10-0096 Specifications.pdf

PDF 3 MB Posted

Attached to
Repair Exhaust Hood and Surrounding Roof
Solicitation number
FA4528-11-R-0024
Issued by

About this file

Specifications

View the file

Other files

File Type Posted
10-0096 Drawings.pdf PDF
Attachment 3Wage Determination ND5.docx DOCX document
Attachment 4 Recent and Relevant Experience.doc DOC document
Solicitation.rtf RTF text file
Attachment 5 Responsibility Questionnaire.doc DOC document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

S P E C I F I C A T I O N

FOR PROJECT

QJVF 10-0096

DESIGN / REPAIR OF ROOF / VENT

HOOD FOR KITCHEN ON BLDG. 292

J.R. ROCKERS

AT

MINOT AIR FORCE BASE, NORTH DAKOTA

PREPARED BY:

5 CES, ENGINEERING FLIGHT

EAPC ARCHITECTS ENGINEERS, MINOT ND

APRIL 2011

TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

Section 00800 Info Available to Bidders Section 01000 Summary Section 01005 Administrative Provisions Section 01045 Cutting and Patching Section 01300 Submittals USAF Forms Section 01400 Quality Control Section 01430 Environmental Protection Section 01500 Construction Facilities and

Temporary Controls Section 01700 Contract Close-out Section 01710 Final Cleaning Section 01732 Selective Demolition Section 01781 Project Record Documents Section 01820 Demonstration & Training

DIVISION 02 - SITE CONSTRUCTION

No Sections Used

DIVISION 03 - CONCRETE

No Sections Used

DIVISION 04 - MASONRY

No Sections Used

DIVISION 05 - METALS

Section 05120 Structural Steel Section 05500 Metal Fabrications

DIVISION 06 - WOOD AND PLASTICS

Section 06100 Rough Carpentry

DIVISION 07 - THERMAL AND MOISTURE

PROTECTION

Section 07511 Built-up Asphalt Roofing Section 07620 Sheet Metal Flashing & Trim Section 07920 Joint Sealants

DIVISION 08 - DOORS AND WINDOWS

No Sections Used

DIVISION 09 - FINISHES

Section 09250 Gypsum Board Section 09912 Interior Painting

DIVISION 10 - SPECIALTIES

No Sections Used

DIVISION 11 - EQUIPMENT

Section 11400 Food Service Equipment

DIVISION 12 - FURNISHINGS

No Sections Used

DIVISION 13 - SPECIAL CONSTRUCTION

No Sections Used

DIVISION 14 - CONVEYING SYSTEMS

No Sections Used

DIVISION 15 - MECHANICAL

Section 15051 Basic Mechanical Materials &

Methods Section 15055 Motors Section 15060 Hangers & Supports Section 15075 Mechanical Identification Section 15081 Duct Insulation Section 15194 Fuel Gas Piping Section 15315 Fire Suppression Piping Section 15715 Kitchen Make-Up AHU Section 15815 Metal Ducts Section 15820 Duct Accessories Section 15835 Power Ventilators Section 15855 Diffusers, Registers & Grilles Section 15870 Commercial Kitchen Hoods Section 15940 Sequence of Operations Section 15950 Testing, Adjusting & Balancing

DIVISION 16 - ELECTRICAL

Section 16060 Grounding & Bonding Section 16073 Hangers & Supports for Electrical Systems Section 16075 Electrical Identification Section 16120 Conductors & Cables Section 16130 Raceways & Boxes Section 16140 Wiring Devices Section 16410 Enclosed Switches & Circuit Breakers Section 16491 Fuses Section 16511 Interior Lighting

SECTION 01000 - SUMMARY

PART 1 - GENERAL

1.1 SUMMARY

A. Section Includes:

1. Project information.

2. Work covered by Contract Documents.

3. Access to site.

4. Coordination with occupants.

5. Work restrictions.

6. Specification and drawing conventions.

7. Miscellaneous provisions.

8. Project schedule

B. Related Requirements:

1. Section 01500 "Temporary Facilities and Controls" for limitations and procedures governing temporary use of Owner's facilities.

1.2 PROJECT INFORMATION

A. Project Identification: QJVF 06-0055 J.R. Rocker B292.

1. Project Location: Minot Air Force Base, Minot, ND 58705.

B. Owner: Minot Air Force Base.

1. Contracting Officer: 211 Missile Avenue, Minot Air Force Base, Minot, ND 58705- 5027.

C. Architect: EAPC Architects Engineers, 300 Third Avenue SW, Suite A, Minot, ND 58701.

D. Contract Administrator: 5CONS/LGCA.

E. Inspector: 5CES/CEPM.

1.3 WORK COVERED BY CONTRACT DOCUMENTS

A. The Work of Project is defined by the Contract Documents and consists of the following:

1. Remove existing kitchen exhaust hood and associated fans, ductwork, fire suppression system, ceilings, lights, roofing systems and wet sprinkler system. Repair built up roofing and all relative flashing, coping, gypsum wallboard ceiling and paint.

SUMMARY 01000 - 1 QJVF 10-0096

B. Type of Contract.

1. Project will be constructed under a single prime contract.

1.4 PHASED CONSTRUCTION

A. The Work shall be conducted in one phase.

1.5 ACCESS TO SITE

A. Use of Site: Limit use of Project site to areas within the Contract limits indicated. Do not disturb portions of Project site beyond areas in which the Work is indicated.

1. Limits: Confine construction operations to area shown on Drawings.

2. Driveways, Walkways and Entrances: Keep driveways loading areas, and entrances serving premises clear and available to Government, Government employees, and emergency vehicles at all times. Do not use these areas for parking or storage of materials.

a. Schedule deliveries to minimize use of driveways and entrances by construction operations.

b. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site.

