter maintain the following kinds of insurance with respect to performance under the contract.
a. Workmen’s Compensation and Employers Liability Insurance as required by law except that if this contract is to be performed in a State which does not require or permit private insurance, then compliance with the statutory or administrative requirements in any such State will be satisfactory. The required Workmen's
Compensation insurance shall extend to cover employer's liability for accidental bodily injury or death and for occupational disease with a minimum liability limit of $100,000.
b. General Liability Insurance. Bodily injury liability insurance, in the minimum limits of $500,000 per occurrence shall be required on the comprehensive form of policy.
c. Automobile Liability Insurance. This insurance shall be required on the comprehensive form of policy and shall provide bodily injury liability and property damage liability covering the operation of all automobiles used in connection with the performance of the contract. At least the minimum limits of $200,000 per person and
$500,000 per occurrence for bodily injury and $20,000 per occurrence for property damage shall be required.
H-804. BONDS
a. Bid Guarantee – Not required
b. Performance and Payment Bonds. In accordance with the Miller Act (40 U.S.C. 3131), the bidder to whom the award is made shall within fifteen (15) calendar days after the award of the contract furnish a
Performance Bond (Standard Form 25) and a Payment Bond (Standard Form 25A), each with good and sufficient surety or sureties acceptable to the Government. (Not required for contracts of $30,000.00 or less).
Contracts exceeding the $150,000 (Miller Act--.
(1) Performance bonds. Unless the contracting officer determines that a lesser amount is adequate for the protection of the Government, the penal amount of performance bonds must equal--
(i) 100 percent of the original contract price; and
(ii) If the contract price increases, an additional amount equal to 100 percent of the increase.
(2) Payment Bonds.
(i) Unless the contracting officer makes a written determination supported by specific findings that a payment bond in this amount is impractical, the amount of the payment bond must equal-
(A) 100 percent of the original contract price; and
(B) If the contract price increases, and additional amount equal to 100 percent of the increase.
(ii) The amount of the payment bond must be no less than the amount of the performance bond.
c. The contractor will not be allowed to start work prior to furnishing the required bonds, including any necessary reinsurance agreements.
H-805. PROGRESS SCHEDULES AND REPORTS
(a) In accordance with FAR 52.236-15, the reports contemplated by the clause titled "Schedules for
Construction Contracts" shall be accomplished on and in accordance with instruction pertaining to AF Form
3064, Contract Progress Schedule, and AF Form 3065, Contract Progress Report. Mobilization/demobilization will not be allowed as a line item on the Progress Schedule. Costs for those items must be included in other elements of work.
(b) Upon award of the contract and as required, the contractor will be furnished (3) copies of the AF Form
3064, Contract Progress Schedule. The Progress Schedule must be approved by the Government prior to start of physical work on the project job site.
H-806. PREPARATION OF MATERIAL APPROVAL SUBMITTALS
In accordance with FAR 52.236-5, the submittals contemplated by the clause herein entitled "Material and
Workmanship" shall be accomplished on and in accordance with instructions pertaining to AF Form 3000, Material Approval Submittal.
H-807. INTERRUPTION OF UTILITY SERVICES
The Government may not be held responsible for interruptions of utility service and will not be liable for contractor delays, damages, or increased costs occasioned by any such interruption of service.
H-808. SUPERINTENDENCE OF CONTRACT
In accordance with FAR 52.236-6, at all times during performance of this contract and until work is completed and accepted, the contractor shall provide a superintendent who will be on the job site at all times when work is being performed. The superintendent will be responsible for ALL employees (including subcontractors) and have the authority to plan work and direct ALL employees. The superintendent will be appointed in writing and this letter submitted to the Contracting Officer, setting forth the authority delegated to the superintendent.
H-809 CONTRACT COMPLETION INSPECTIONS
The contractor will schedule (preferably with 3 working days notice) a pre-completion inspection to be held approximately 10 calendar days prior to the expiration of the contract. This inspection may result in a
"punchlist" indicating items to be furnished or work to be completed by the contractor or subcontractors in order to complete the work specified in the contract documents. This list may not be construed to be all inclusive. A copy of the list will be furnished to the contractor within 2 workdays for his use in completing the contractual work. If the pre-completion inspection results in no "punchlist" and the work is complete, this inspection may be considered the "final" inspection as determined by the Contracting Officer.
