Statement of Work VICADS Phase II.pdf
PDF 290 KB Posted
- Solicitation number
- FA452827NCS01
About this file
This is a Statement of Work (SOW) for remote perimeter camera upgrade services at Minot Air Force Base in North Dakota, issued by the 5th Security Forces Squadron Technology and Innovation Section (Version 2.2, dated 11 August 2026). The project, titled "Project Vigilance Phase II," is a Contractor Furnish/Contractor Install (CFCI) effort requiring the contractor to provide all labor, materials, equipment, transportation, tools, supplies, and network accessories to install a video management system and cameras at multiple base locations.
The scope includes installing cameras at five primary locations: Building 547/5 SFS Confinement (13 cameras including anti-ligature and anti-vandal models), Building 197/Magic City Gate, Building 1014/Minot Gate, Building 1034/Air Traffic Control Tower (replacement with Bosch MIC IP 9000I or better), and Building 837/Hangar 5. The system must support real-time monitoring at Buildings 547, 475, and 768, with 90-day video retention capability and 30+ days for the confinement facility. The contractor must use only Air Force Approved Products List (APL) compliant equipment and comply with the Configuration Management Database (CMD). All connectivity must utilize dark fiber (non-AFNet/non-NIPR) infrastructure, with the contractor providing required network switches, fiber connectors (LC-LC, SC-LC, ST-LC), 10G SFPs, and RJ-45 cables. Equipment specifications include high-resolution 1080P cameras with pan-tilt-zoom capability, 2.5 candlepower low-light functionality, object/vehicle/person detection analytics, solar power with 1200WH lithium battery backup (minimum 18-hour capacity), operation in -30 to +120 degree temperatures, IP 55/IP 65 weatherproofing, and perpetual licensing with no recurring fees. The Period of Performance is 180 calendar days from contract award to achieve full system operationality. The contractor must provide a one-year workmanship warranty, all manufacturer warranties, and five years of sustainment including semi-annual on-site maintenance and 24/7 technical support. The contractor must be a U.S. company employing U.S. citizens, designate a Project Manager as key personnel, complete Level 1 Antiterrorism Awareness training within 30 days, comply with all base security protocols including NCIC and III background checks, and work during standard business hours (8:00 AM–5:00 PM CST, Monday–Friday, excluding federal holidays and base closures). The government will provide power and dark fiber connectivity to specified locations; the contractor is responsible for verifying site conditions, purchasing materials, coordinating with the Post Award Conference within 10 business days of award, and providing a detailed project plan within five business days after that conference. All documents and information must be marked as Controlled Unclassified Information (CUI) or Controlled Unclassified Nuclear Information (DCNI) and comply with security requirements prohibiting disclosure of sensitive military operations or personnel information.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK (SOW) FOR
5 SFS Remote Perimeter Camera(s) Upgrade Services (5 MSG)
“Project Vigilance Phase II”
MINOT AIR FORCE BASE
NORTH DAKOTA
Prepared by:
5th Security Forces Squadron Technology and Innovation Section
Minot Air Force Base, North Dakota
Version 2.2
Date: 11 Aug 2026
Table of Contents
1. OVERVIEW
2. LOCATION
3. BACKGROUND
4. GENERAL REQUIREMENTS
5. SCOPE
6. PERIOD OF PERFORMANCE (PoP)
7. OPERATING CONSTRAINTS
8. WARRANTY
9. OTHER APPLICABLE CONDITIONS
ATTACHMENT 1
STATEMENT OF WORK (SOW)/ SCOPE OF WORK /
GENERAL REQUIREMENTS
1. OVERVIEW/DESCRIPITION OF SERVICES.
The contractor shall provide all management, tools, supplies, equipment, and labor necessary to perform video management system and camera install services at Minot Air Force Base (AFB), The government will provide power and dark fiber (non-NIPR/non-AFnet) communications to the locations outlined in this SOW. Contractor shall install cameras and video management services in Minot AFB North Dakota, in accordance with all applicable federal, state, local laws and regulations and this statement of work (SOW) only covers and explains Phase II of a multi-phase project.
2. LOCATION.
2.1. Within Minot AFB to provide video surveillance capabilities at: Bldg. 547/5 SFS Confinement, Bldg. 197/Magic City Gate, Bldg. 1014/Minot Gate. Replace existing exterior IP Pan, Tilt, Zoom (PTZ) camera with Bosh MIC IP 9000I, like, or better camera in accordance with the Air Force published Configuration Management Database (CMD) at Bldg. 1034/Air Traffic Control (ATC) Tower. Install removed IP PTZ from Bldg.