B. Condition of Existing Building: Maintain portions of existing building affected by construction operations in a weathertight condition throughout construction period. Repair damage caused by construction operations.

1.6 COORDINATION WITH OCCUPANTS

A. Government Limited Occupancy of Completed Areas of Construction: Government reserves the right to occupy and to place and install equipment in completed portions of the Work, prior to Substantial Completion of the Work, provided such occupancy does not interfere with completion of the Work. Such placement of equipment and limited occupancy shall not constitute acceptance of the total Work.

1. Before limited occupancy, mechanical and electrical systems shall be fully operational, and required tests and inspections shall be successfully completed. On occupancy, Government will operate and maintain mechanical and electrical systems serving occupied portions of Work.

2. On occupancy, Government will assume responsibility for maintenance and custodial service for occupied portions of Work.

SUMMARY 01000 - 2 QJVF 10-0096

1.7 WORK RESTRICTIONS

A. Work Restrictions, General: Comply with restrictions on construction operations.

1. Comply with limitations on use of public streets and with other requirements of authorities having jurisdiction.

B. Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by Government or others unless permitted under the following conditions and then only after providing temporary utility services according to requirements indicated:

1. Notify Government not less than two days in advance of proposed utility interruptions.

C. Noise, Vibration, and Odors: Coordinate operations that may result in high levels of noise and vibration, odors, or other disruption to Government occupancy with Government.

D. Nonsmoking Building: Smoking is not permitted within the building or within 25 feet (8 m) of entrances, operable windows, or outdoor-air intakes.

E. Controlled Substances: Use of tobacco products and other controlled substances on Project site is not permitted.

1.8 SPECIFICATION AND DRAWING CONVENTIONS

A. Specification Content: The Specifications use certain conventions for the style of language and the intended meaning of certain terms, words, and phrases when used in particular situations.

These conventions are as follows:

1. Imperative mood and streamlined language are generally used in the Specifications. The words "shall," "shall be," or "shall comply with," depending on the context, are implied where a colon (:) is used within a sentence or phrase.

2. Specification requirements are to be performed by Contractor unless specifically stated otherwise.

B. Division 01 General Requirements: Requirements of Sections in Division 01 apply to the Work of all Sections in the Specifications.

C. Drawing Coordination: Requirements for materials and products identified on Drawings are described in detail in the Specifications. One or more of the following are used on Drawings to identify materials and products:

1. Terminology: Materials and products are identified by the typical generic terms used in the individual Specifications Sections.

2. Abbreviations: Materials and products are identified by abbreviations published as part of the U.S. National CAD Standard.

3. Keynoting: Materials and products are identified by reference keynotes referencing Specification Section numbers found in this Project Manual.

SUMMARY 01000 - 3 QJVF 10-0096

SUMMARY 01000 - 4 QJVF 10-0096

1.9 MISCELLANEOUS PROVISIONS

A. Codes used: IBC 2006, IMC 2006, NFPA 13, NFPA 96 and NEC.

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION (Not Used)

END OF SECTION 01000

SECTION 01045 – CUTTING AND PATCHING

1.1 REQUIREMENTS INCLUDED

A. Requirements and limitations for cutting and patching of Work.

1.2 RELATED REQUIREMENTS

A. Individual specifications.

B. Cutting and patching incidental to Work of the Section.

C. Advance notification to other Sections of openings required in Work of those Sections.

D. Limitations on cutting structural members.

1.3 SUBMITTALS

A. Submit written request in advance of cutting or alteration which affects:

1. Structural integrity of any element of project.

2. Integrity of weather-exposed or moisture-resistant element.

3. Efficiency, maintenance, or safety of any operational element.

4. Visual qualities of sight-exposed elements.

5. Work by Government.

B. Include in request.

1. Identification of project.

2. Location and description of affected Work.

3. Necessity for cutting or alteration.

4. Description of proposed Work and products to be used.

5. Alternatives to cutting and patching.

6. Date and time Work will be executed.

PART 2 - PRODUCTS

2.1 MATERIALS

A. Those required for original installation.

CUTTING & PATCHING 01045 - 1 QJVF 10-0096

CUTTING & PATCHING 01045 - 2 QJVF 10-0096

PART 3 - EXECUTION

3.1 GENERAL

A. Execute cutting, fitting and patching (including excavation and fill) to complete Work, and to:

1. Fit the several parts together, to integrate with other work.

2. Uncover work to install ill-timed work.

3. Remove and replace defective and non-conforming work.

4. Remove samples of installed work for testing.

5. Provide openings in elements of work for penetrations of mechanical and electrical work.

3.2 INSPECTION

A. Inspect existing conditions, including elements subject to damage or movement during cutting and patching.

B. After uncovering, inspect conditions affecting performance of work.

C. Beginning of cutting or patching means acceptance of existing conditions.

3.3 PREPARATION

A. Provide supports to assure structural integrity of surroundings; devices and methods to protect other portions of project from damage.

B. Provide protection from elements for areas which may be exposed by uncovering work;

maintain excavations free of water.

3.4 PERFORMANCE

A. Execute work by methods to avoid damages to other work and which will provide proper surfaces to receive patching and finishing.

B. Cut rigid materials using masonry saw or core drill. Pneumatic tools not allowed.

C. Restore work with new products.

D. Fit work airtight to pipes, sleeves, ducts, conduit and other penetrations through surfaces.

END OF SECTION 01045

SECTION 01300 – SUBMITTALS

1.1 PROCEDURES

A. The Contractor shall be required to submit items listed in the Submittal Schedule at the end of this section.

B. Transmit each item under AF 3000, Material Approval Submittal form. Identify contract num ber, project number, and Contractor. Identify section and paragraph reference for each item submitted with the AF 3000. Submit five (5) copies unless otherwise required elsewhere in the specification.

C. Unless specifically stated otherwise elsewhere in this specification, each submittal shall be ap-proved by the Contracting Officer prior to incorporation of materials into the work.