If required, the contractor will be responsible for scheduling the contract completion inspection (preferably with
3 working days notice) to be held no later than the final day of contract performance. Should this inspection result in a "punchlist", the contractor will have 10 calendar days (after receipt of punchlist) to complete all punchlist items and notify the Contracting Officer of this. NO FINAL INVOICE SHALL BE PAID UNTIL
ALL PUNCHLIST ITEMS ARE COMPLETED TO THE SATISFACTION OF THE CONTRACTING
OFFICER. Should a contractor exceed the time allowed for these corrections, it may result in negative past performance which could affect future contract awards.
H-811. CLASS I OZONE DEPLETING SUBSTANCES/CHEMICALS
If this project has any materials or equipment that contains Class I Ozone depleting substances/chemicals, you are required to contact the Contracting Officer, 318/456-6833, for further instructions prior to providing the product or equipment.
CLAUSES INCORPORATED BY FULL TEXT
BOSSIER CITY -- PARISH SALES AND USE TAX
Bossier City and Bossier Parish levy a use tax defined by state and local sales tax law. As such, these sales are taxable at the point of delivery to the "contractor" (consumer). If the sales or use tax is not collected by the vendor, tax is payable directly to the jurisdiction in which delivery is made. Contractors and subcontractors are each individually liable for sales and use tax on the basis of their individual purchase transactions. This tax may extend to equipment leased or rented to the Government. It may also extend to supplies and equipment purchased elsewhere, but brought into Bossier Parish for final use. All contractors are cautioned to assure themselves of any liability for this tax. The local telephone number for questions concerning this tax is A/C 318 741-8551.
CONTRACTOR/VENDOR ACCESS TO BARKSDALE AFB
All commercial vehicles are required to enter Barksdale AFB through the East Gate, just off I-20 and Industrial
Drive. This includes construction, food, supply, FedEX, and UPS deliveries, as well as contractors entering with company trucks. Contractors entering in their privately owned vehicles with an approved pass will be allowed entry at any gate. Hours of operation for the East Gate are 0500-2200 Monday through Friday, Saturday 0600-1200.
Background Checks for Contractor Personnel Requiring Entry/Access to Barksdale AFB (Jan 2005)
Security Forces will conduct a National Crime and Information Center (NCIC) background check on all contractor or subcontractor personnel prior to granting access to the installation.
(End of Clause)
CELL PHONE POLICY
The use of cell phones while operating a moving vehicle on Barksdale AFB is prohibited, unless the phone is operated in a ―hands free‖ mode. ―Use of cell phones‖ includes placing calls, retrieving stored information from the phone, programming the phone, talking on the phone, and receiving calls, regardless of the source. Violators may be issued a citation and assessed 3 points on their base driving record. Additional points may be assessed if cell phone use is found to be a contributing factor in a motor vehicle accident.
Lay-down Area Temporary Fencing
1. The Contractor shall furnish all labor, materials, and equipment necessary to provide secure and visually aesthetic temporary fencing for surrounding project equipment and material in lay-down areas.
Work shall include:
a. Clearing area of all encumbrances to safe erection of fencing.
b. Provide fence that is: metal tube frame; metal woven wire mesh (minimum 11 gauge); minimum 6 feet in height.
c. Provide integral to fence visual blocking material, either slat weave or sheet goods.
d. Erecting fence in such manner as to prevent loss of fencing or blocking due to inclement weather.
e. At no time shall fence interfere with fire egress paths or fire equipment ingress, to include periods when gates are in operation.
Contractor shall submit cut sheets on all items for installation, prior to procurement, for approval by the C.E.
Architect. Complete the design as indicated on drawings in accordance with UFC 1-200-01 General Building
Requirements which includes the latest editions of the International Building Code and NFPA Life Safety Code, and
Americans with Disabilities Act. All required work shall be accomplished in accordance with the Barksdale AFB
Design Compatibility Guidelines (DCG). All colors and materials shall be selected by the Civil Engineer Architect in accordance with the DCG. Construction shall be conducted in a quality workmanlike manner. Contractor shall take any steps necessary to protect government and occupant property from damage caused by weather or other occurrence while work is in progress.