1034/ATC Tower on Bldg. 837/Hangar 5.
2.1.1. Monitored viewing capability of locations must occur at Building 547/Central Security Control, Building 547/Confinement, Bldg. 768/Maintenance Operations Center, and recording capability must occur at Bldg. 547/Central Security Control using previously Phase I installed V100 Server. Recording capability of 30 days or more must occur at Bldg. 547/Confinement in accordance with higher headquarters guidance.
2.1.2. Effective communication and sufficient connectivity are required for all locations.
For real time or near-real time visual observations. Contractor shall use dark fiber (non-NIPR/non-AFnet) infrastructure at all locations and provide all required network Air Force Approved Products List (APL) compliant switches, LC-LC, SC- LC, ST-LC, 10G SFPs and RJ-45 cables to directly connect the system to cameras via Fiber cable and any miscellaneous connectors required for installation not previously referenced by this SOW.
2.2. Place of performance may include other locations to ensure system connectivity and functionality.
2.2.1. Contractor shall remove installed CCTV Network Switch from communications room in Bldg. 1142 and reinstall CCTV Network Switch outside of the communications room via a contractor furnished wall mount switch cabinet with capability to be locked via key or combination.
2.2.1.1. 5 CS shall run dark fiber from network switch in Bldg. 1142 to an communications room exterior demarcation point ensuring fiber connectivity from Bldg. 1142 communications room to exterior CCTV
Network switch enclosure. 5 CS shall enclose fiber in hardened conduit from communications room to exterior CCTV Network switch to maintain physical and cyber security requirements of the closed network.
2.2.2. Contractor shall remove installed CCTV Network Switch from communications room in Bldg. 1034 and reinstall CCTV Network Switch outside of the communications room via a contractor provided wall mount switch cabinet with capability to be locked via key or combination.
2.2.2.1. 5 CS shall run dark fiber from network switch in Bldg. 1034 to an communications room exterior demarcation point ensuring fiber connectivity from Bldg. 1034 communications room to exterior CCTV Network switch enclosure. 5 CS shall enclose fiber in hardened conduit from communications room to exterior CCTV Network switch to maintain physical and cyber security requirements of the closed network.
2.2.3. Contractor shall remove installed CCTV Network Switch from communications room in Bldg. 718 and reinstall CCTV Network Switch outside of the communications room via a contractor provided wall mount switch cabinet with capability to be locked via key or combination.
2.2.3.1. 5 CS shall run dark fiber from network switch in Bldg. 718 to an communications room exterior demarcation point ensuring fiber connectivity from Bldg. 718 communications room to exterior CCTV Network switch enclosure. 5 CS shall enclose fiber in hardened conduit from communications room to exterior CCTV Network switch to maintain physical and cyber security requirements of the closed network.
2.2.4. Contractor shall remove installed CCTV Network Switch from communications room in Bldg. 475 and reinstall CCTV Network Switch outside of the communications room via a contractor provided wall mount switch cabinet with capability to be locked via key or combination.
2.2.4.1. 5 CS shall run dark fiber from network switch in Bldg. 475 to an communications room exterior demarcation point ensuring fiber connectivity from Bldg. 475 communications room to exterior CCTV Network switch enclosure. 5 CS shall enclose fiber in hardened conduit from communications room to exterior CCTV Network switch to maintain physical and cyber security requirements of the closed network.
2.2.5. Contractor shall remove installed CCTV Network Switch from communications room in Bldg. 546 and reinstall CCTV Network Switch outside of the comm room via a contractor provided wall mount switch cabinet with capability to be locked via key or combination.
2.2.5.1. 5 CS will run dark fiber from network switch in Bldg. 546 to an communications room exterior demarcation point ensuring fiber connectivity from Bldg. 546 communications room to exterior CCTV Network switch enclosure. 5 CS shall enclose fiber in hardened conduit from communications room to exterior CCTV Network switch to maintain physical and cyber security requirements of the closed network.
2.2.6. Contractor shall install CCTV Network Switch outside of the communication room of Bldg. 768 via a contractor provided wall mount switch cabinet with capability to be locked via key or combination.
2.2.6.1. 5 CS shall run dark fiber from network switch in Bldg. 798 to an communications room exterior demarcation point ensuring fiber connectivity from Bldg. 798 communications room to exterior CCTV Network switch enclosure. 5 CS shall enclose fiber in hardened conduit from communications room to exterior CCTV Network switch to maintain physical and cyber security requirements of the closed network.
