B457 Boiler 1 Repair - Questions and Answers.docx
DOCX document 14 KB Posted
- Attached to
- Offutt AFB Boiler Repair
- Solicitation number
- FA460025Q0003
About this file
This document contains questions and answers related to the federal contract opportunity for the repair of Boiler 1 at Offutt Air Force Base. The key details are:
Facility access and logistics: Parking is allowed next to the boiler room or in the west side parking lot. Materials and tools can be left overnight in the mechanical room, but security cannot be guaranteed. Hot work requires a permit from the fire department. There are no anticipated confined space conditions.
Boiler requirements: The contractor must plan for a separate mobilization to make the portable boiler connection modifications, as the boiler systems cannot be shut off during winter operations when the boiler re-tube would occur. The 30-day delivery or performance period may be extended to allow for the installation of these connection locations.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| PWS B457 Boiler 1 repair rev 2.docx | DOCX document | |
| COMBO - CES Boiler Repair - Amendment 0001.pdf | ||
| Seminole 6-5-500.pdf | ||
| COMBO - CES Boiler Repair.pdf | ||
| PWS B457 Boiler 1 repair.pdf | ||
| original boiler record.pdf | ||
| SCA - Wage Determination.pdf | ||
| NCIC Screening and Pass Request.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
B457 Boiler 1 Q&A
General Building Access & Logistics
0. What is the plan for building access? Parking Parking is allowed next to the Boiler Rm by the cooling tower, within reason, or at the edges of the west side parking lot.
0. Material/Tool Storage Materials and tools can be left overnight in the Mechanical Rm in a tidy fashion, although it must be noted that other CES, Facility, and Contractor personnel have access to this space for various reasons and CES cannot guarantee security.
0.
0. Please advise if the contractor will be allowed to leave equipment/materials tidily in the space overnight for resumption of activities the following day. Yes
0. Please provide facility requirements related to confined space working conditions. There are no anticipated confined space conditions related to this project. Contractors who do work in confined spaces on Base are required to operate by their own Confined-Space program.
0. Please provide facility requirements related to hot work & fire watch procedures. All hot work (cutting, grinding, welding, ect) must get a hot work permit from the Fire Department – this involves simply going to the Fire Department, meeting an Inspector, describing the work and methods, and they will issue a permit.
Boiler Requirements
1. Please clarify the desired portable boiler connection sizes desired to be left. See revised PWS
1. Please clarify if we are to plan for a separate mobilization to make the portable boiler connection modifications, as we are of the understanding that the boiler systems can not be shut off during winter operations, when boiler re-tube would occur. If so, the Combined Synopsis/Solicitation document states that the delivery or performance period from date of lead time event to completion of performance is 30-days. Will this be extended to allow for the installation of these connection locations? See revised PWS