D. Approvals of submittals which do not conform to the Contract shall not be construed as a change to the contract.

E. The Contractor shall fill in the “Required Submission Date” on the AF Form 66s with the date he plans on submitting the submittals to the Government. A copy of the AF Form 66s with the required submission date filled in shall be submitted to the Contracting Officer for use by the contract administrator. Submit in accordance with Section 01300.

1.2 MANUFACTURER’S DATA AND SAMPLES

A. For the following types of submittals when a specific product of a specific manufacturer is iden-tified (by catalog or product number, pattern, or style) and the Contractor does not desire to propose an alternate product as an equal, where an equal is allowed, a detailed submittal will not be required. The Contractor shall submit on an AF Form 3000 a list of submittals for which the specified products will be used. Submit in accordance with procedures identified in 1.1 above.

B. Product Data: Submit complete manufacturer’s literature which describes all salient characteris-tics identified as requirements in the specification. Literature which is not specific to the pro-posed product shall be marked to indicate clearly which item is being proposed for use in this contract.

C. Manufacturer’s Certification: Submit a statement from the product manufacturer that proposed products meet the specified standards and other salient characteristics identified as require-ments in the specification.

D. Installation Instructions: Submit manufacturer’s printed instructions for delivery, storage, as-sembly, installation, start-up (if applicable) and adjustments. Information shall include tempera-ture restrictions and any other environmental limitations as well as substrate preparation re-quirements if any exist.

SUBMITTALS 01300 - 1 QJVF 10-0096

1.3 SHOP DRAWINGS

A. Drawings shall illustrate how the specified materials are integrated into the work as a whole.

Adjacent materials which affect the complete installation of the specified products shall be shown and identified. Deviations from Contract drawings shall be clearly identified and reason for deviation clearly explained.

1.4 TEST DATA

A. Test results shall be dated and signed by the agency performing the test.

1.5 WARRANTY

A. Submit detailed warranty information which identifies specifically items covered as well as ex clusions from the warranty and the warranty period. All copies shall be dated and signed by an authorized officer of the company. The officer’s name and title shall be typed on the warranty adjacent to the signature.

1.6 OPERATION/MAINTENANCE INSTRUCTIONS

A. Submit manufacturer’s published instructions.

1.7 MISCELLANEOUS SUBMITTALS

A. Submittals which are none of the above types shall meet the specific requirements identified in the referenced paragraph of the Specification Section identified in the schedule.

1.8 SUBMITTAL SCHEDULE

A. The following is a list of required submittals for this Contract.

1. See attached AF Form 66.

SUBMITTALS 01300 - 2 QJVF 10-0096

SUBMITTALS 01300 - 3 QJVF 10-0096

1.9 AS-BUILT DRAWINGS

A. The Contractor shall maintain a set of red-lined full scale, as-built construction drawings marked-up to fully indicate as- built conditions. These drawings shall be maintained in a current review by Government personnel at all times. The location as dimensioned from permanent features, general description, type of material, and approximate depth below finished grade of all new and existing exterior underground utilities encountered shall be indicated. All variations from the contract drawings for the required coordination between trades shall be indicated.

These variations shall be shown in the same general detail utilized in the initial contract drawings. As-built construction drawings shall be furnished to the Contracting Officer for use during the final inspection. The as-built drawings shall be submitted to the Contracting Officer in accordance with this section.

END OF SECTION 01300

SECTION 01400 - QUALITY CONTROL

1.1 REQUIREMENTS INCLUDED

A. General Quality Control.

B. Workmanship.

C. Manufacturers’ Instructions.

D. Manufacturers’ Certificates.

E. Manufacturers’ Field Services.

F. Testing Laboratory Services.

1.2 RELATED REQUIREMENTS

A. Section 01300 – Submittals: Submittal of Manufacturers’

1.3 QUALITY CONTROL

A. Maintain quality control over suppliers, manufactures, products, services, site conditions and workmanship, to produce work of specified quality.

1.4 WORKMANSHIP

A. Comply with industry standards except when more restrictive tolerances or specified requirements indicate more rigid standards or more precise workmanship.

B. Perform work by persons qualified to produce workmanship of specified quality.

C. Secure products in place with positive anchorage devices designed and sized to withstand stresses, vibrations and racking.

1.5 MANUFACTURERS’ INSTRUCTIONS

A. Comply with instructions in full detail, including each step in sequence. Should instructions conflict with Contract Documents, request clarification from Contracting Officer before proceeding.

QUALITY CONTROL 01400 - 1 QJVF 10-0096

QUALITY CONTROL 01400 - 2 QJVF 10-0096

1.6 MANUFACTURERS’ CERTIFICATES

A. When required by individual Specifications Section, submit manufacturer’s certificate (five copies) that products meet or exceed specified requirements.

1.7 MANUFACTURERS’ FIELD SERVICES

A. When specified in respective Specifications Sections, require supplier or manufacturer to provide qualified personnel to observe field conditions, conditions of surfaces and installation, quality of workmanship, start-up of equipment, test, adjust and balance of equipment as applicable, and to make appropriate recommendations. This is required for installation of the ditch sluice gate.

B. Representative shall submit written report to the Contracting Officer listing observations and recommendations.

1.8 TESTING LABORATORY SERVICES

A. Contractor shall employ and pay for services of an Independent Testing Laboratory to perform inspections, tests and other services required by individual Specification Sections.

B. Services will be performed in accordance with requirements of governing authorities and with specified standards.

C. Reports will be submitted to Contracting Officer in duplicate giving observations and results of tests, indicating compliance or non-compliance with specified standards and with Contract Documents.

D. Contractor shall cooperate with Testing Laboratory personnel; furnish tools, samples of material, design mix, equipment, storage and assistance as required.