2. Upon notification of completion by the contractor a determination will be made as to the satisfactory completion and acceptance of the contract specification(s). Any segment of the operation that is not acceptable because of an unsightly or unprofessional appearance will be justification for rejection of the treatment. The contractor will incur all costs, both labor and materials, for reaccomplishment of any unacceptable work identified.
3. The contractor will be responsible for and incur any and all labor and material costs required to repair any damages to government facilities that occurred during and as result of repair work, replacement operations, or new work, under this contract. This damage will be identified as separate from the condition of the facilities as identified during the initial inspection. The damage will be identified, but not limited, to the following items.
a. Government gas, water and electric transmission and distribution systems
b. Occupant personal property
Additional Information.
a. The contractor will begin work not earlier than 7:30 am each workday. Work will not be performed later than 6:00 pm.
b. Inspections will be conducted by the Contracting Officer and /or Contracting Officer’s Representative and the Contractor’s Manager.
c. Any discrepancies should be noted and forwarded to the Architect.
Section I - Contract Clauses
52.204-7 Central Contractor Registration FEB 2012
52.209-6 Protecting the Government's Interest When Subcontracting
With Contractors Debarred, Suspended, or Proposed for
Debarment
DEC 2010
52.209-10 Prohibition on Contracting With Inverted Domestic
Corporations
MAY 2011
52.215-8 Order of Precedence--Uniform Contract Format OCT 1997
52.222-1 Notice To The Government Of Labor Disputes FEB 1997
52.222-3 Convict Labor JUN 2003
52.222-5 Davis-Bacon Act--Secondary Site of the Work JUL 2005
52.222-6 Davis Bacon Act JUL 2005
52.222-7 Withholding of Funds FEB 1988
52.222-8 Payrolls and Basic Records JUN 2010
52.222-9 Apprentices and Trainees JUL 2005
52.222-10 Compliance with Copeland Act Requirements FEB 1988
52.222-11 Subcontracts (Labor Standards) JUL 2005
52.222-12 Contract Termination-Debarment FEB 1988
52.222-13 Compliance with Davis-Bacon and Related Act Regulations. FEB 1988
52.222-14 Disputes Concerning Labor Standards FEB 1988
52.222-15 Certification of Eligibility FEB 1988
52.222-21 Prohibition Of Segregated Facilities FEB 1999
52.222-26 Equal Opportunity MAR 2007
52.222-27 Affirmative Action Compliance Requirements for
Construction
FEB 1999
52.222-35 Equal Opportunity for Veterans SEP 2010
52.222-36 Affirmative Action For Workers With Disabilities OCT 2010
52.222-37 Employment Reports on Veterans SEP 2010
52.222-50 Combating Trafficking in Persons FEB 2009
52.222-99 Notification of Employee Rights under the National Labor
Relations Act.