2.2.7. Contractor shall install CCTV Network Switch outside of the communication room of Bldg. 837 via a contractor provided wall mount switch cabinet with capability to be locked via key or combination.
2.2.7.1. 5 CS will run dark fiber from network switch in Bldg. 837 to an communications room exterior demarcation point ensuring fiber connectivity from Bldg. 837 communications room to exterior CCTV Network switch enclosure. 5 CS must enclose fiber in hardened conduit from communications room to exterior CCTV Network switch to maintain physical and cyber security requirements of the closed network.
2.3. Pictures of Minot AFB perimeter can be viewed from commercial search via open internet;
however, specified perimeter drawings/pictures are “Controlled Unclassified Information (CUI) or Controlled Unclassified Nuclear Information (DCNI)” and is not releasable for public use but can be provided during any site visits.
3. BACKGROUND:
3.1. This SOW outlines requirements necessary to support Contractor furnished/Contractor installed (CFCI) camera(s) to provide monitored viewing capability as a security enhancement of key installation perimeter locations for Minot AFB and the 5 SFS Confinement Facility.
3.2. The person(s) or entity performing the CFCI work outlined in this SOW is referred to as “Contractor” hereafter.
3.3. The 5th Security Forces Squadron (5 SFS) is the responsible “end-user.” Security Forces Operations (5 SFS/S3) is the office of primary responsibility (OPR) and is identified as the “customer” hereafter, whereas the 5th Security Forces Squadron, Technology and Innovation (5 SFS/S6) is the project facilitator for the customer’s needs/intent between the Government, Project Manager(s), and/or Contractor(s).
3.4. Compliance Documents. The following documents provide specifications, standards, or guidance that must be complied with to meet the requirements of this work.
3.4.1. Configuration Management Database (CMD) equipment approval list, when applicable (list may be sourced from 5 SFS/S6, Technology and Innovation (S6) office – Bldg. 437, Room 152, or via office phone at 701-723-4735).
4. GENERAL REQUIREMENTS.
4.1. This work is a Contractor Furnish/Contractor Install (CFCI).
4.2. The Contractor must coordinate with the Government before purchasing camera system(s) or validate/verify with customer to use any existing government camera equipment.
4.3. The Contractor must use only approved cameras/system(s) listed on the current configuration management database (CMD) issued by AF/HBUC.
4.4. The Contractor shall install all materials in strict accordance with the manufacturer’s printed instructions and details: rigid, secure, plumb, level, aligned, square and straight with suitable fastening devices.
4.5. Dispose of all waste generated by this work according to all applicable regulations.
4.6. The Contractor is responsible to verify site conditions, measurements, quantities, and materials needed to complete this work prior to submitting a proposal, ordering materials, and starting work activities. All materials including those concealed or covered must be new and of the most suitable and highest grade and type for the intended use unless otherwise indicated.
4.7. The term “provides” means provide (or furnish) and install.
4.8. The term “replace” means remove existing material or items and furnish and install a similar new material as required to match existing adjacent material or items.
4.9. Products must comply with the Buy American Act for Supplies IAW FAR 52.225-1.
4.10. Contractor must provide a detailed list of the equipment to be installed, as well as subsequent data sheets and documentation to further explain the capabilities of the equipment.
4.11. All licensing associated with the system/equipment must be perpetual; no licensing fees or reoccurring costs shall be part of the system/equipment.
4.12. Contractor must ensure work area is to be cleaned of debris daily. Work areas must be cleaned prior to departure for the workday and to limit hazards of neighboring work, common areas, and/or walkways. Protect the existing facility, sidewalks, and landscaping from damage due to equipment or personnel. Promptly remedy all damage or loss thereto.
4.13. Hours of Operation. The contractor must perform the work required under this contract during the normal operating hours of 8:00 AM to 5:00 PM Central Standard Time (CST), Monday through Friday, excluding base closures/down days and Federal Holidays.
Contractor may start the day of or the day after award of the contract. Coordinate with the Government Project Manager or the Contracting Office if additional or off-hours are required to accomplish work.
4.13.1. Recognized Holidays. The contractor is not required to provide service on the following days, unless otherwise noted:
• New Year’s Day (January 1).
• Birthday of Martin Luther King, Jr. (Third Monday in January).
• Washington’s Birthday (Third Monday in February).
• Memorial Day (Last Monday in May).
• Juneteenth National Independence Day (June 19).
• Independence Day (July 4).
• Labor Day (First Monday in September).
