SOW - CDC Flooring
87 KB Posted
- Attached to
- RECOVERY-- GHLN081074 - Repair Flooring Replace Carpet Base Child Development Ctr Bldg 465
- Solicitation number
- FA4513-09-R-0010
Text of this file
STATEMENT OF WORK
REPLACE FLOORING
IN
CHILD DEVELOPMENT CENTER, BLDG. 465
F. E. WARREN AIR FORCE BASE
WYOMING
PROJECT NO.: GHLN 08-1074
Prepared By:
90th Civil Engineering Squadron
F.E. Warren Air Force Base, Wyoming
03 April 2009
STATEMENT OF WORK
REPLACE FLOORING IN CHILD DEVELOPMENT CENTER
GHLN 08-1074
F.E. WARREN AFB, WYOMING
1.
SCOPE OF WORK
a. Provide all labor, supervision, materials, equipment, accessories, incidentals and transportation necessary to REPLACE ALL CARPET and RESILIENT SHEET FLOORING in the Child Development Center (CDC) Building 465 in accordance with this Statement of Work and Attachments.
2. DESCRIPTION OF WORK:
a. The work descriptions provided herein are primarily "scope descriptions" that give a general overview and do not describe the full range of materials and processes needed to complete the required work.
b. The project includes but is not limited to the following principle items:
· Remove all existing carpet, sheet vinyl flooring and associated resilient base throughout the entire building.
· Install new carpet, sheet vinyl flooring and base at same locations as removed materials.
· Other related or incidental work as required to finish the described project. A complete and finished installation shall be provided.
c. No materials or equipment will be furnished by the Government.
d. No work is required in rooms having exposed concrete floors (Mechanical Room, Electrical Room and Comm Room) nor in rooms having quarry tile floors (Vestibules, Kitchen and Kitchen Storage Rooms) or in rooms with ceramic tile floors (Restrooms 118 and 119).
e. Refer to the end of this SOW for the six (6) Drawing Attachments that apply to this project.
3.
GENERAL INFORMATION and REQUIREMENTS
a. The CDC is a one-story building that was constructed in 1999. The existing floors are a concrete slab on grade. The walls are gypsum board. The total gross area of the entire building including exterior walls is approx. 19,000 sq. ft.
b. Prior to proposal submission, a scheduled tour of the building will be provided for Contractors to observe existing conditions and determine the full extent and nature of work required.
c. The performance period is 120 calendar days (four months) after award.
d. The building will be occupied during the entire duration of the project. Working hours for the Contractor will be restricted to CDC non-operating hours (i.e., 6:00 p.m. to 6:00 a.m., Monday through Friday) and Saturdays, Sundays and Federal holidays.
e. Coordinate access to the Base and Project Facility with the Government. All personnel must obtain a Base-issued Pass and ID card before working on the Base. The Contractor shall make a request for the proposed workers in a format dictated by the Government on a company letterhead. The ID card of each worker must be returned to the Government when that worker no longer requires access to the Base. All Contractor and delivery vehicles must enter the Base through Gate No. 2 where they will be inspected before entering the base.
f. Comply with pertinent Government security regulations while working on the project. Delays caused by entering and exiting the Base, military exercises, missile movements or other security reasons shall not result in any additional cost to the Government.
g. Protect the existing facility. Contractor shall be responsible for repairing any damage caused during the performance of this contract.
4.
SUBMITTALS
a. Submit manufacturer’s product data for Government review and approval of materials provided under this contract. For color selection, submit samples of the actual materials or color chips supplied by the manufacturer. Ordinary paper copies of colors are NOT acceptable.
b. Submit a Material Data Safety Sheet (MSDS) for each potentially hazardous material as described under the section entitled “HAZARDOUS and PROHIBITED CONSTRUCTION MATERIALS“.
5.