JUN 2010
52.223-2 Affirmative Procurement of Biobased Products Under Service and Construction Contracts
DEC 2007
52.223-3 Hazardous Material Identification And Material Safety Data JAN 1997
52.223-5 Pollution Prevention and Right-to-Know Information MAY 2011
52.223-6 Drug-Free Workplace MAY 2001
52.223-17 Affirmative Procurement of EPA-Designated Items in Service and Construction Contracts
MAY 2008
52.223-18 Encouraging Contractor Policies To Ban Text Messaging
While Driving
AUG 2011
52.225-13 Restrictions on Certain Foreign Purchases JUN 2008
52.227-1 Authorization and Consent DEC 2007
52.227-2 Notice And Assistance Regarding Patent And Copyright
Infringement
DEC 2007
52.227-4 Patent Indemnity-Construction Contracts DEC 2007
52.228-2 Additional Bond Security OCT 1997
52.228-11 Pledges Of Assets JAN 2012
52.228-12 Prospective Subcontractor Requests for Bonds OCT 1995
52.228-14 Irrevocable Letter of Credit DEC 1999
52.228-15 Performance and Payment Bonds--Construction OCT 2010
52.232-5 Payments under Fixed-Price Construction Contracts SEP 2002
52.232-23 Assignment Of Claims JAN 1986
52.232-27 Prompt Payment for Construction Contracts OCT 2008
52.232-33 Payment by Electronic Funds Transfer--Central Contractor
Registration
OCT 2003
52.233-1 Disputes JUL 2002
52.233-3 Protest After Award AUG 1996
52.233-4 Applicable Law for Breach of Contract Claim OCT 2004
52.236-5 Material and Workmanship APR 1984
52.236-6 Superintendence by the Contractor APR 1984
52.236-7 Permits and Responsibilities NOV 1991
52.236-8 Other Contracts APR 1984
52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements
APR 1984
52.236-10 Operations and Storage Areas APR 1984
52.236-11 Use and Possession Prior to Completion APR 1984
52.236-12 Cleaning Up APR 1984
52.236-13 Accident Prevention NOV 1991
52.236-14 Availability and Use of Utility Services APR 1984
52.236-17 Layout of Work APR 1984
52.236-21 Specifications and Drawings for Construction FEB 1997
52.242-14 Suspension of Work APR 1984
52.242-15 Stop-Work Order AUG 1989
52.243-4 Changes JUN 2007
52.243-5 Changes and Changed Conditions APR 1984
52.248-3 Value Engineering-Construction OCT 2010
52.249-2 Termination For Convenience Of The Government (Fixed-
Price)
MAY 2004
52.249-10 Default (Fixed-Price Construction) APR 1984
52.249-10 Alt I Default (Fixed-Price Construction) (Apr 1984) Alternate I APR 1984
52.253-1 Computer Generated Forms JAN 1991
252.203-7000 Requirements Relating to Compensation of Former DoD
Officials
SEP 2011
252.203-7002 Requirement to Inform Employees of Whistleblower Rights JAN 2009
252.204-7004 Alt A Central Contractor Registration Alternate A SEP 2007
252.223-7006 Prohibition On Storage And Disposal Of Toxic And
Hazardous Materials
APR 1993
252.232-7010 Levies on Contract Payments DEC 2006
252.236-7000 Modification Proposals-Price Breakdown DEC 1991
252.243-7001 Pricing Of Contract Modifications DEC 1991
252.247-7023 Transportation of Supplies by Sea MAY 2002
252.247-7023 Alt III Transportation of Supplies by Sea (May 2002) Alternate III MAY 2002
52.204-10 REPORTING EXECUTIVE COMPENSATION AND FIRST-TIER SUBCONTRACT AWARDS
(FEB 2012)
(a) Definitions. As used in this clause:
Executive means officers, managing partners, or any other employees in management positions.
First-tier subcontract means a subcontract awarded directly by a Contractor to furnish supplies or services (including construction) for performance of a prime contract, but excludes supplier agreements with vendors, such as long-term arrangements for materials or supplies that would normally be applied to a Contractor's general and administrative expenses or indirect cost.
Total compensation means the cash and noncash dollar value earned by the executive during the Contractor's preceding fiscal year and includes the following (for more information see 17 CFR 229.402(c)(2)):
(1) Salary and bonus.
(2) Awards of stock, stock options, and stock appreciation rights. Use the dollar amount recognized for financial statement reporting purposes with respect to the fiscal year in accordance with the Financial Accounting Standards
Board's Accounting Standards Codification (FASB ASC) 718, Compensation-Stock Compensation.
(3) Earnings for services under non-equity incentive plans. This does not include group life, health, hospitalization or medical reimbursement plans that do not discriminate in favor of executives, and are available generally to all salaried employees.
(4) Change in pension value. This is the change in present value of defined benefit and actuarial pension plans.
(5) Above-market earnings on deferred compensation which is not tax-qualified.
(6) Other compensation, if the aggregate value of all such other compensation (e.g., severance, termination payments, value of life insurance paid on behalf of the employee, perquisites or property) for the executive exceeds
$10,000.