• Columbus Day (Second Monday in October).
• Veterans’ Day (November 11).
• Thanksgiving Day (Fourth Thursday in November).
• Christmas Day (December 25).
4.14. Licenses and Permits. Follow local, State, and Federal rules and regulations relating to licenses and permits required throughout the entirety of the project, as applicable.
4.15. Facilities will be occupied throughout the duration of the project. Coordination and/or notification with the Facility Manager and/or Government Project Manager at the beginning/ending of each workday for access to work areas.
4.16. The Government must evaluate the contractor’s performance by monitoring it to ensure the work is completed efficiently. The Government shall evaluate the contractor’s performance through on-site inspections and receipt of customer complaints. The Government shall inspect each task as completed.
4.17. Contractor personnel shall not discuss government operations in public or over unprotected or unencrypted communications. Controlled unclassified information (CUI) and Controlled Unclassified Nuclear Information (DCNI) may only be transmitted as directed in this SOW.
4.18. The Contractor shall not post to company websites, publications, newsletters, or other media any images, data or information that reveal sensitive government operations, personnel, equipment, and/or classified or controlled unclassified information. When in doubt, company press releases related to this contract should be coordinated through the Contracting Officer.
4.19. Because observation of events, operations, physical changes, etc. may reveal National Security information, specific restrictions are needed to preclude unintentional release of this information to unauthorized parties. Unauthorized disclosure and transfer of National Security Information is punishable under 10 USC § 793. Therefore, contractor personnel must not disclose to unauthorized third parties, post to unofficial sites (including Social Networking sites) any images, data/information, or observed events that reveal sensitive government operations, personnel, equipment, including, but not limited to:
4.19.1. Tactics, techniques and procedures, production, or work schedules, any visible or concealed modifications, upgrades, additions to vessels, aircraft, or weapons or equipment; increases, change, or decreases in work/deployment frequency or government personnel, vehicle, vessel, or aircraft movements; specialized equipment orders, deliveries, shipments, etc. Unauthorized disclosures and attempts to solicit this type of information by unauthorized third parties or others not affiliated with this contract must be reported to the Contracting Officer.
4.20. Government issued badges, identification must be removed and/or concealed from plain sight when off base and must not be left in vehicles or unprotected areas. Badges and passes may not be duplicated, copied, or loaned to others. Lost or stolen identification badges, vehicle passes, etc. will be immediately reported to the Contracting Officer and/or Installation Security Office (i.e., Visitor Control Center).
4.21. Contractor(s) must be required to produce information and documents needed to gain access to Minot AFB. A valid driver’s license, state issued identification card or U.S.
passport, identifying person’s photo and applicable information of which, the documents cannot be expired, and a current unexpired automobile insurance document and vehicle registration will be needed. The Project Manager will provide above information as well as employes Social Security Numbers (SSN) to the Contracting Officer and/or The Technology and Innovation Section (S6) at minimum fifteen (15) days prior to work start date.
4.22. Antiterrorism:
4.22.1. Notification. If the Contractor (contract employees/subcontractors) identify any suspicious activity, they must contact the Law Enforcement Desk (LED) at +1(701)-723-3096 or Central Security Control (CSC) at +1(701)-723-3011 and notify the CO and COR (if appointed) that they contacted the Law Enforcement Desk and/or Central Security Control.
4.22.2. Training. Contractor employees that require routine physical access to a Federally controlled facility or military installation must complete Level 1 Antiterrorism Awareness training within 30 days of requiring access and annually thereafter and send a copy of their employees’ training certificate(s) to the CO and COR (if assigned). Training is located at Joint Knowledge Online (JKO) website: https://jkodirect.jten.mil/Atlas2/page/login/Login.jsf.
4.23. Records Management:
4.23.1. All records, files, documents, regardless of media (e.g. paper, electronic, etc.), as described in the Statement of Work, that are the responsibility of the contractor are the property of the Government and must remain so upon termination or completion of the contract. The contractor must keep these items current and maintain and dispose of them in accordance with the requirements established in Air Force Instruction (AFI) 33-322, Records https://jkodirect.jten.mil/Atlas2/page/login/Login.jsf
Management Program and the Air Force Records Disposition Schedule which can be provided by the Chief of Records upon request. Records must be turned over to the Government upon completion of the contract unless otherwise stated. All records are subject to the Freedom of Information and Privacy Act.
The Minot AFB Records Management Office (5 BW/IPR), 723-7917, will provide assistance and training to the contractor to ensure compliance with Federal record keeping requirements.