NEW and RECYCLED MATERIALS and EQUIPMENT / GENERAL REQUIREMENTS
a. All materials and equipment including those concealed or covered shall be new or newly manufactured using recycled content unless otherwise indicated. All materials (both new and recycled) shall be the most suitable and highest grade and type for the intended use unless otherwise indicated. They shall be produced by a manufacturer regularly engaged in manufacturing or fabricating similar products with a history of successful production acceptable to the Contracting Office.
b. When names of manufacturers or models are listed, the purpose is to give examples of products meeting the specifications and to provide a basis for the design, not to limit competition. Products by other manufacturers may be used, subject to the following: (1) The product is equivalent to the specified product, meets or exceeds the requirements of the specifications and is otherwise suitable for the intended use. Appearance is a major consideration for flooring. (2) The warranty meets or exceeds that of the specified product and the requirements of the specifications. (3) The Contractor coordinates the installation and makes any necessary changes at no additional cost to the Government. (4) The Contractor waives claims for any time extension associated with the use of the product. (5) The Government approves the use of the product in writing.
c. Comply with Air Force guidelines and requirements for the purchase and use of recycled construction materials. This is based upon Air Force Space Command Affirmative Procurement Program Policy and Guidance Letter dated 08 April 2002. The main legal requirements for an Affirmative Procurement Program (APP) are derived from Executive Order 13101 dated 14 September 1998 (http;//www.ofee.gov) and the Resource Conservation and Recovery Act (RCRA) Section 6002 (http://www.ornl.gov/ornlp2/sec6002.htm). This policy requires action by the Federal Government to make more efficient use of natural resources by maximizing recycling and preventing waste whenever possible. Specifically, it mandates procurement of the five EPA guideline items; calls for review of government plans and specifications to eliminate virgin material requirements; requires recycling programs and requires consideration of recovered materials use, reuse of products, life cycle cost analysis, ease of recycling and use of environmentally preferable products.
d. The use of materials with recycled content is mandatory unless they are not available within a reasonable time frame, or if the cost exceeds the cost of a non-recycled item or if they do not meet the technical requirements of the project, or if they are not available from at least two (2) sources so as to maintain a satisfactory level of competition.
e. Recycled Products Reporting. Contractors must compile a "Recycled Products Report" for the Resource Recovery and Recycling Manager at 90 CES/CEV listing the total quantity of recycled products used. Submit the report through the COAR at the end of the contract period or at the end of the calendar year, whichever comes first.
f. Material Storage: Contractors shall protect materials during delivery, storage, handling and installation per manufacturers’ printed instructions. Materials should be delivered in original containers or packaging with labels intact. No storage space is available in the existing CDC building.
6.
HAZARDOUS and PROHIBITED CONSTRUCTION MATERIALS:
a. Hazardous Materials (HM) Approval: Submit a Materials Safety Data Sheet (MSDS) for each chemical and/or compound proposed for this project. The Base Bioenvironmental Office (90 ADOS/SGGB) must complete their review and approval process prior to delivery to the Base. A HM is defined in Federal Standard DED-STD-313D, Tables I and II. The definition of materials presenting a health or physical hazard is found in OSHA 29 Code of Federal Regulations 1910.1200(c). These materials include such items as paint strippers, oils, paints, adhesives, sealants, cleaners and other chemicals. Contractors who bring hazardous materials onto FEW AFB without authorization are responsible for any punitive or regulatory actions.
b. Hazardous Materials Management: All HM shall be managed, stored and monitored in full compliance with all applicable local, state, federal and Goernment regulations. All chemicals shall be secured and properly stored when not in use. Flammable liquids shall be stored in an approved fireproof storage cabinet provided by the contractor. Contractors are responsible for proper off-base disposal of containers and hazardous material.
c. Prohibited Hazardous Materials. Prohibited materials include those that contain Class 1 ozone-depleting substances (including CFCs, halons, carbon tetrachloride, methyl chloroform and methyl bromide) per Air Force Policy and as regulated by Title VI of the Clean Air Act, specifically Sections 601-607. Other prohibited construction materials include lead (i.e. lead-based paint), asbestos, PCBs or other hazardous substances.
7.