(b) Section 2(d)(2) of the Federal Funding Accountability and Transparency Act of 2006 (Pub. L. 109-282), as amended by section 6202 of the Government Funding Transparency Act of 2008 (Pub. L. 110-252), requires the
Contractor to report information on subcontract awards. The law requires all reported information be made public, therefore, the Contractor is responsible for notifying its subcontractors that the required information will be made public.
(c)(1) Unless otherwise directed by the contracting officer, by the end of the month following the month of award of a first-tier subcontract with a value of $25,000 or more, (and any modifications to these subcontracts that change previously reported data), the Contractor shall report the following information at http://www.fsrs.gov for each first-tier subcontract. (The Contractor shall follow the instructions at http://www.fsrs.gov to report the data.)
(i) Unique identifier (DUNS Number) for the subcontractor receiving the award and for the subcontractor's parent company, if the subcontractor has a parent company.
(ii) Name of the subcontractor.
(iii) Amount of the subcontract award.
(iv) Date of the subcontract award.
(v) A description of the products or services (including construction) being provided under the subcontract, including the overall purpose and expected outcomes or results of the subcontract.
(vi) Subcontract number (the subcontract number assigned by the Contractor).
http://www.fsrs.gov/ http://frwebgate.access.gpo.gov/cgi-bin/leaving.cgi?from=leavingFR.html&log=linklog&to=http://www.fsrs.gov
(vii) Subcontractor's physical address including street address, city, state, and country. Also include the nine-digit zip code and congressional district.
(viii) Subcontractor's primary performance location including street address, city, state, and country. Also include the nine-digit zip code and congressional district.
(ix) The prime contract number, and order number if applicable.
(x) Awarding agency name and code.
(xi) Funding agency name and code.
(xii) Government contracting office code.
(xiii) Treasury account symbol (TAS) as reported in FPDS.
(xiv) The applicable North American Industry Classification System code (NAICS).
(2) By the end of the month following the month of a contract award, and annually thereafter, the Contractor shall report the names and total compensation of each of the five most highly compensated executives for the Contractor's preceding completed fiscal year in the Central Contractor Registration (CCR) database via https://www.acquisition.gov, if--
(i) In the Contractor's preceding fiscal year, the Contractor received--
(A) 80 percent or more of its annual gross revenues from Federal contracts (and subcontracts), loans, grants (and subgrants) and cooperative agreements; and
(B) $25,000,000 or more in annual gross revenues from Federal contracts (and subcontracts), loans, grants (and
(ii) The public does not have access to information about the compensation of the executives through periodic reports filed under section 13(a) or 15(d) of the Securities Exchange Act of 1934 (15 U.S.C. 78m(a), 78o(d)) or section 6104 of the Internal Revenue Code of 1986. (To determine if the public has access to the compensation information, see the U.S. Security and Exchange Commission total compensation filings at http://www.sec.gov/answers/execomp.htm.)
(3) Unless otherwise directed by the contracting officer, by the end of the month following the month of a first-tier subcontract with a value of $25,000 or more, and annually thereafter, the Contractor shall report the names and total compensation of each of the five most highly compensated executives for each first-tier subcontractor for the subcontractor's preceding completed fiscal year at http://www.fsrs.gov, if--
(i) In the subcontractor's preceding fiscal year, the subcontractor received--
(A) 80 percent or more of its annual gross revenues from Federal contracts (and subcontracts), loans, grants (and
(B) $25,000,000 or more in annual gross revenues from Federal contracts (and subcontracts), loans, grants (and
(ii) The public does not have access to information about the compensation of the executives through periodic reports filed under section 13(a) or 15(d) of the Securities Exchange Act of 1934 (15 U.S.C. 78m(a), 78o(d)) or section 6104 of the Internal Revenue Code of 1986. (To determine if the public has access to the compensation https://www.acquisition.gov/ http://frwebgate.access.gpo.gov/cgi-bin/leaving.cgi?from=leavingFR.html&log=linklog&to=http://www.sec.gov/answers/execomp.htm http://frwebgate.access.gpo.gov/cgi-bin/leaving.cgi?from=leavingFR.html&log=linklog&to=http://www.fsrs.gov information, see the U.S. Security and Exchange Commission total compensation filings at http://www.sec.gov/answers/execomp.htm.)