5. SCOPE.
5.1. The Contractor shall furnish all labor, materials, equipment, transportation, tools, supplies, Air Force APL compliant network switches, network accessories, locking wall mount switch cabinets etc. and all other direct/indirect costs to complete the work.
5.2. Camera(s) shall be installed at the location(s) identified within this SOW. Monitoring and enunciation of Phase I and II installed cameras must occur to be viewed and actioned at Bldg. 547/CSC, monitoring of Phase I and II installed cameras must occur in Bldg.
475/CAT. Monitoring and enunciation for Bldg. 547/Confinement must occur to be viewed at Bldg. 547/Confinement Office. Monitoring of previously installed Phase I cameras and Hangar 5 camera must occur at Bldg. 768/MOC.
5.2.1. Cameras will be installed at the following locations:
• On the top of Bldg. 1034/Air Traffic Control (ATC) Tower directly above the controller viewing area. Replace existing exterior IP Pan/Tilt/Zoom (PTZ) camera with Bosh MIC IP 9000I, like or better camera in accordance with the CMD.
Camera shall be installed facing North. Install removed IP PTZ from Bldg.
1034/ATC Tower on front Southwest corner of Bldg. 837/Hangar 5 facing South.
• Install cameras on the inbound and outbound lanes, and sentry credential check area of Bldg. Bldg. 197/Magic City Gate. Cameras must have “wrong way” detection capabilities that enunciate to the posted sentry and at Bldg. 547/CSC.
• Install cameras on the inbound and outbound lanes, and sentry credential check area of Bldg. 1014/Minot Gate. Cameras must have “wrong way” detection capabilities that enunciate to the posted sentry and at Bldg. 547/CSC.
• Install thirteen (13) cameras in Bldg. 547/Confinement to replace existing analog system. Installation shall consist of eight (08) corner mount, anti-ligature cameras, two (02) indoor/outdoor vandal dome cameras, three (03) IR Vandal resistant dome cameras with varifocal lens. Cameras shall be CMD and DAFMAN 31- 115V1, Department of the Air Force Corrections System compliant (i.e. anti-tamper/anti-vandal proofed). Camera feeds shall only be displayed in Bldg.
547/Confinement Office.
• Install removed IP PTZ camera from Bldg. 1034/ATC Tower on top of the front Southwest corner of Bldg. 837/Hangar 5.
5.3. Contractors must provide a work plan/schedule as part of their proposal incorporating all equipment, tools, materials, supplies, transportation, labor, supervision, management, and other incidentals necessary to meet the requirements as stated in this SOW.
5.4. Installation and Configuration.
5.4.1. Install video management system and cameras according to current Authority to Operate (ATO) and to manufacturer’s specifications.
5.4.2. Contractor must comply with all current, applicable TIA telecommunication installation and testing commercial standards. All equipment must meet all applicable TAA/BAA/NDAA requirements.
5.4.3. Contractor must comply with all facility modification requirements for mounting and installment of hardware.
5.4.4. Any applicable software application needed to operate/function camera(s) will be a direct point-to-point connection and will not be connected to the Air Force Network (AFNet)/NIPR. Contractor shall utilize dark fiber relay points to connect from camera endpoint to monitoring location(s) (i.e., Bldg. 547, Bldg. 475, Bldg. 768).
5.4.5. Contractor must provide an itemized list of equipment to be installed per building as well as subsequent data sheets and documentation to further explain the capabilities of the equipment.
5.4.6. Camera(s) must be compatible with the Video Management Systems identified on the most current CMD.
5.5. Specification(s).
5.5.1. Equipment specifications will be equal to or better as identified in Table 1.1. to Attachment 1 of this SOW.
5.5.2. System must enable the ability to detect and identify unauthorized access on or through the base boundary line of Minot AFB. This includes the following:
5.5.2.1. Detecting personnel and/or vehicles approaching the installation perimeter; identifying the location of unauthorized access along the perimeter; and communication with the camera system to identify an attempted or completed breach/trespassing (i.e., crossing the base boundary to enter and/or exit the base from the wrong direction). The system should include the ability to pull incidents for analysis and reporting per customer request.
5.6. Training and Materials.
5.6.1. Contractor and Customer must coordinate a date/time where the Contractor can provide initial training on how to use, operate, function test, and troubleshoot common errors regarding the installed equipment. In the case where the Contractor and Customer cannot agree to a specified initial training date/time, the Contracting Officer will arbitrate a date/time. Initial training will be accomplished prior to
Government acceptance of installed equipment but, equipment must be fully operational/functional.
