Attachment 1 - SOW Install Fencing .docx

DOCX document 327 KB Posted

Attached to
Install Govenment Furnished Fence at BAFB Outdoor Rec
Solicitation number
FA4608-11-Q-C003
Issued by

About this file

Attachment 1 - Statement of Work

View the file

Other files

File Type Posted
Site visit Q A - 9 Nov 2011.docx DOCX document
Attachment 6 - AFI 32-1001.rtf RTF text file
Attachment 5 - Wage Determination.doc DOC document
Attachment 2 - Drawings.pdf PDF
Attachment 4 - BAFBI 33-2.rtf RTF text file
Attachment 3 - Environmental.doc DOC document
Attachment 7 - Insurance.doc DOC document
FA4608-12-Q-C003 GFM Fence installation.pdf PDF
SOW Install Fencing Equipment Rental B4964.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FA4608-12-Q-C003

Attachment 1

Statement of Work for Install 477 LF of 8’ Wooden Fence

AWUB-11-0152

15 Oct 2011

Summary of Work: The contractor shall provide all labor and equipment to construct Government Furnished Materials (GFM) approximately 477 linear feet of 8’ high cedar wood fence and install 2 each , 16 feet double swing gates as indicated on the attached drawing at Barksdale Air Force Base, Louisiana.

1. The contractor will utilize 2-3/8” sch 40 galvanized line posts, 10‘ long and 3” galvanized corner and gate posts. Runners shall be treated with 3 sets runners spanning between posts. All work described herein shall be performed in fullest compliance with Construction Standard policy of Barksdale AFB Design Compatibility Guidelines, Also comply with base standards and all local rules and regulations for the design and other guidance stated in the following Scope of Work. Construction shall be conducted in a quality workmanlike manner. Completed construction shall exhibit a superior quality for completed work. Contractor shall take any steps necessary to protect government and occupant property from damage.

2. Detailed Work Requirements:

(A) General Fencing:

2.1.1 Footings: all line footings will be 12” diameter, 3’ deep and utilize (GFM) 3000 psi concrete.

2.1.2 Excavations for all footings may be done by augering, taking care to avoid existing utilities

2.2 Wood Fencing: (GFM)

2.2.1 Vertical member: The standard wood fence picket will be 1” x 6” x 8’ feet high They shall be fastened on to horizontal wood members bolted on to galvanized posts.

2.2.2 Horizontal wood members: The horizontal members shall be bolted on to galvanized post utilizing the wood post clamp shown below, or an approved equal. The bottom horizontal member shall be 6 inches above finished grade elevation. The top horizontal member shall be bolted 6 inches below galvanized post’s cap. The middle horizontal members shall be bolted center between the two. A total of 3 each horizontal wood members will receive the vertical pickets.

3.3.3Fence Height: The height of the wood fence shall be 8 FT.
3.3.4Ground Clearance: The bottom of the fence shall be within two inches of the firm soil to allow for grass maintenance without damaging the fence boards.
3.3.5Fence Posts (Line) (GFM): All posts shall be sch 40, shall be galvanized, shall be capped, and spaced at 8 ft on center.
3.3.6Fence Posts and Foundations: Fence post size is as described in dimension, but not less than depth (2’-6”) and with diameter of footing not less than 12”. Allow fence post foundation (minimum of 3 days) to cure prior to applying loads. Posts shall be set plumb and alignment.
3.3.7Swing Gate and Posts (GFM): A 16’ wide gate shall be provided, with two(2) 8’ Gate leaves with a truss or intermediate braces to alleviate sagging. Latches hinges, stops, keepers, and other hardware items shall be furnished as required for the operation of the gate. Latches shall be arranged for padlocking so that the padlock will be accessible from both sides of the gate. Stops shall be provided for holding gate in the open position by use of drop bars. Gate posts shall conform to ASTM A53 or ASTM A500 for Hollow Structural Sections (HSS) and shall be galvanized and 3” in dia.
3.3.8Gate Post and Foundations (GFM): Gate post size shall be 3” galvanized posts with a minimum of 3’ in the ground, footings shall not be less than 12” dia. Corner post holes to be a little larger. 3000 PSI concrete shall be used. Allow concrete a minimum of 3 days to cure prior to applying loads. Posts shall be set plumb.

Point of Contact

a) Point of Contact for this project is Mr. Del Valencia, CEPM at 456-3060

3. Period of Performance:

Government shall issue a single Notice to Proceed (NTP) and the Contractor will have 45 days to complete all work described within.

Submittals Period:5 Calendar Days
Construction period:45 Calendar Days

Total Task Order Period: NTP + 45 Calendar Days image1.png