1. Notify Contracting Officer and Testing Laboratory 24 hours prior to expected time for operations requiring testing services.

2. Make arrangements with Testing Laboratory and pay for additional samples and tests for Contractor’s convenience.

PART 2 - PRODUCTS: Non applicable.

PART 3 - EXECUTION: Non applicable.

END OF SECTION 01400

SECTION 01430 – ENVIRONMENTAL PROTECTION

1.1 The Contractor shall perform all work in such manner as to minimize the polluting of air, water, or land, and shall within reasonable limits, control noise and the disposal of solid waste materials, as well as other pollutants. The Contractor shall be responsible for implementing the terms and requirements of NPDES PERMIT REQUIREMENTS FOR STORM WATER

DISCHARGE FROM CONSTRUCTION SITES.

1.2 IMPLEMENTATION

A. Within 20 calendar days after Notice to Proceed and prior to commencement of the Work at the Site, the Contractor shall:

1. Detail his proposal for implementing the requirements for environmental pollution control specified herein.

2. Meeting: Meet with representatives of the Contracting Officer to review and alter his proposal as needed for compliance with the environmental pollution control program.

PART 2 - PRODUCTS: Non Applicable.

PART 3 - EXECUTION

3.1 PRECONSTRUCTION SURVEY

A. Prior to start of any on-site construction activities, the Contractor and the Contracting Officer shall make a joint condition survey after which the Contractor shall prepare a brief report indicating on a layout plan the condition of trees, shrubs and grassed areas immediately adjacent to the site of the work and adjacent to his assigned storage area and access route as applicable. This report will be signed by both the Contracting Officer and Contractor upon mutual agreement as to its accuracy and completeness.

3.2 PROTECTION OF LAND AREAS

A. Except for work areas, storage areas, or access routes specifically assigned for the use of the Contractor under this contract, the land areas outside the limits of permanent work performed under this contract shall be preserved in their present condition. The Contractor shall confine his construction activities to areas defined for work on- the plans or specifically assigned for his use. Storage and related areas and access routes required temporarily by the Contractor in the performance of the work will be assigned by the Contracting Officer.

ENVIRONMENTAL PROTECTION 01430 - 1 QJVF 10-0096

3.3 PROTECTION OF TREES AND SHRUBS

A. Except for trees or shrubs marked on the plans to be removed, the Contractor shall not deface, injure or destroy trees or shrubs, nor remove or cut them without special authority. No ropes, cables, or guys shall be fastened to or attached to any existing nearby trees f or anchorage.

1. Tree Protective Structures: Where, in the opinion of the Contracting Officer, trees may possibly be defaced, bruised, injured, or otherwise damaged by the Contractor’s equipment or by his other operations, he may direct the Contractor to provide temporary protection of such trees by placing boards, planks, or poles around them.

2. Restoration of Damaged Trees: Any tree scarred or damaged by the Contractor’s equipment or operations shall be restored as nearly as possible to its original condition at the Contractor’s expense. All scars made on trees not designated on the plans to be removed by construction operations shall be coated as soon as possible with an approved tree wound dressing. Trees that are to remain, either within or outside established clearing limits, that are damaged by the Contractor so as to be beyond saving in the opinion of the Contracting Officer shall be immediately removed, if so directed, and replaced with a nursery-grown tree of the same species and size.

3.4 WASTE DISPOSAL

A. As part of his proposed implementation under paragraph 1.2, and prior to on-site construction, the Contractor shall submit a description of his scheme for handling and disposing of all waste resulting from the work under this contract. If any waste is dumped in unauthorized areas, the Contractor shall remove the waste and restore the area to the condition of the adjacent undisturbed areas. Where directed, soil which is contaminated by the Contractor shall be excavated, disposed of as approved by the Contracting Officer, and replaced with suitable fill material, all at the expense of the Contractor.

3.5 BURNING

A. Burning shall be prohibited on the Government premises.

3.6 DUST CONTROL

A. The Contractor shall maintain all work areas free from excess dust to such reasonable degree as to avoid causing a hazard or nuisance. Dust control shall be performed as the work proceeds and whenever a dust nuisance or hazard occurs.

3.7 CORRECTIVE ACTION

A. The Contractor shall, upon receipt of a notice in writing of any noncompliance with the foregoing provisions, take immediate corrective action. If the Contractor fails or refuses to comply promptly, the Contracting Officer may issue an order stopping all or part of the work until satisfactory corrective action has been taken. No part of the time lost due to any such stop orders shall be made the subject of a claim for extension of time or for excess costs of damages by the Contractor unless it was latter determined that the Contractor was in compliance.

ENVIRONMENTAL PROTECTION 01430 - 2 QJVF 10-0096

3.8 POST-CONSTRUCTION CLEANUP OR OBLITERATION

A. The Contractor shall, unless otherwise instructed in writing by the Contracting Officer, obliterate all signs of temporary construction facilities such as haul roads, work areas, structures, foundations of temporary structures, stockpiles of excess or waste materials, and other vestiges of construction prior to final acceptance of the work. The disturbed areas shall be graded and filled and the entire area seeded.

3.9 SPILL PREVENTION AND RESPONSE PLAN

A. The Contractor shall include a Spill Prevention and Response Plan in the Implementation Proposal. The plan shall describe the Contractor’s procedures for preventing and responding to spills of hazardous materials.

3.10 ARCHEOLOGICAL PRESERVATION:

A. Should the Contractor uncover any skeletons, artifacts or other archeological remains during the course of excavation, the work shall be stopped and the Contracting Officer notified immediately.

3.11 NDPDES PERMIT REQUIREMENTS FOR STORM WATER DISCHARGES FROM

CONSTRUCTION SITES

A. Notice of Intent: The Contractor shall complete and submit a Notice of Intent (NOI) in accordance with the NDPDES general permit. A copy of the submitted Notice of Intent and Notice of Acceptance (NOA) shall be furnished to the Contracting Officer at least 2 days prior to the commencement of construction activities.