5.6.2. Contractor must provide three (3) copies of manufacturer’s instructions, technical orders, and equipment manuals, as applicable. Copies can be provided in either hard-copy and/or digital mediums.
6. PERIOD OF PERFORMANCE (PoP).
6.1. To include lead time and training, PoP for a fully functional/operational system must be at 180 calendar days after contract award.
7. OPERATING CONSTRAINTS.
7.1. Qualified Personnel. The Contractor must provide qualified personnel to perform all requirements specified in this SOW. The Contractor will only be awarded to a United States (U.S.) company employing U.S. citizens.
7.2. Key Personnel. Before replacing any individual designated as Key by the Government, the Contractor must notify the Contracting Office no less than fifteen (15) business days in advance, submit written justification for replacement, and provide the full name and qualifications of any proposed substitute(s). All proposed substitute(s) must possess qualifications equal to or superior to those of the Key personnel being replaced, unless otherwise approved by the Contracting Office. The Contractor must not replace Key Contractor personnel without approval from the Contracting Officer. The following Contractor personnel are designated as “Key” for this requirement.
7.2.1. Project Manager (PM). The Contractor will provide a PM who must be responsible for all Contractor work performed under this SOW. The PM must be a single point of contact (POC) for the Contracting Officer and any assigned Contracting Officer Representative (COR). The name of the PM, and the name(s) of any alternate(s) who must act for the Contractor is the absence of the PM, must be provided to the Government as part of the Contractor’s proposal. The PM is further designated as Key by the Government. During any absence of the PM, only one alternate must have full authority to act for the Contractor on all matters relating to work performed under this contract. The PM and all designated alternates must be able to read, write, speak, and understand the English language. Additionally, the Contractor must not replace the PM without prior coordination with the Contracting Office.
7.2.1.1. The PM must be available to the COR via telephone between the hours of 8:00 a.m. and 5:00 p.m. Central Standard Time (CST), Monday through Friday and must respond to a request for discussion or resolution of technical problems within three (3) hours of notification.
7.2.2. Employee Identification.
7.2.2.1. Contractor’s employees must comply with all applicable local, state, and federal laws, ordinance, regulations, policies, and procedures (e.g., fire, safety, sanitation, environmental protection, security, “off-limits” areas, possession of weapons/drugs (to include Marijuana and/or similar products), et al.) when visiting or working at Department of War (DoW) Government facilities and/or installations. The Contractor must ensure contractor employees always present a professional appearance, and their conduct must not reflect discredit on the U.S. or the DoW. The PM must ensure contractor employees understand and abide by the DoW and Minot AFB established rules, regulations and policies concerning safety and security.
7.2.3. Removing Employees for Misconduct or Security Reasons.
7.2.3.1. The Government may, at its sole discretion (via the Contracting Office or by 5 SFS, when relating to Law and Order and/or Security concerns), direct the Contractor to remove any contractor employees from Minot AFB facilities and/or installation for misconduct or security reasons. Removal does not relieve the Contractor of the responsibility to continue providing the services required under this SOW.
8. WARRANTY.
8.1. The Contractor must provide a one (1)-year workmanship warranty and all manufacturer’s equipment warranties, with optional additional years of warranty service, which begins from government acceptance date.
8.2. The Contractor must warrant the entire product and workmanship. Faulty or defective work or product must be corrected at no cost to the Government. The Contractor must provide a warranty POC in their proposal.
8.3. The warranty service must include on-site repair, all parts, labor, and replacement, as necessary, and other costs associated with on-site repair within a 72-hour response time.
8.4. Contractor shall provide 5-years of sustainment and maintenance that includes but is not limited to semi-annual contractor on-site maintenance/sustainment, and 24/7/365 telephonic access to a technician to assist the owner/user with system troubleshooting and maintenance.
9. OTHER APPLICABLE CONDITIONS.
9.1. Security.
9.1.1. All contractor personnel will have a National Crime Information Center (NCIC) and Interstate Identification Index (III) Check conducted, of which, person(s) with negative criteria as outline in the 5th Bomb Wing (5 BW) Base Defense and Antiterrorism Plan (DD/ATP), 5 BW Plan 31-1, must not have access to Minot AFB property. The Contractor PM will be able to coordinate with 5 SFS/S6, Technology and Innovation, regarding installation access and issuance of Defense Biometric Identification System (DBIDS) passes for contractors. The Contractor PM will provide applicable information a minimum of fifteen (15) calendar days to 5 SFS/S6 prior to requiring installation access, to have proper vetting completed.
