Additional Questions and Answers.pdf

PDF 49 KB Posted

Attached to
10, 000 Gallon Storage Tank
Solicitation number
FA460024Q0095
Issued by

About this file

This document contains Additional Questions and Answers related to a federal contract opportunity for a 10,000 Gallon Storage Tank. The key details are:

The contract requires a transfer point with a 3-inch camlock connection to be provided. Piping is not specifically required, but if provided it can be either stainless steel or fiberglass. The transfer point should be located at the front of the tank. No dispenser is required, only the transfer point connection. The agency issuing the contract is the Department of the Air Force Air Combat Command.

View the file

Other files

File Type Posted
Questions and answers.pdf PDF
2024_Statement of Need_ Storage Tanker10000 gal_1.docx DOCX document
10K Tank solication combo.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

1. Is there any piping involved?

-A transfer point with a 3” camlock connection will need to be provided

2. Is there any piping to the unit where you will pump from?

- A transfer point with a 3” camlock connection will need to be provided

3. Is there a dispenser used to fill the trucks?

– A transfer point with a 3” camlock connection is all that is required, this will be used to connect to our own transfer pump

4. Is the piping stainless steel or fiber glass?

– This is not identified in the SON so it will not be an evaluation factor so either will be fine

5. If piping is involved, how far do I have to pipe it or long is it going from tank to the dispenser (pumping unit)

– It is preferred to have a transfer point with 3” camlock connection located at the front of the tank

File details come from the government source that posted it. Updated .