B. Storm Water Pollution Prevention Plan: The Contractor shall prepare, submit and implement a Storm Water Pollution Prevention Plan in accordance with the NDPDES general permit. Any temporary or permanent erosion and sedimentation control measures shown on the drawings shall be incorporated into the Contractor’s Storm Water Pollution Prevention Plan. A copy of the Storm Water Pollution Prevention Plan shall be submitted to the Contracting Officer at least 2 days prior to the commencement of construction activities.

C. Inspections and Reporting: The Contractor shall be responsible for all inspections and reporting required under the NDPDES general permit. Copies of each inspection Report Form shall be furnished to the Contracting Officer.

D. Retention of Records: The Contractor shall retain copies of the storm water pollution prevention plan and all reports in accordance with the NDPDES general permit.

E. Notice of Termination: The Contractor shall complete and submit a Notice of Termination (NOT) in -accordance with the NDPDES general permit. A copy of the submitted Notice of Termination shall be furnished to the Contracting Officer.

ENVIRONMENTAL PROTECTION 01430 - 3 QJVF 10-0096

ENVIRONMENTAL PROTECTION 01430 - 4 QJVF 10-0096

F. Renotification: If the current NDPDES general permit expires prior to completion of construction, the Contractor shall request to retain coverage under a renewal of the permit in writing to the State at least 15 days prior to the expiration date of the permit. Upon request by the State, a new NOI shall be submitted. The Contractor shall provide certification to the State that the SWPP plan is accurate. The certification shall be submitted within 90 days after the coverage under the permit begins.

G. A copy of all submissions to the State shall be furnished to the Contracting officer.

END OF SECTION 01430

SECTION 01500 – CONSTRUCTION FACILITIES & TEMPORARY CONTROLS

1.1 REQUIREMENTS INCLUDED

A. Electricity, lighting.

B. Heat, ventilation.

C. Telephone service.

D. Water.

E. Sanitary Facilities.

F. Barriers.

G. Enclosures.

H. Protection of installed work.

I. Security.

J. Water Control.

K. Cleaning during construction.

L. Field offices and sheds.

1.2 RELATED REQUIREMENTS

A. Outages.

1. Outages shall include:

a. Blocking of roadways.

b. Blocking of parking lots.

c. Power outages.

d. High temperature hot water lines.

B. Notification.

1. The contractor shall notify the Contracting Officer in writing, seven days in advance of the intended outage.

2. The contractor shall notify the Fire Department of an intended roadway blockage.

CONSTRUCTION FACILITIES &

TEMPORARY CONTROLS 01500 - 1 QJVF 10-0096

1.3 REGULATIONS

1. The contractor shall comply with the prevention practice contained in NFPA Standard #241, Standard for Safeguarding Building Construction and Demolition Operations.

1.4 ELECTRICITY

1. All reasonable quantities of utilities will be made available to the Contractor at no charge.

2. Provide service required for construction operations, with branch wiring and distribution boxes located to allow service and lighting by means of Construction-type power cords.

3. Provide lighting for construction operations.

4. Existing and permanent lighting may be used during construction. Maintain lighting and make routine repairs.

1.5 HEAT, VENTILATION

A. Provide as required to maintain specified conditions for construction operations, to protect material and finishes from damage due to temperature or humidity.

B. Coordinate use of existing facilities with Using Agency; extend and supplement with temporary units as require to maintain specified conditions for construction operations, to protect materials and finishes from damage due to temperature or humidity. The Government will furnish all Contractor energy.

C. Prior to operation of permanent facilities for temporary purposes, verify that installation is approved for operation, and that filters are in place. Provide for operation and maintenance.

D. Provide ventilation of enclosed areas to cure material, to disperse humidity and to prevent accumulation of dust, fumes, vapors, or gases.

1.6 TELEPHONE SERVICE

A. Provide telephone service to field office.

B. Contractor shall pay all telephone, land line or cellular, related expenses included installation and disconnection.

1.7 WATER

A. Government shall provide water as required for construction operations. Extend brand piping with outlets located so that water is available by use of hoses.

1.8 SANITARY FACILITIES

A. Contractor to provide portable sanitary facility at no cost to the Government.

TEMPORARY CONTROLS 01500 - 2 QJVF 10-0096

1.9 BARRIERS

A. Provide as required to prevent public entry to construction areas and to protect existing facilities and adjacent properties from damage from construction operations.

B. Provide barricades as required by governing authorities for public right-of-way and for public access to existing building.

C. Provide barriers around trees and plants designate to remain. Protect against vehicular traffic, stored material, dumping, chemically injurious materials and puddling or continuous running water.

1.10 ENCLOSURES

A. Provide temporary weather-tight closures of openings in exterior surfaces to provide acceptable working conditions and protection for materials, to allow for temporary heating and to prevent entry of unauthorized persons. Provide doors with self-closing hardware and locks.

1.11 PROTECTION OF INSTALLED WORK

A. Provide temporary protection for installed products. Control traffic in immediate area to minimize damage.

B. Provide protection coverings at walls, projections, jambs, sills and soffits of openings. Protect finished floors and stairs from traffic, movement of heavy objects and storage.

C. Prohibit traffic and storage on waterproofed and roofed surfaces and on lawn and landscaping areas.

1.12 SECURITY

A. Provide security program and Using Agency’s facilities to protect work (existing facilities) and Using Agency’s operations from unauthorized entry, vandalism and theft. Coordinate with Contracting Officer and Security Police.

1.13 WATER CONTROL

A. Grade site to drain. Maintain excavations free of water. Provide and operate pumping equipment, as required.

1.14 CLEANING DURING CONSTRUCTION

A. Control accumulation of waste materials and rubbish; periodically dispose of off-site daily.

B. Clean interior areas prior to start of finish work, maintain areas free of dust and other contaminants during finishing operations.