9.1.2. The following behavior or criminal record(s) pose unacceptable risk and are denied initial installation access IAW DoDM5200.08V3_DAFMAN 31-101V3, Installation Perimeter Access Control:
9.1.2.1. The individual is known to be or reasonably suspected of being a terrorist or belongs to an organization with known terrorism links/support.
9.1.2.2. The installation is unable to verify the individual’s claimed identity.
9.1.2.3. The individual has previously been barred from access to a federal installation or stand-alone facility.
9.1.2.4. Federal, State, Local, or other civil law enforcement authorities, regardless of offense or violation, want the individual.
9.1.2.5. The individual has any conviction for espionage, sabotage, treason, terrorism, or murder.
9.1.2.6. The individual’s name appears on any Federal or State agency’s watch list or hit list for criminal behavior or terrorist activity (e.g., National Sex Offender Registry (NSOR), Violent Persons File (VPF), etc.).
9.1.2.7. The individual has been convicted of a firearms or explosive violation.
9.1.2.8. The individual has been convicted of sexual assault, armed robbery, rape, child molestation, child pornography, trafficking in humans, drug possession with intent to sell, or drug possession with intent to sell, or drug distribution.
9.1.2.9. The individual has knowingly and willfully engaged in acts or activities designated to overthrow the U.S. Government by force.
9.1.3. Privately Owned Firearms are not authorized on Minot AFB with respect to contractor personnel, in the performance of this SOW.
9.1.4. Oversized commercial company vehicles will be required to be searched prior to base entry. All vehicles are subject to inspections while entering, exiting, and operating within the confines of Minot AFB boundaries. Failure to comply will result in contractor personnel barment.
9.1.5. Contractor personnel may be required to halt performance during periods of high alert, Force Protection Condition (FPCON) changes, base-level exercises, and/or natural or man-made emergencies. The Contractor PM will be notified by the Government when work can be resumed.
9.2. Safety.
9.2.1. The safety requirements will be the same throughout. Follow the Accident
Prevention Plan (AAP) and Activity Hazard Analysis (AHA), as applicable, the Contractor has created for the entirety of the work.
9.3. Deliveries and Travel.
9.3.1. Vehicle inspections may be required at the Installation Access Control Point (IACP) prior to allowing installation access.
9.3.2. Coordination between Contractor and 5 SFS/S6 may occur to allow pre-delivery of materials regarding shipping/delivery address if space is available.
9.3.3. Travel is at the responsibility of the Contractor, as applicable, to fulfill the performance of this SOW.
9.3.4. Post Award Conference.
9.3.4.1. The Contractor must attend a Post Award Conference with the Contracting Officer, Customer, and other Government entities, no later than ten (10) business days after the date of award. The purpose of the Post Award Conference, which will be chaired by the Contracting Officer or Government PM, is to discuss technical and contracting objectives of this contract and review the Contractor’s draft project plan.
9.4. Project Plan, when applicable.
9.4.1. The Contractor must provide a draft Project Plan at the Post Award Conference for Government review and comment. The Project Plan must include the floor plan design, as required within this SOW. The Contractor must provide a final Project Plan to the Customer not later than five (5) business days after the Post Award Conference.
9.5. Document/Drawing Security.
9.5.1. Transmittal. Electronic transmittal is approved, unless otherwise instructed to do so.
9.5.2. Labeling of information on Drawings:
9.5.2.1. All information, either in electronic or paper formats, must have imprinted on each page of the following information:
PROPERTY OF THE UNITED STATES GOVERNMENT
CONTROLLED UNCLASSIFIED INFORMATION (CUI)
Do Not Remove This Notice Properly Destroy Medium When No Longer Needed
9.5.2.2. The following information will be included on the cover page of the information (such as the cover page on the set of construction drawings or on the cover page of the specifications) and on the label of all magnetic media:
PROPERTY OF THE UNITED STATES GOVERNMENT
CONTROLLED UNCLASSIFIED INFORMATION (CUI)
COPYING, DISSEMINATION, OR DISTRIBUTION OF THESE DRAWINGS, PLANS,
OR SPECIFICATIONS TO UNAUTHROIZED USERS IS PROHIBITED.
Do Not Remove This Notice.
Properly Destroy Documents When No Longer Needed.
NOTE* Manufacture instructions of equipment may not be required to have above labeling.
A.1. SPECIFICATIONS.