(d)(1) If the Contractor in the previous tax year had gross income, from all sources, under $300,000, the Contractor is exempt from the requirement to report subcontractor awards.
(2) If a subcontractor in the previous tax year had gross income from all sources under $300,000, the Contractor does not need to report awards to that subcontractor.
(e) Phase-in of reporting of subcontracts of $25,000 or more.
(1) Until September 30, 2010, any newly awarded subcontract must be reported if the prime contract award amount was $20,000,000 or more.
(2) From October 1, 2010, until February 28, 2011, any newly awarded subcontract must be reported if the prime contract award amount was $550,000 or more.
(3) Starting March 1, 2011, any newly awarded subcontract must be reported if the prime contract award amount was
$25,000 or more.
(End of clause)
52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984)
The Contractor shall be required to (a) commence work under this contract within 30 calendar days after the date the
Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 210 Calender Days. The time stated for completion shall include final cleanup of the premises.
52.219-28 POST-AWARD SMALL BUSINESS PROGRAM REREPRESENTATION (APR 2009)
(a) Definitions. As used in this clause--
Long-term contract means a contract of more than five years in duration, including options. However, the term does not include contracts that exceed five years in duration because the period of performance has been extended for a cumulative period not to exceed six months under the clause at 52.217-8, Option to Extend Services, or other appropriate authority.
Small business concern means a concern, including its affiliates, that is independently owned and operated, not dominant in the field of operation in which it is bidding on Government contracts, and qualified as a small business under the criteria in 13 CFR part 121 and the size standard in paragraph (c) of this clause. Such a concern is ``not dominant in its field of operation'' when it does not exercise a controlling or major influence on a national basis in a kind of business activity in which a number of business concerns are primarily engaged. In determining whether http://frwebgate.access.gpo.gov/cgi-bin/leaving.cgi?from=leavingFR.html&log=linklog&to=http://www.sec.gov/answers/execomp.htm dominance exists, consideration shall be given to all appropriate factors, including volume of business, number of employees, financial resources, competitive status or position, ownership or control of materials, processes, patents, license agreements, facilities, sales territory, and nature of business activity.
(b) If the Contractor represented that it was a small business concern prior to award of this contract, the Contractor shall rerepresent its size status according to paragraph (e) of this clause or, if applicable, paragraph (g) of this clause, upon the occurrence of any of the following:
(1) Within 30 days after execution of a novation agreement or within 30 days after modification of the contract to include this clause, if the novation agreement was executed prior to inclusion of this clause in the contract.
(2) Within 30 days after a merger or acquisition that does not require a novation or within 30 days after modification of the contract to include this clause, if the merger or acquisition occurred prior to inclusion of this clause in the contract.
(3) For long-term contracts--
(i) Within 60 to 120 days prior to the end of the fifth year of the contract; and
(ii) Within 60 to 120 days prior to the date specified in the contract for exercising any option thereafter.
(c) The Contractor shall rerepresent its size status in accordance with the size standard in effect at the time of this rerepresentation that corresponds to the North American Industry Classification System (NAICS) code assigned to this contract. The small business size standard corresponding to this NAICS code can be found at http://www.sba.gov/services/contractingopportunities/sizestandardstopics/.
(d) The small business size standard for a Contractor providing a product which it does not manufacture itself, for a contract other than a construction or service contract, is 500 employees.
(e) Except as provided in paragraph (g) of this clause, the Contractor shall make the rerepresentation required by paragraph (b) of this clause by validating or updating all its representations in the Online Representations and
Certifications Application and its data in the Central Contractor Registration, as necessary, to ensure that they reflect the Contractor's current status. The Contractor shall notify the contracting office in writing within the timeframes specified in paragraph (b) of this clause that the data have been validated or updated, and provide the date of the validation or update.
(f) If the Contractor represented that it was other than a small business concern prior to award of this contract, the
Contractor may, but is not required to, take the actions required by paragraphs (e) or (g) of this clause.