TEMPORARY CONTROLS 01500 - 3 QJVF 10-0096

TEMPORARY CONTROLS 01500 - 4 QJVF 10-0096

1.15 REMOVAL

A. Remove temporary material, equipment, services and construction prior to substantial completion inspection.

B. Clean and require damage caused by installation of use of temporary facilities and services;

restore existing facilities used during construction to specified, or to original condition.

C. The Contractor shall daily maintain the site in a clean and orderly manner in accordance with Corp of Engineers Manual EM 385-1-1.

D. Asbestos.

1. Transportation of asbestos material shall be in accordance with North Dakota Century Code, Section 33-15-13-02.

2. Disposal of asbestos material shall be in accordance with Environmental Protection Agency “Standards for Owners and Operators of Hazardous Waste Treatment, Storage and Disposal Facilities,” as published in Vol. 45., No. 98 of the Federal Register, Monday, May 19, 1980. (40 CFR Parts 264 and 265, FRL 1446-B).

3. Submit a notarized statement from the Disposer that said disposal met all requirements of this regulation and any applicable state regulations.

PART 2 - PRODUCTS – Not Used.

PART 3 - EXECUTION – Not Used.

END OF SECTION 01500

SECTION 01700 – CONTRACT CLOSE-OUT

1.1 REQUIREMENTS INCLUDED

A. Close Out Procedures.

B. Final Cleaning.

C. Project Record Documents.

D. Operation and Maintenance Data.

E. Warranties and Bonds.

F. Spare Parts and Maintenance Materials.

1.2 RELATED REQUIREMENTS

A. Section 01005 – Administrative Provisions.

B. Section 01500 – Construction Facilities & Temporary Controls; Cleaning during construction.

1.3 CLOSE-OUT PROCEDURES

A. Using Agency will occupy designated portion of project for the purpose of conduct of business, under provision stated in Certificate of Substantial Completion.

B. When Contractor considers Work has reached final completion, submit written certification that Contract Documents have been reviewed, Work has been inspected and that Work is complete in accordance with Contract Documents and ready for final inspection.

1.4 FINAL CLEANING

A. See Section 01710.

END OF SECTION 01700

CONTRACT CLOSE-OUT 01700 - 1 QJVF 10-0096

SECTION 01710 – FINAL CLEANING

1.1 REQUIREMENTS INCLUDED

A. Final cleaning of project.

1.2 RELATED REQUIREMENTS

A. Individual Specifications Sections: Specific cleaning for product or Work.

1.3 DESCRIPTION

A. Execute cleaning prior to inspection for Final Completion of the Work.

B. Execute exterior and site cleaning.

PART 2 - PRODUCTS

2.1 CLEANING MATERIALS

A. Use materials which will not create hazards to health or property and which will not damage surfaces.

B. Use only material and methods recommended by manufacturer of material being cleaned.

PART 3 - EXECUTION

3.1 CLEANING

A. In addition to removal of debris and cleaning specified in other sections, clean exterior exposed-to-view surfaces.

B. Maintain cleaning until substantial completion, completion, or occupancy by Using Agency.

C. Remove waste, foreign matter and debris from all Work areas.

D. Remove waste, debris and surplus material from site. Clean grounds; remove stains, spills and foreign substances from paved areas and sweep clean.

END OF SECTION 01710

FINAL CLEANING 01710 - 1 QJVF 10-0096

SECTION 01732 - SELECTIVE DEMOLITION

1.1 SUMMARY

A. Section Includes:

1. Demolition and removal of selected portions of building or structure.

2. Salvage of existing items to be reused or recycled.

1.2 DEFINITIONS

A. Remove: Detach items from existing construction and legally dispose of them off-site unless indicated to be removed and salvaged or removed and reinstalled.

B. Remove and Reinstall: Detach items from existing construction, prepare for reuse, and reinstall where indicated.

C. Existing to Remain: Existing items of construction that are not to be permanently removed and that are not otherwise indicated to be removed, removed and salvaged, or removed and reinstalled.

1.3 PREINSTALLATION MEETINGS

A. Predemolition Conference: Conduct conference at Project site.

1.4 INFORMATIONAL SUBMITTALS

A. Qualification Data: For refrigerant recovery technician.

B. Predemolition Photographs or Video: Submit before Work begins.

C. Statement of Refrigerant Recovery: Signed by refrigerant recovery technician.

1.5 CLOSEOUT SUBMITTALS

A. Landfill Records: Indicate receipt and acceptance of hazardous wastes by a landfill facility licensed to accept hazardous wastes.

1.6 QUALITY ASSURANCE

A. Refrigerant Recovery Technician Qualifications: Certified by an EPA-approved certification program.

SELECTIVE DEMOLITION 01732 - 1 QJVF 10-0096

1.7 FIELD CONDITIONS

A. Government will occupy portions of building immediately adjacent to selective demolition area.

Conduct selective demolition so Government’s operations will not be disrupted.

B. Conditions existing at time of inspection for bidding purpose will be maintained by Government as far as practical.

C. Notify Contracting Officer of discrepancies between existing conditions and Drawings before proceeding with selective demolition.

D. Hazardous Materials: It is not expected that hazardous materials will be encountered in the Work.

1. If suspected hazardous materials are encountered, Contractor shall not disturb; but shall immediately notify Contracting Officer and Government. Hazardous materials will be removed and properly disposed of by this Contractor as part of this contract.

2. Asbestos report is attached in Section 00800.

E. Storage or sale of removed items or materials on-site is not permitted.

F. Utility Service: Maintain existing utilities indicated to remain in service and protect them against damage during selective demolition operations.