ATTACHMENT 1
SOW to Project Vigilance
NOTE* Specifications are to be equal to or greate in accordance with the equipment options listed on the Configuration Management Database Provided by 5 SFS/S6 upon request.
Table 1.1.
ITEM TITLE: ITEM EXPLANATION:
Compatibility
Monitoring capability must be compatible with Bldg. 547, Bldg. 475, and Bldg. 768, existing infrastructure.
Monitoring Ability to connect to contractor provided monitor(s), viewing all cameras simultaneously from Central Security Control (CSC). At Bldg. 475, ability to connect to contractor provided monitor(s), viewing all Phase I and Phase II cameras installed on the Flightline. Bldg. 475 do not have a requirement to view Security Forces, Confinement cameras. At Bldg. 768/MOC, ability to connect to contractor provided monitor(s), viewing all Phase I and Phase II cameras installed on the Flightline. MOC does not have a requirement to view Security Forces Gates or Confinement cameras.
Standalone system Ability to connect from camera location(s) (i.e., open field) to/from control center WITHOUT utilizing AFNet. AFNet/(NIPR) will not be utilized. Dark fiber will be utilized to connect camera locations to control centers.
Perpetual Licensing No additional outyear licensing fees, costs, taxes, etc.
Server(s) Redundant servers that provide automatic failover.
Capability to store video for 90-days and 30 days or more for Confinement.
Self-Diagnostic Program Complete and automatic capability.
Calibration (if applicable) Automatic and manual calibration.
Resolution High resolution 1080P Color Pan-tilt Zoom Cameras with 90-Day Video Retention.
Viewing / Operability
Fixed wide-angle cameras that provide visual coverage of entry/exit points and perimeter of the installation and/or, pan-tilt-zoom (PTZ) to provide similar coverage.
Ability to functionally operate with a visibility of 2.5 candle watts capability.
Analytics Ability to identify/distinguish object, vehicle, person detection during low light visibility.
Tamper-Proof Preventive measures and/or securing devices to prevent inadvertent and direct damage. Confinement cameras must be anti-ligature and anti-vandal proofed.
Power
Ability to function without use of grid AC power input.
Equipment will require solar power with battery back-up; solar panel 200W with pole mount bracket; 1200WH lithium battery with charge controller.
Battery Pack Minimum of 18-hours.
Temperatures Ability to operate: -30 degrees to +120 degrees.
Humidity to 65% non-condensing. Or provide enclosures to meet the threshold as prescribed.
Weatherproofing Meets IP 55, IP 65, standard for moisture, foreign matter protection.
Ability to functionally operate in an outdoor environment such as snow, hail, -30 degrees, and high winds.
Connection System will have point-to-point wired connection. Contractor will provide required amount of APL compliant network switches, LC-LC, SC-LC, ST-LC, 10G SFPs, and RJ-45 cables to directly connect the system to cameras via Fiber cable and any miscellaneous connectors required for installation not previously referenced by this SOW.
Output(s) Multiple POE outputs to connect multiple devices.
Construction
Robust enclosure, made of 1.2mm – 1.5mm SECC steel.
Immunity to electrical interference, ambient noise, and mechanical vibrations.
Cooling Cooling and ventilation design to prevent overheating and damage.
Mounting
Compact dimensions for pole mount.
Ability to be installed in current mounting locations or installed with minimal modifications to location when hardware is available. Provide wall-mount, lockable, switch cabinets at all locations requiring a network switch.
Quick Program Change Ability to change program settings without waiting for the system to update, as applicable.
Remote Control Desktop Remote Control with Zone indication.
Warranty/Sustainment Provide 5-year warranty/sustainment that includes but is not limited to; at a minimum semi-annual on-site sustainment of all installed equipment and 24/7 contact with on-call technicians to assist owner/user with system and equipment troubleshooting.
Definitions:
CSC Central Security Control FCC Federal Communications Commission ICNIRP International Commission on Non-Ionizing Radiation Protection IEEE Institute of Electrical and Electronics Engineers IP Ingress Protection POE Power over Ethernet SECC Electrolytic zinc-coated steel sheet and strip
| 1. OVERVIEW/DESCRIPITION OF SERVICES. |
| 2. LOCATION. |
| 3. BACKGROUND: |
| 4. GENERAL REQUIREMENTS. |
| 5. SCOPE. |
| 6. PERIOD OF PERFORMANCE (PoP). |
| 7. OPERATING CONSTRAINTS. |
| 8. WARRANTY. |
| 9. OTHER APPLICABLE CONDITIONS. |
| ATTACHMENT 1 |
| SOW to Project Vigilance |