(g) If the Contractor does not have representations and certifications in ORCA, or does not have a representation in
ORCA for the NAICS code applicable to this contract, the Contractor is required to complete the following rerepresentation and submit it to the contracting office, along with the contract number and the date on which the rerepresentation was completed:
The Contractor represents that it ( ) is, ( ) is not a small business concern under NAICS Code 238910- assigned to contract number FA4608-12-R-0005.
(Contractor to sign and date and insert authorized signer's name and title).
52.223-11 OZONE-DEPLETING SUBSTANCES (MAY 2001)
(a) Definition. Ozone-depleting substance, as used in this clause, means any substance the Environmental Protection
Agency designates in 40 CFR part 82 as--
(1) Class I, including, but not limited to, chlorofluorocarbons, halons, carbon tetrachloride, and methyl chloroform;
or
(2) Class II, including, but not limited to, hydrochlorofluorocarbons.
(b) The Contractor shall label products which contain or are manufactured with ozone-depleting substances in the manner and to the extent required by 42 U.S.C. 7671j (b), (c), and (d) and 40 CFR Part 82, Subpart E, as follows:
―WARNING: Contains (or manufactured with, if applicable), a substance(s) which harm(s) public health and environment by destroying ozone in the upper atmosphere.‖----------------------------
The Contractor shall insert the name of the substance(s).
52.225-9 BUY AMERICAN ACT—CONSTRUCTION MATERIALS (SEP 2010)
(a) Definitions. As used in this clause--
Commercially available off-the-shelf (COTS) item—
(1) Means any item of supply (including construction material) that is--
(i) A commercial item (as defined in paragraph (1) of the definition at FAR 2.101);
(ii) Sold in substantial quantities in the commercial marketplace; and
(iii) Offered to the Government, under a contract or subcontract at any tier, without modification, in the same form in which it is sold in the commercial marketplace; and
(2) Does not include bulk cargo, as defined in section 3 of the Shipping Act of 1984 (46 U.S.C. App. 1702), such as agricultural products and petroleum products.
Component means an article, material, or supply incorporated directly into a construction material.
Construction material means an article, material, or supply brought to the construction site by the Contractor or a subcontractor for incorporation into the building or work. The term also includes an item brought to the site preassembled from articles, materials, or supplies. However, emergency life safety systems, such as emergency lighting, fire alarm, and audio evacuation systems, that are discrete systems incorporated into a public building or work and that are produced as complete systems, are evaluated as a single and distinct construction material regardless of when or how the individual parts or components of those systems are delivered to the construction site.
Materials purchased directly by the Government are supplies, not construction material.
Cost of components means--
(1) For components purchased by the Contractor, the acquisition cost, including transportation costs to the place of incorporation into the construction material (whether or not such costs are paid to a domestic firm), and any applicable duty (whether or not a duty-free entry certificate is issued); or
(2) For components manufactured by the Contractor, all costs associated with the manufacture of the component, including transportation costs as described in paragraph (1) of this definition, plus allocable overhead costs, but excluding profit. Cost of components does not include any costs associated with the manufacture of the construction material.
Domestic construction material means--
(1) An unmanufactured construction material mined or produced in the United States;
(2) A construction material manufactured in the United States, if--
(i) The cost of its components mined, produced, or manufactured in the United States exceeds 50 percent of the cost of all its components. Components of foreign origin of the same class or kind for which nonavailability determinations have been made are treated as domestic; or
(ii) The construction material is a COTS item.
Foreign construction material means a construction material other than a domestic construction material.
United States means the 50 States, the District of Columbia, and outlying areas.
(b) Domestic preference.
(1) This clause implements the Buy American Act (41 U.S.C. 10a-10d) by providing a preference for domestic construction material. In accordance with 41 U.S.C. 431, the component test of the Buy American Act is waived for construction material that is a COTS item (See FAR 12.505(a)(2)). The Contractor shall use only domestic construction material in performing this contract, except as provided in paragraphs (b)(2) and (b)(3) of this clause.
(2) This requirement does not apply to information technology that is a commercial item or to the construction materials or components listed by the Government as follows: NONE
(3) The Contracting Officer may add other foreign construction material to the list in paragraph (b)(2) of this clause if the Government determines that
(i) The cost of domestic construction…
This is the start of the file's text. The full file is on GovTribe.