1. Maintain fire-protection facilities in service during selective demolition operations.

1.8 WARRANTY

A. Existing Warranties: Remove, replace, patch, and repair materials and surfaces cut or damaged during selective demolition, by methods and with materials so as not to void existing warranties.

PART 2 - PRODUCTS

2.1 PEFORMANCE REQUIREMENTS

A. Regulatory Requirements: Comply with governing EPA notification regulations before beginning selective demolition. Comply with hauling and disposal regulations of authorities having jurisdiction.

B. Standards: Comply with ANSI/ASSE A10.6 and NFPA 241.

PART 3 - EXECUTION

3.1 EXAMINATION

A. Verify that utilities have been disconnected and capped before starting selective demolition operations.

SELECTIVE DEMOLITION 01732 - 2 QJVF 10-0096

B. Survey existing conditions and correlate with requirements indicated to determine extent of selective demolition required.

C. When unanticipated mechanical, electrical, or structural elements that conflict with intended function or design are encountered, investigate and measure the nature and extent of conflict.

Promptly submit a written report to Contracting Officer.

3.2 UTILITY SERVICES AND MECHANICAL/ELECTRICAL SYSTEMS

A. Existing Services/Systems to Remain: Maintain services/systems indicated to remain and protect them against damage.

1. Comply with requirements for existing services/systems interruptions specified in Section 01000 "Summary."

B. Existing Services/Systems to Be Removed, Relocated, or Abandoned: Locate, identify, disconnect, and seal or cap off indicated utility services and mechanical/electrical systems serving areas to be selectively demolished.

1. Contracting Officer will arrange to shut off indicated services/systems when requested by Contractor.

2. Arrange to shut off indicated utilities with utility companies.

3. If services/systems are required to be removed, relocated, or abandoned, provide temporary services/systems that bypass area of selective demolition and that maintain continuity of services/systems to other parts of building.

4. Disconnect, demolish, and remove fire-suppression systems, plumbing, and HVAC systems, equipment, and components indicated to be removed.

a. Piping to Be Removed: Remove portion of piping indicated to be removed and cap or plug remaining piping with same or compatible piping material.

b. Piping to Be Abandoned in Place: Drain piping and cap or plug piping with same or compatible piping material.

c. Equipment to Be Removed: Disconnect and cap services and remove equipment.

d. Equipment to Be Removed and Reinstalled: Disconnect and cap services and remove, clean, and store equipment; when appropriate, reinstall, reconnect, and make equipment operational.

e. Equipment to Be Removed and Salvaged: Disconnect and cap services and remove equipment and deliver to Government.

f. Ducts to Be Removed: Remove portion of ducts indicated to be removed and plug remaining ducts with same or compatible ductwork material.

g. Ducts to Be Abandoned in Place: Cap or plug ducts with same or compatible ductwork material.

C. Refrigerant: Remove refrigerant from mechanical equipment to be selectively demolished according to 40 CFR 82 and regulations of authorities having jurisdiction.

SELECTIVE DEMOLITION 01732 - 3 QJVF 10-0096

3.3 PREPARATION

A. Site Access and Temporary Controls: Conduct selective demolition and debris-removal operations to ensure minimum interference with roads, streets, walks, walkways, and other adjacent occupied and used facilities.

1. Comply with requirements for access and protection specified in Section 01500.

B. Temporary Facilities: Provide temporary barricades and other protection required to prevent injury to people and damage to adjacent buildings and facilities to remain.

3.4 SELECTIVE DEMOLITION, GENERAL

A. General: Demolish and remove existing construction only to the extent required by new construction and as indicated. Use methods required to complete the Work within limitations of governing regulations and as follows:

1. Neatly cut openings and holes plumb, square, and true to dimensions required. Use cutting methods least likely to damage construction to remain or adjoining construction.

Use hand tools or small power tools designed for sawing or grinding, not hammering and chopping, to minimize disturbance of adjacent surfaces. Temporarily cover openings to remain.

2. Cut or drill from the exposed or finished side into concealed surfaces to avoid marring existing finished surfaces.

3. Do not use cutting torches until work area is cleared of flammable materials. At concealed spaces, such as duct and pipe interiors, verify condition and contents of hidden space before starting flame-cutting operations. Maintain fire watch and portable fire-suppression devices during flame-cutting operations.

4. Locate selective demolition equipment and remove debris and materials so as not to impose excessive loads on supporting walls, floors, or framing.

5. Dispose of demolished items and materials promptly.

B. Removed and Reinstalled Items:

1. Clean and repair items to functional condition adequate for intended reuse.

2. Pack or crate items after cleaning and repairing. Identify contents of containers.

3. Protect items from damage during transport and storage.

4. Reinstall items in locations indicated. Comply with installation requirements for new materials and equipment. Provide connections, supports, and miscellaneous materials necessary to make item functional for use indicated.

C. Existing Items to Remain: Protect construction indicated to remain against damage and soiling during selective demolition. When permitted by Contracting Officer items may be removed to a suitable, protected storage location during selective demolition and cleaned and reinstalled in their original locations after selective demolition operations are complete.

SELECTIVE DEMOLITION 01732 - 4 QJVF 10-0096

SELECTIVE DEMOLITION 01732 - 5 QJVF 10-0096

3.5 DISPOSAL OF DEMOLISHED MATERIALS

A. General: Except for items or materials indicated to be recycled, reused, salvaged, reinstalled, or otherwise indicated to remain Government’s property, remove demolished materials from Project site and legally dispose of them in an EPA-approved landfill.

1. Do not allow demolished materials to accumulate on-site.

2. Remove and transport debris in a manner that will prevent spillage on adjacent surfaces and areas.

3. Remove debris from elevated portions of building by chute, hoist, or other device that will convey debris to grade level in a controlled descent.

4. Comply with requirements specified in Section 01524 "Construction Waste

Management."