MATERIALS REQUIRED FOR THIS PROJECT:
a. Carpet: Level loop with cushion back, Weight not less than 24 oz. / SY. 100 percent solution dyed nylon to withstand frequent chlorine cleaning solutions. Anti-microbial backing. Class I or II fire rating per ASTM E-648. Low formaldehyde and volatile organic compounds (VOCs) content meeting Government requirements.
b. Sheet vinyl flooring: Homogenous vinyl through-chip construction. Overall thickness 0.080 inches. Wear layer 0.050 inches, minimum. Class I or II fire rating per ASTM E-648.
c. Rubber base: Height four (4) inches with coved bottom.
d. Transition pieces, accessories, moldings, adhesives and incidentals: As best suited for the proposed usage. Adhesives must not emit toxic or offensive fumes.
e. Leveling and patching compound: As best suited for the proposed usage.
f. All colors and patterns will be approved by the Government.
8.
PREPARATION FOR WORK and REMOVAL OF EXISTING FLOORING
a. Verify dimensions, quantities and field conditions prior to ordering materials or starting work activities.
b. The building occupants will empty shelves and book cases. The Contractor shall move furniture, washers, dryers and other equipment as required to accomplish the work and shall replace and reconnect upon completion.
c. Remove all existing carpet, sheet vinyl flooring and associated resilient base throughout the entire building per an approved schedule that will allow for continued use of the building during the duration of this project.
d. Dispose of all removed materials at a DEQ-permitted landfill or other approved off-base location.
e. Repair holes, cracks, depressions, rough areas or other defects in substrates under flooring or behind wall base. Use materials suitable for the purpose intended. Scrape or grind raised areas and ridges to a smooth, level surface.
f. Sweep floor clean of all foreign materials before installation of flooring.
g. Remove, trim and reinstall any doors that touch carpet surface.
9.
FLOORING INSTALLATION
a. All work shall be performed by workmen skilled in the trades involved.
b. Install materials in strict accordance with the manufacturers’ printed instructions and details.
c. Install carpet and sheet vinyl flooring at same locations as removed materials. Refer to the original Floor Plans (Sheets A1.1 through A1.5) and Room Finish Schedule (Sheet A9.1), all dated March 1998, that show locations of the different types of flooring. On the drawings SVF denotes sheet vinyl flooring and CPT denotes carpet. The specific brands and colors called out thereon are NOT what will be used under the current contract.
d. Install carpet and flooring in a full spread of adhesive applied with notched trowel. Roll as recommended by manufacturer. Flooring shall be smooth, uniform and secure with a minimum of seams.
e. Run seams toward light where practical with carpet pile in the same direction and patterns accurately matched. Located seams at doorways centered directly under doors. Treat carpet seams with a seam adhesive. Seams in sheet vinyl flooring shall be heat welded.
f. Install rubber edge strips at all carpet edges that meet hard surface flooring. Trim edges at walls straight and true.
g. Install coved rubber base at all walls and cabinet toe spaces. Existing coved type bases integral with turn-up flooring are NOT to be duplicated in new work. Use top-set base only.
h. All work shall be left free of blemishes and defects.
i. Take measures to prevent traffic or any adverse usage while adhesive is drying.
10.
PROJECT CLEANUP
a. Remove all debris and surplus materials from work areas daily.
b. On completion of flooring in each room, leave surfaces in a clean, sanitary, odor-free, acceptable condition, ready for occupancy.
c. Remove any adhesive, soiled spots or stains using cleaning materials and procedures as recommended by the manufacturer of the surface being cleaned. Protect adjacent materials or surfaces that may be damaged by the cleaning materials or procedures.
d. Remove any protruding face yarn with sharp scissors. Vacuum carpet to remove all small debris, dust footprints, etc. Scraps smaller than 2' x 3' shall be removed. Pieces larger than 2' x 3' but less than 12' x 10' shall be rolled and tied and left in the building unless directed otherwise.
11.
ATTACHMENTS TO SOW:
· Composite Floor Plan, Sheet A1.1 - dated March 1998 (One 8-1/2” x 11” sheet)
· Floor Plans, Sheets A1.2 through A1.5 - dated March 1998 (Four 8-1/2” x 11” sheets)
· Room Finish Schedule, Sheet A9.1 - dated March 1998 (One 8-1/2” x 11” sheet)
END OF STATEMENT OF WORK
PAGE
REPLACE FLOORING IN CDC, BLDG. 465
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
File details come from the government source that posted it. Updated .