This document is a Statement of Work (SOW) for a federal contract opportunity to replace the existing child playground enclosure at the Offutt Field House on Offutt Air Force Base in Nebraska. The project involves removing the current plexiglass fencing and gates and replacing it with approximately 43 linear feet of new acrylic panels with aluminum framework, protective foam padding, and two 48-inch access gates with powder-coated steel framing, magnetic safety latches, and protective foam padding. The contractor will be responsible for providing all labor, equipment, materials, and services required to complete the work in a neat, substantial, and competent manner, with all construction debris removed and the area left clean and orderly. The SOW specifies the required enclosure dimensions, materials, and safety features. The related federal contract opportunity, Solicitation Number FA460024Q0026, is for the Field House Child Play Area Fence Upgrade project.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Statement of Work For

Child Playground Enclosure

55 FSS

Offutt Field House Offutt AFB, NE

Objectives: The current CPA (Child Play Area/playground) requires a reenforced fence/gate to hold children within the playground area and withstand daily wear and tear from child customer usage. The enclosure is degrading causing too much bend in the plexi-glass and lose of proper gate closure. Upgraded acrylic panels, protective foam padding around the frames to support customer’s requirements. Removal of existing playground enclosure (plexiglass fencing and two gates) and replace with upgraded acrylic panels, padding and two gates with latching system.

Description of services:

The project involves replacing the existing enclosure and gates within the Offutt Field House, Offutt Air Force Base, NE, with a new child-safe enclosure, including removal and disposal of the current installation.

The contractor shall furnish all labor, equipment, materials, services, and incidentals. No alterations, additions, or deletions shall be made unless by prior approval of the Project Manager and the government Procuring Contracting Officer (PCO). Work shall be completed in a neat, substantial, and competent manner.

All lifts provided by contractor, must be OSHA-approved, two-man scissor lifts, unless otherwise specified.

Ensure all installed components meet federal regulations for safety standards. All construction debris will be removed by contractor and area left in a clean and orderly condition.

Enclosure must meet or exceed the following specifications.

1. Approximately 43 linear feet of Acrylic Panels with aluminum framework

a. Aluminum framework will be lined with child safe foam padding glued in place

b. Panels must be secured with aluminum posts

c. Panel height 57 inches with protective foam padding around frame

d. Child safe infill designed for use in play areas

e. Panels must be clear/see through

2. Two access 48” gates

a. Gates must be secured with powder coated steel framing

b. Gate height 57 inches with protective foam padding around frame

c. Heavy-duty top-pull magnetic safety latch or self-adjusting gravity latch on the outside of gate

LEAHY, MARK J CIV USAF ACC 55 CONS/PKP

Specify if you want any type of locking mechanism or how you want them to open and close (spring closing?, childproof lock?, etc)

Drawings/Photos:

Magnetic safety gate latch

Self-adjusting gravity latch