B. Burning: Do not burn demolished materials.

C. Disposal: Transport demolished materials off Government’s property and legally dispose of them.

3.6 CLEANING

A. Clean adjacent structures and improvements of dust, dirt, and debris caused by selective demolition operations. Return adjacent areas to condition existing before selective demolition operations began.

END OF SECTION 01732

SECTION 01781 - PROJECT RECORD DOCUMENTS

1.1 SUMMARY

A. Section includes administrative and procedural requirements for project record documents, including the following:

1. Record Drawings.

2. Record Specifications.

3. Record Product Data.

B. Related Requirements:

1. Section 01782 "Operation and Maintenance Data" for operation and maintenance manual requirements.

1.2 CLOSEOUT SUBMITTALS

A. Record Drawings: Comply with the following:

1. Number of Copies: Submit one set of marked-up record prints.

2. Number of Copies: Submit copies of record Drawings as follows:

a. Submittal:

1) Submit one paper-copy set of marked-up record prints.

2) Submit PDF electronic files of scanned record prints.

3) Submit record digital data files and one set of plots.

4) Government will indicate whether general scope of changes, additional information recorded, and quality of drafting are acceptable.

B. Record Specifications: Submit one paper copy and one annotated PDF electronic files of Project's Specifications, including addenda and contract modifications.

C. Record Product Data: Submit one paper copy and one annotated PDF electronic files and directories of each submittal.

PROJECT RECORD DOCUMENTS 01781 - 1 QJVF 10-0096

PART 2 - PRODUCTS

2.1 RECORD DRAWINGS

A. Record Prints: Maintain one set of marked-up paper copies of the Contract Drawings and Shop Drawings, incorporating new and revised Drawings as modifications are issued.

1. Preparation: Mark record prints to show the actual installation where installation varies from that shown originally. Require individual or entity who obtained record data, whether individual or entity is Installer, subcontractor, or similar entity, to provide information for preparation of corresponding marked-up record prints.

a. Give particular attention to information on concealed elements that would be difficult to identify or measure and record later.

b. Record data as soon as possible after obtaining it.

c. Record and check the markup before enclosing concealed installations.

2. Mark the Contract Drawings and Shop Drawings completely and accurately. Use personnel proficient at recording graphic information in production of marked-up record prints.

3. Mark record sets with erasable, red-colored pencil. Use other colors to distinguish between changes for different categories of the Work at same location.

4. Note Construction Change Directive numbers, alternate numbers, Change Order numbers, and similar identification, where applicable.

B. Record Digital Data Files: Immediately before inspection for Certificate of Substantial Completion, review marked-up record prints with Contracting Officer. When authorized, prepare a full set of corrected digital data files of the Contract Drawings, as follows:

1. Format: Annotated PDF electronic file.

2. Incorporate changes and additional information previously marked on record prints.

Delete, redraw, and add details and notations where applicable.

3. Refer instances of uncertainty to Contacting Officer for resolution.

4. Architect will furnish Contractor one set of digital data files of the Contract Drawings for use in recording information.

C. Format: Identify and date each record Drawing; include the designation "PROJECT RECORD DRAWING" in a prominent location.

1. Record Prints: Organize record prints and newly prepared record Drawings into manageable sets. Bind each set with durable paper cover sheets. Include identification on cover sheets.

2. Format: Annotated PDF electronic file.

3. Record Digital Data Files: Organize digital data information into separate electronic files that correspond to each sheet of the Contract Drawings. Name each file with the sheet identification. Include identification in each digital data file.

PROJECT RECORD DOCUMENTS 01781 - 2 QJVF 10-0096

4. Identification: As follows:

a. Project name.

b. Date.

c. Designation "PROJECT RECORD DRAWINGS."

d. Name of Contracting Officer.

e. Name of Contractor.

2.2 RECORD SPECIFICATIONS

A. Preparation: Mark Specifications to indicate the actual product installation where installation varies from that indicated in Specifications, addenda, and contract modifications.

1. Give particular attention to information on concealed products and installations that cannot be readily identified and recorded later.

2. Mark copy with the proprietary name and model number of products, materials, and equipment furnished, including substitutions and product options selected.

3. Record the name of manufacturer, supplier, Installer, and other information necessary to provide a record of selections made.

4. Note related Change Orders, record Product Data, and record Drawings where applicable.

B. Format: Submit record Specifications as scanned PDF electronic file(s) of marked-up paper copy of Specifications.

2.3 RECORD PRODUCT DATA

A. Preparation: Mark Product Data to indicate the actual product installation where installation varies substantially from that indicated in Product Data submittal.

1. Give particular attention to information on concealed products and installations that cannot be readily identified and recorded later.

2. Include significant changes in the product delivered to Project site and changes in manufacturer's written instructions for installation.

3. Note related Change Orders, record Specifications, and record Drawings where applicable.

B. Format: Submit record Product Data as scanned PDF electronic file(s) of marked-up paper copy of Product Data.

2.4 MISCELLANEOUS RECORD SUBMITTALS

A. Assemble miscellaneous records required by other Specification Sections for miscellaneous record keeping and submittal in connection with actual performance of the Work. Bind or file miscellaneous records and identify each, ready for continued use and reference.

B. Format: Submit miscellaneous record submittals as scanned PDF electronic file(s) of marked-up miscellaneous record submittals.

PROJECT RECORD DOCUMENTS 01781 - 3 QJVF 10-0096

PROJECT RECORD DOCUMENTS 01781 - 4 QJVF 10-0096

PART 3 - EXECUTION

3.1 RECORDING AND MAINTENANCE

A. Recording: Maintain one copy of each submittal during the construction period for project record document purposes. Post changes and revisions to project record documents as they occur; do not wait until end of Project.

B. Maintenance of Record Documents and Samples: Store record documents and Samples in the field office apart from the Contract Documents used for construction. Do not use project record documents for construction purposes.

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .