This is a Request for Quote (RFQ) for a Secondary Crash Network (SCN) upgrade for McGuire Airfield and a Primary Crash Network (PCN) and SCN upgrade for Lakehurst Maxfield Field. The contract is a firm-fixed-price, 100% small business set-aside under NAICS code 517810 with a $40 million size standard. The project requires engineering, furnishing, installation, and testing of a standalone voice-initiated mass notification system supporting up to 20 parties at McGuire Field and 30 parties at Lakehurst Maxfield Field.
Key details include a 90-day delivery timeline from contract award, with offers due by 1000 EST on August 25th via email to Shawna Dancel and Christina Vargas. Contractors must have an active System for Award Management (SAM) registration and submit a 10-page technical proposal and pricing documentation. The government will use a Lowest Price Technically Acceptable (LPTA) methodology for evaluation, with technical acceptability determined by meeting Statement of Work requirements. The contract will be awarded to the lowest-priced technically acceptable, responsible offeror, with the government reserving the right to conduct discussions if deemed necessary.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
WOMEN-OWNED SMALL
BUSINESS (WOSB)
SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL PRODUCTS AND COMMERCIAL SERVICES
1. REQUISITION NUMBER PAGE 1 OF
2. CONTRACT NUMBER 3. AWARD/EFFECTIVE
DATE
4. ORDER NUMBER 5. SOLICITATION NUMBER 6. SOLICITATION ISSUE
DATE
7. FOR SOLICITATION
INFORMATION CALL:
a. NAME b. TELEPHONE NUMBER (No collect calls)
8. OFFER DUE DATE/
LOCAL TIME
9. ISSUED BY
13b. RATING
14. METHOD OF SOLICITATION
CODE
15. DELIVER TO 16. ADMINISTERED BY CODE
18a. PAYMENT WILL BE MADE BY CODE17a. CONTRACTOR/
OFFEROR
CODE
FACILITY
CODE
CODE
TELEPHONE NUMBER
17b. CHECK IF REMITTANCE IS DIFFERENT AND PUT SUCH ADDRESS IN
OFFER
18b. SUBMIT INVOICES TO ADDRESS SHOWN IN BLOCK 18a UNLESS BLOCK
BELOW IS CHECKED
REQUEST
FOR QUOTE
(RFQ)
INVITATION
FOR BID
(IFB)
REQUEST
FOR
PROPOSAL
(RFP)
SEE ADDENDUM
19.
ITEM NUMBER
20.
SCHEDULE OF SUPPLIES/SERVICES
21.
QUANTITY
22.
UNIT
23.
UNIT PRICE
24.
AMOUNT
(Use Reverse and/or Attach Additional Sheets as Necessary)
25. ACCOUNTING AND APPROPRIATION DATA 26. TOTAL AWARD AMOUNT (For Government Use Only)
28. CONTRACTOR IS REQUIRED TO SIGN THIS DOCUMENT AND RETURN
COPIES TO ISSUING OFFICE. CONTRACTOR AGREES TO FURNISH
AND DELIVER ALL ITEMS SET FORTH OR OTHERWISE IDENTIFIED ABOVE AND
ON ANY ADDITIONAL SHEETS SUBJECT TO THE TERMS AND CONDITIONS
SPECIFIED
29. AWARD OF CONTRACT: REFERENCE OFFER
DATED . . YOUR OFFER ON SOLICITATION
(BLOCK 5), INCLUDING ANY ADDITIONS OR CHANGES WHICH ARE
SET FORTH HEREIN, IS ACCEPTED AS TO ITEMS:
30a. SIGNATURE OF OFFEROR/CONTRACTOR
30b. NAME AND TITLE OF SIGNER (Type or print) 30c. DATE SIGNED
31a. UNITED STATES OF AMERICA (SIGNATURE OF CONTRACTING OFFICER)
31b. NAME OF CONTRACTING OFFICER (Type or print) 31c. DATE SIGNED
AUTHORIZED FOR LOCAL REPRODUCTION
PREVIOUS EDITION IS NOT USABLE
STANDARD FORM 1449 (REV. 11/2021)
Prescribed by GSA - FAR (48 CFR) 53.212
10. THIS ACQUISITION IS UNRESTRICTED OR
NORTH AMERICAN
INDUSTRY CLASSIFICATION
STANDARD (NAICS):
SIZE STANDARD:
13a. THIS CONTRACT IS A
RATED ORDER UNDER
THE DEFENSE PRIORITIES
AND ALLOCATIONS
SYSTEM - DPAS (15 CFR 700)
SET ASIDE: % FOR:
11. DELIVERY FOR FREE ON
BOARD (FOB) DESTINATION
UNLESS BLOCK IS MARKED
SEE SCHEDULE
12. DISCOUNT TERMS
ARE ARE NOT ATTACHED
ARE ARE NOT ATTACHED
27a. SOLICITATION INCORPORATES BY REFERENCE (FEDERAL ACQUISITION REGULATION) FAR 52.212-1, 52.212-4. FAR 52.212-3
AND 52.212-5 ARE ATTACHED. ADDENDA
27b. CONTRACT/PURCHASE ORDER INCORPORATES BY REFERENCE FAR 52.212-4. FAR 52.212-5 IS ATTACHED. ADDENDA
8(A)
ECONOMICALLY
DISADVANTAGED
WOMEN-OWNED SMALL
BUSINESS (EDWOSB)
SERVICE-DISABLED
VETERAN-OWNED
SMALL BUSINESS
(SDVOSB)
HUBZONE SMALL
BUSINESS
SMALL BUSINESS
NOTE: OFFEROR TO COMPLETE BLOCKS 12, 17, 23, 24, AND 30.
Solicitation/Contract Form Crash Network
Product Service Code: 7G21
FA448425Q00440001
Supplies or Services & Prices or Costs Additional Information/Notes
Item Supplies / Services Quantity Unit Unit Price Amount
Secondary Crash Network (SCN) for McGuire Airfield Purchase with Installation and service.
Product Service Code: 7G21 Pricing Arrangement: Firm Fixed Price
1 Each
Primary Crash Network (PCN) and SCN upgrade for Lakehurst Maxfield Field Purchase with Installation and service.
Product Service Code: 7G21 Pricing Arrangement: Firm Fixed Price
1 Each
Description/Specifications/Statement of Work
Statement of Work (SOW):
Primary Crash Network (PCN) and Secondary Crash Network (SCN)
For McGuire Field and Lakehurst Maxfield Field
INTRODUCTION: This SOW defines the requirement for a Contractor to Engineer, Furnish, Install and Test(EFI&T) into service, a Secondary Crash Network (SCN) upgrade for McGuire Airfield and a Primary Crash Network (PCN) and Secondary Crash Network (SCN) upgrade for Lakehurst Maxfield Field. This upgrade shall provide a completely standalone voice-initiated and controlled mass notification system for up to 20 parties at McGuire Field and up to 30 parties at Lakehurst Maxfield Field, that directly support the multiple flying missions. All future references for Government Furnished Equipment shall be reflected as (GFE).
All locations are on Joint Base McGuire-Dix-Lakehurst.
1. PROJECT SCOPE:
The current PCN/SCN system is discontinued. The Contractor shall EFI&T all hardware and software to support:
- One Department of Defense (DoD) VoIP Emergency Notification System with 20 SIP sessions and a user interface console/GUI in Building 1758, and eight (8)additional Push-to-Talk (PTT) phones across the Joint Base.
- One DoD VoIP Emergency Notification System with 30 SIP sessions and a user interface console/GUI in Building 307, and 14 additional PTT phones across the Joint Base.
The systems must be compatible with the existing base transport and gateway infrastructure and use the currently installed PTT phones at additional locations.
1.1. This effort shall require the Contractor to EFI&T all PTT phones at each Initiator Console location. The remaining drop PTT phones shall be Contractor EFI&T.
1.2. Building and room numbers for each PTT phone will be provided by the Government per Contractor's requests. Note: Locations are subject to change based on mission requirements. These are provided for the Contractor to properly plan their install locations and required equipment. At each location, the Government shall provide space for the Contractor to EFI&T of all their equipment. This includes GFE 120VAC,60 Hz power with a standard US electrical outlet.
1.3. Before installing equipment in any cabinet, the Contractor is responsible for coordinating with Government representatives that the cabinet is properly grounded. If it is not, the Government shall take all required actions to ground the cabinet properly.
1.4. The Contractor shall EFI&T all materials, and perform all work to include making all crossconnection assignments and changes required to complete requirements as specified in this SOW. The Contractor shall provide a List of Materials (LOM) to include all equipment to be installed. The Contractor shall coordinate all installations through 305th and the Government Representative (GR).
1.5. It is the Contractor's responsibility to test all associated equipment, fiber modems/switches, UPSes, blocks, and cables to ensure that they meet all standards and requirements. The Contractor shall correct any deficiencies and provide the GR all testing results. The Contractor shall provide an end-to- end test on all circuits to ensure that there is minimal interference and correct functionality.
1.6. All Contractor EFI&T equipment shall be manufactured by the approved National Defense Authorization Act (NDAA) companies.
2.0. PROJECT SUPPORT REQUIREMENTS:
2.1. Project Requirement: For the areas identified above, the Contractor shall provide all management, personnel, equipment, tools, transportation, supplies, materials, supervision, and other incidentals necessary to
EFI&T McGuire Field SCN and Lakehurst Field PCN and SCN. All materials provided shall be new and not refurbished.
2.2. Base Support Requirements: The Contractor shall identify any base support requirements (for example, laydown and storage areas) necessary to complete this project.
2.2.1. The 305 OSS will assign a GR for both McGuire and Lakehurst. The Contractor shall coordinate all efforts with the GR. The GR shall process all Contractor efforts and requests with the Contracting Officer and appropriate base personnel.
2.2.1.1. The 305 OSS appointed GR's will coordinate with 87 CS on all installation requirements once POC's for installation are provided.
2.2.2. The Government shall provide approximately 100' square feet of secure and dry storage space for Contractor materials at McGuire Field and Lakehurst Maxfield Field. The Contractor shall be responsible for loading, unloading, unpacking and transportation of all Contractor provided materials, test equipment, training documentation, etc. at both locations. The Contractor shall be responsible for disposal of all packing materials and unused installation materials. If the GR concurs, the Contractor may turn these items over to the Government for use/disposal at no compensation to the Contractor. If the GR does not agree, the Contractor shall properly dispose of these items IAW the local Governments' environmental practices.
2.2.3. Shipping Address for project materials to McGuire Field is: 305 OSS/OSAA 1758 Vandenberg Ave JB
MDL, NJ08641
The Contractor shall send an email 5 days prior to shipment. The Contractor shall include tracking information within the email. The Contractor is responsible for acceptance of materials upon arrival. The Government shall not be responsible for items lost or damaged during shipment.
2.2.4. Shipping Address for project materials to Lakehurst Maxfield Field is: 305OSS/OSAA Bldg 307 Highway 547 Lakehurst, NJ 08733
The Contractor shall send an email 5 days prior to shipment. The Contractor shall include tracking information within the email. The Contractor is responsible for acceptance of materials upon arrival. The Government shall not be responsible for items lost or damaged during shipment.
2.2.5. Stated work and associated products shall be performed at the UNCLASSIFIED level. However, some of this work will take place in secure areas where Contractor employees must be always escorted. The Contractor must coordinate access to secure areas at least three (3) working days ahead of time. It is the Government's responsibility to provide escorts. Contractor personnel, while under escort in restricted areas, shall always obey the direction and orders of their escorts. During any time of an emergency, the Contractor personnel shall be directed to vacate the area(s) and return later without additional costs to be incurred by the Government.
2.3. Restoration: The Contractor shall restore all disturbed property to the "as found" condition or better after installation. The Contractor shall comply with Base Grounds Restoration requirements.
2.4. Project Residue: The Contractor shall dispose all residues from this project off base and In Accordance With (IAW) Federal, local, and base environmental laws, and regulations. See 2.2.2 above.
2.5. Fire Suppression: Any wall penetrations shall use adequate fire blocking to meet or exceed the current standard in place.
2.6. Excavation/Building Penetrations: All wall penetrations, including inside buildings, shall be restored to meet the required base fire ratings.
2.7. Labeling: The Contractor shall label all equipment and cables they install in accordance with ANSI/TIA/ EIA-606-A-2002 and as directed by the GR.
2.8. Redline Drawings: The Government shall provide building floor plans and scaled Joint Base McGuire-Dix- Lakehurst Base Maps to the Contractor, after contract award. The Contractor shall provide updated As Builts drawings at project completion (CDRL A001).
2.9. Outages: The Contractor shall be responsible for preventing any unscheduled outages (i.e. cutting or disabling any in-service cables or equipment). Contractor-caused, interruptions of communications capabilities shall be immediately identified to the GR. Such outages shall be Contractor worked non-stop until corrected, entirely at the Contractor's expense. The Contractor shall coordinate planned outages with the GR at least 10 calendar days in advance of the outage if the implementation necessitates disruption of service, (e.g., communications, electrical, or other utilities).
2.10. Hours of Operation: The Contractor shall perform the services required under this contract during normal duty hours 0730-1630, Mon-Fri of the facility where work is being performed. Any other work schedule outside of normal duty hours requires GR approval. Part or all of any facility may be occupied during this effort.
Contractor shall accomplish the installation with minimum disruption of daily office activities. If performance of work outside normal duty hours will be required to meet the scheduled dates stated above, include desired working hours in the Contractor's Proposal.
2.11. Holidays/Down Days: The Contractor shall not perform work under this contract on US Federal holidays or site-unique down-days unless expressly authorized by the GR.
2.12. Final Acceptance: The Contractor shall schedule a final project walk-through with the GR. This should be scheduled at least 2 calendar days prior to acceptance. Final acceptance will be when the GR signs off on the AFTO Form 747, thereby indicating Government Acceptance.
2.13. All Contractor cables shall be supported every 18 inches by Contractor EFI&T tie wraps, Velcro straps, conduit, raceway, and/or J Hooks. The Government shall provide analog, and fiber cross connection cut sheets and participate in all cross connections with the Contractor.
3.0. The Contractor shall EFI&T the PCN and SCN systems as defined COMMODITY REQUIREMENTS:
herein.
3.1. PTT Drops: The Contractor shall test the GFE PTT phones at the locations provided by the GR.
3.2. Contractor Furnished (CF) Materials and Network Specific Warranty: The Contractor shall furnish all materials for this project except as identified. The Contractor shall supply Commercial-Off-the-Shelf (COTS) end-item system components required for contract performance wherever possible. The Contractor shall identify all materials or equipment required for the project in their Proposal. The Contractor shall list the manufacturer and part number of the proposed material in the Proposal. Unless otherwise specified, the Contractor shall provide copies of existing COTS technical or equipment manuals and warranty documentation and procedures for Contractor-furnished end-item system equipment maintenance. The Contractor shall identify and conduct system familiarization for Government personnel to ensure proper operation and maintenance of the system(s). See paragraph 5.5.
3.3. Physical Inspection: The physical inspection consists of the Contractor performing a physical inspection of each location where installation is required. At each location, the Contractor shall verify the specified placement of the equipment to ensure the installation shall meet required safety standards. The Contractor shall verify that each location shall have proper rack space, proper mounting of equipment, rack grounding, and proper primary power. An installation test report IAW CDRL A005 shall be provided after physical inspection is completed.
Results shall comply before component validation and operational tests are run.
3.4. Component Validation: The Contractor shall perform component validation by testing all the individual Contractor EFI&T PCN and SCN Hardware and Software, cables, and other related equipment to ensure they are working correctly. The Contractor shall test components prior to assembly and installation before continuing too Operational Test. An installation test report IAW CDRL A005 shall be provided after component validation is completed.
3.5. Operations Test: The operations test shall consist of testing the newly installed equipment. This shall be the real world test to ensure functionality of the new installation and equipment related to this project. An installation test report IAW CDRL A005 shall be provided after operational test is completed.
3.6. Grounding and Bonding: The Contractor EFI&T equipment shall be grounded and bonded to the building ground. All grounding and bonding shall follow J-STD-607-A.
3.7. The Contractor shall EFI&T 2 each Operations and Maintenance (O&M) compact disks for the Government to access the core equipment. The Contractor shall turn these disks over to the GR.
4.0. MANAGEMENT:
4.1. Schedule: The Contractor shall provide a complete milestone schedule that denotes major activities to include time-phased start and completion dates for this project and sub-projects associated with the installation of the components and systems. (CDRL A002).
4.2. In-Brief: The Contractor shall conduct an in-brief with the GR or designated representative and other site personnel before the start of site survey or implementation. The in-brief shall familiarize the customer with the purpose of the Contractor's visit and coordinate the project schedule (e.g., arrange for required escorts; QAP schedule; etc.).
4.3. Project Manager or Site Point of Contact (POC) on Site. The Contractor shall designate the Contractor's on-site team leader and alternate(s) as the Site POC for this project in their Access Request Letter. They shall oversee all facets of the project. The Site POC or alternate(s) shall be on site during duty hours until project completion. The Site POC shall be the interface for all work site communications with the Government, including quality, safety, and discrepancy matters.
4.4. Quality Assurance (QA): The Contractor shall provide quality assurance support for the entire life of the project. This support shall assist the Government representative in performing random spot checks and in performing the system acceptance tests. Contractor QA shall be responsible for identifying deficiencies and/or discrepancies throughout the life of the project to the GR. A weekly report (soft copy) will be submitted indicating project progress/statuses and listings any deficiencies/discrepancies found and actions to correct them. (CDRL A003).
4.5. Compliance: The Contractor shall remain in compliance with all Federal, State, and base security and safety laws, regulations, policies, and requirements.
4.6. Clean up: At day's end, the installer shall remove all debris and surplus materials from the workplace.
Equipment and materials required to complete the work effort may remain on site if they are organized/stored in a manner that does not cause a safety hazard.
4.7. Environmental Management: The Contractor shall comply with the most stringent environmental Federal, and local laws and regulations. and Air Force policies, instructions, and plans. The Federal Government is not exempt from compliance with environmental regulations. The Contractor shall maintain an awareness of changing environmental regulatory requirements to avoid environmental deficiencies for activities on the Joint Base. The Prime Contractor shall ensure their sub-Contractors (if any) comply with these specifications.
4.8. Walk-Through: The Contractor shall schedule a final project walk-through of all work completed prior to close out, with the GR. This should be scheduled at least 72 hours prior to the event.
4.9. Personnel Requirements: The Contractor's technical team shall be Certified to EFI&T equipment and fiber modems/switches. In their proposal, the Contractor shall confirm their personnel have the required certifications.
4.10. Base Access: The Contractor shall coordinate with the site GR to obtain base access for both McGuire Field and Lakehurst Maxfield Field. The Contractor shall process and provide a site Access Request letter, to the GR, within 5 calendar days after contract award. This Access Request letter shall identify the names (as shown on the individual's Passport or Real ID), Passport or driver's license numbers, the state of issue, birth date, and citizenship of the personnel who will be performing work under this SOW. It shall also include the company name, address, phone number, contract number, project start date and end date. If required by the GR, the Contractor shall provide identification badges for their employees. All Contractor personnel shall wear these badges while on duty on the Government site. The badges shall identify the individual, company name, and be clearly and distinctly marked as Contractor and be IAW Joint Base regulations.
5. DELIVERABLES:
5.1. List of Deliverables: All deliverables are subject to Government acceptance and approval. They shall meet professional standards and the requirements set forth in this SOW. All deliverables shall be produced using recommended software tools/versions as accepted by the Government. The Contractor shall submit the following deliverables:
CDRL Data Item Title
A001 As Built
A002 Installation Plan
A003 Training Materials
A004 Reserved
A005 Test Report
A006 Cutover Plan
5.2. Cutover Plan: The Contractor shall provide a detailed cutover plan IAW CDRL A006 to delineate how the transition shall be implemented. This plan should outline how the system shall be placed into service and clearly specify how the newly installed systems shall connect to the existing base systems IAW CDRL A006.
5.3. Acceptance Test Plan: The Contractor shall provide a detailed acceptance test plan of the installation covering all aspects of the installation and demonstrate the acceptability of the work on meeting the Government's requirements. The Contractor shall perform all tests and document results of tests with Government's witnesses overseeing the Acceptance testing IAW CDRLs A005 and A006.
5.4. As-Built Drawings: The Contractor shall provide as-built drawings for the installed equipment to include where and how they connect/interface with each other and existing base systems IAWCDRL A001.
5.5. Training: The Contractor shall provide operational hands-on training for 6 Government Personnel. The Contractor shall provide all training materials (slides, Technical Documents, Manuals, etc.) IAW CDRL A003.
The training shall cover complete capabilities of the equipment. The training shall also provide Operations and Maintenance training for the complete system so Government personnel shall be capable of adequately maintaining and providing future additional voice interfaces. This includes complete training for utilizing the Alert III Core Operations and Maintenance Compact Disk with a GFE Laptop. The GR shall arrange a training space for the trainees and Contractor trainer.
5.6. Testing Requirements: The Contractor shall perform testing and inspections of all solutions to ensure the technical adequacy and accuracy of all work, including reports and other documents required in support of that work. The Contractor shall conduct on-site testing in accordance with the procedures. The Contractor shall provide a detailed test plan IAW CDRL A006.
5.6.1. When any system, subsystem, component, or requirement test fails to meet the requirements of the test, Government acceptance shall be withheld until such time as the cause of the failure is corrected to the Government's satisfaction.
5.6.2. After appropriate corrective action has been taken, all tests including those previously completed related to the failed test and the corrective action shall be repeated and successfully completed prior to Government acceptance. Pre-cutover audits shall consist of verification of all testing completed by the Contractor such that the system is deemed ready for functional cutover. As part of this audit, any engineered changes, or approved waivers applicable to the installation shall be reviewed and agreed upon between the Contractor and the GR.
Post-cutover audits shall verify that all post-cutover acceptance testing has been performed satisfactorily in accordance with the standard practices and identify those tests, if any which have not been successfully completed and shall be re-tested prior to acceptance. The Contractor shall do all testing in accordance with the acceptance test plan mentioned above. The Contractor shall provide a logical test process that minimizes interruptions and avoids sustained downtime and presents a contingency procedure to be implemented in the event of systems failure during testing.
5.6.3. The Contractor shall furnish all test equipment and personnel required to conduct all required testing.
The Contractor shall document all test results in an installation test report IAWCDRL A005. During the testing phase, the Government reserves the right to perform any of the Contractor performed inspections and tests to assure solutions conform to prescribed requirements. The Contractor shall provide on-site support during the acceptance testing. The Test Report(s) shall be provided to the Government no later than 10 days after test(s) have been completed.
5.7. System Acceptance: Acceptance of the SCN shall be dependent upon successful completion and documentation of tests in the Contractor submitted/Government approved test plan IAW CDRL A006 and test report CDRL A005. Screen shots (if applicable) shall serve to document successful test results.
6.0 WARRANTY:
The Contractor shall provide a one-year warranty or manufacturer's standard commercial warranty, whichever is longer. The Contractor shall also provide a one-year workmanship warranty. The warranty period shall start from the date of system and/or project acceptance. The Contractor shall provide hardware replacement, major and minor software upgrades for one year for all equipment. The Contractor shall transfer warranties to the Government.
7.0 PERFORMANCE:
7.1. Period of Performance. The Contractor shall have 90 days from contract award to complete all facets of the project including final walk thru with the Government representative.
7.2. Place of Performance. The place of performance is at Joint Base McGuire-Dix-Lakehurst.
8.0 GOVERNMENT FURNISHED INFORMATIONAND STANDARDS:
The Contractor shall comply with all base installation standards. The Contractor shall comply with all commercial code sand standards where applicable in the performance of this contract. It is the Contractor's responsibility to identify and obtain applicable standards and best commercial practice documentation. Should a conflict arise between this SOW and any commercial standard referenced, the Contractor shall make the Government aware of the conflict. The Government shall determine which standard applies.
9.0 SAFETY:
The Contractor shall be responsible for complying with all Federal, State, and Base safety guidelines.
9.1. Accident/Incident Reporting and Investigation: The Contractor shall record and report all available facts relating to each instance of accidental damage to Government property or injury to either Contractor or Government personnel to the Base Safety Office and GR. The Contractor shall secure the scene of any accident and wreckage until released by the accident investigative authority through the Contracting Officer. If the Government elects to investigate the incident, the Contractor shall cooperate fully and assist the Government personnel until the investigation is completed.
9.2. Potential Problems: The Contractor shall determine any potential problems with the projected work in areas that may contain asbestos, hazardous materials, and hazardous wastes and local procedures to be followed in the event such problems are encountered.
9.3. Disposal/Reporting: The Contractor shall comply with Federal, State, and Base procedures concerning the use, disposal, or reporting of hazardous materials.
9.4. Hazardous Material Identification: The Contractor shall submit Safety Data Sheets (SDS) for any hazardous materials (paints, solvents, cleaners, encapsulating compound, etc.) to be used in performance of the contract. The Contractor shall file the SDS(s) with the Base Environmental Management Office prior to using hazardous material. The GR may assist with this effort.
9.5. Identification / Marking: The Contractor shall clearly mark all Contractor Furnished Packaging (CFP) with their company's name, contract number, and project number. The Contractor shall place an easily read, very visible, sign (minimum 8.5" x 11") on large containers, construction equipment, or un-manned rental vehicles while on the Government installation indicating the company name; contract/task order number; project title;
and both the Contractor and Site POC's names and local telephone numbers.
9.6. Project Equipment: The Contractor shall provide equipment (e.g., man lifts, etc.) required to support implementation. The Contractor shall be responsible for transportation of project materials and equipment to/ from the work site, as well as their security.
9.7. Transportation and Storage of Material/Equipment: The Contractor shall transport and store all Contractor Furnished Materials (CFM) and Contractor Furnished Equipment (CFE) required for completion of the contract requirements.
9.8. Security
9.8.1 Contractor employees shall comply with Joint Base security requirements imposed by the Installation Commander at all times while on Joint Base premises. The contractor shall obtain all necessary passes, decals, badges, or other items required for access to perform contract services at Joint Base MDL. The contractor is responsible for accountability of all such media, which shall be surrendered to the Security Forces Squadron Pass and Registration Section upon completion or termination of the contract, or upon termination of an individual's employment for the contractor, or at the written discretion of the Contracting Officer (CO). The contractor shall comply with all Joint Base MDL policies regarding entry to the installation, rules of the road, contingency operations compliance, and photography prohibitions. Contractor employees are authorized entry to the installation for the purpose of work under this contract only, and are not authorized in other facilities or areas without prior government authorization. Due to safety/security requirements, contractor personnel shall be required to fluently speak, comprehend, read, and write English. U.S. citizens only.
9.8.2 Base Access. The contractor must be aware that entry requirements are subject to change due to installation and world situations. All employees will be subject to a background check for base access.
9.8.3 Main Base Access. Current security access restrictions require all contractor vehicles (which are the size of a standard bread delivery truck or larger or towing a trailer) to enter through the Commercial Gate only.
Contractor vehicles may be subject to search prior to gaining base entry. The contractor should plan and allow for delays as a result of increased and ever-changing security procedures.
9.8.4 Project POC Information.
Requirements This requirement is for a Contractor to Engineer, Furnish, Install and Test (EFI and T) into service, a Secondary Crash Network (SCN) upgrade for McGuire Airfield and a Primary Crash Network (PCN) and Secondary Crash Network (SCN) upgrade for Lakehurst Maxfield Field. This upgrade shall provide a completely standalone voice initiated and controlled mass notification system for up to 20 parties at McGuire Field and up to 30 parties at Lakehurst Maxfield Field, that directly support the multiple flying missions. All future references to Government Furnished Equipment shall be reflected as (GFE). All locations are on Joint Base McGuire- Dix-Lakehurst.
Packaging and Marking
Inspection and Acceptance Overall Contract Inspection/Acceptance Locations
Inspection and Acceptance Location
Both Other Instructions: See Statement of Work (SOW) for Acceptance/inspection criteria.
DoDAAC: F3A11C CountryCode: USA
305 OSS CC
AF BPN NO MILSBILLS PROCESSES, 1730 VANDENBERG AVE
MC GUIRE AFB, NJ 08641-5013
UNITED STATES
Inspection and Acceptance Location
Both Other Instructions: See Statement of Work (SOW) for Acceptance/inspection criteria.
DoDAAC: F3A11C CountryCode: USA
305 OSS CC
AF BPN NO MILSBILLS PROCESSES, 1730 VANDENBERG AVE
MC GUIRE AFB, NJ 08641-5013
UNITED STATES
Deliveries or Performance
Line Item Delivery Schedule Quantity Address and POC Special Handling/Notes
Delivery Schedule From date of lead time event to completion of performance 90 Calendar Days Date of Award
1 Each Ship To DoDAAC: F3A11C CountryCode: USA
305 OSS CC
AF BPN NO MILSBILLS PROCESSES, 1730
VANDENBERG AVE
MC GUIRE AFB, NJ 08641-5013
UNITED STATES
FoB Details Contractor Destination
Additional Descriptive Data:
CLIN 0001 - Shipping Address for Project Materials to McGuire Field is: 305 OSS/OSAA 1758 Vandenberg Ave JB MDL,NJ 08641
Delivery Schedule From date of lead time event to completion of performance 90 Calendar Days Date of Award
1 Each Ship To DoDAAC: F3A11C CountryCode: USA
305 OSS CC
AF BPN NO MILSBILLS PROCESSES, 1730
VANDENBERG AVE
MC GUIRE AFB, NJ 08641-5013
UNITED STATES
FoB Details Contractor Destination
Additional Descriptive Data:
CLIN 0002 - Shipping Address for Project Materials to Lakehurst Maxfield Field is: 305 OSS/OSAA Bldg 307 Highway 547 Lakehurst, NJ 08733
Contract Administration Data
DFARS Clauses Incorporated by Reference
Number Title Effective Date
Alternate/ Deviation
Variation Effective Date
252.232-7003 Electronic Submission of Payment Requests and Receiving Reports. Dec 2018
DFARS Clauses Incorporated by Full Text
252.232-7006 Wide Area WorkFlow Payment Instructions. (Jan 2023)
As prescribed in 232.7004(b), use the following clause:
WIDE AREA WORKFLOW PAYMENT INSTRUCTIONS (JAN 2023)
(a) As used in this clause- Definitions.
"Department of Defense Activity Address Code (DoDAAC)" is a six position code that uniquely identifies a unit, activity, or organization.
"Document type" means the type of payment request or receiving report available for creation in Wide Area WorkFlow (WAWF).
"Local processing office (LPO)" is the office responsible for payment certification when payment certification is done external to the entitlement system.
"Payment request" and "receiving report" are defined in the clause at 252.232-7003, Electronic Submission of Payment Requests and Receiving Reports.
(b) The WAWF system provides the method to electronically process vendor payment requests and receiving reports, as authorized by Electronic invoicing.
Defense Federal Acquisition Regulation Supplement (DFARS) 252.232-7003, Electronic Submission of Payment Requests and Receiving Reports.
(c) To access WAWF, the Contractor shall- WAWF access.
(1) Have a designated electronic business point of contact in the System for Award Management at https://www.sam.gov; and
(2) Be registered to use WAWF at https://wawf.eb.mil/ following the step-by-step procedures for self-registration available at this web site.
(d) The Contractor should follow the training instructions of the WAWF Web-Based Training Course and use the Practice Training Site before WAWF training.
submitting payment requests through WAWF. Both can be accessed by selecting the "Web Based Training" link on the WAWF home page at https://wawf.eb.mil/
(e) Document submissions may be via web entry, Electronic Data Interchange, or File Transfer Protocol. WAWF methods of document submission.
(f) The Contractor shall use the following information when submitting payment requests and receiving reports in WAWF for this WAWF payment instructions.
contract or task or delivery order:
(1) The Contractor shall submit payment requests using the following document type(s): Document type.
(i) For cost-type line items, including labor-hour or time-and-materials, submit a cost voucher.
(ii) For fixed price line items-
(A) That require shipment of a deliverable, submit the invoice and receiving report specified by the Contracting Officer.
_Combo__
(Contracting Officer: Insert applicable invoice and receiving report document type(s) for fixed price line items that require shipment of a deliverable.)
(B) For services that do not require shipment of a deliverable, submit either the Invoice 2in1, which meets the requirements for the invoice and receiving report, or the applicable invoice and receiving report, as specified by the Contracting Officer.
N/A_
(iii) For customary progress payments based on costs incurred, submit a progress payment request.
(iv) For performance based payments, submit a performance based payment request.
(v) For commercial financing, submit a commercial financing request.
(2) ) Fast Pay requests are only permitted when Federal Acquisition Regulation (FAR) 52.213-1 is included in the contract.
[Note: The Contractor may use a WAWF "combo" document type to create some combinations of invoice and receiving report in one step.]
(3) The Contractor shall use the information in the Routing Data Table below only to fill in applicable fields in WAWF when creating Document routing.
payment requests and receiving reports in the system.
Routing Data Table*
Field Name in WAWF Data to be entered in WAWF
Pay Official DoDAAC F87700
Issue By DoDAAC FA4484
Admin DoDAAC FA4484
Inspect By DoDAAC F3A11C
Ship To Code F3A11C
Ship From Code _N/A_
Mark For Code _N/A_
Service Approver (DoDAAC) _N/A_
Service Acceptor (DoDAAC) _N/A_
Accept at Other DoDAAC _N/A_
LPO DoDAAC _N/A_
DCAA Auditor DoDAAC _N/A_
Other DoDAAC(s) _N/A_
(4) The Contractor shall ensure a payment request includes documentation appropriate to the type of payment request in accordance Payment request.
with the payment clause, contract financing clause, or Federal Acquisition Regulation 52.216-7, Allowable Cost and Payment, as applicable.
(5) The Contractor shall ensure a receiving report meets the requirements of DFARS Appendix F. Receiving report.
(g) WAWF point of contact.
(1) The Contractor may obtain clarification regarding invoicing in WAWF from the following contracting activity's WAWF point of contact.
Samuel Dutton @ samual.dutton.2@us.af.mil____
(2) Contact the WAWF helpdesk at 866-618-5988, if assistance is needed.
(End of clause)
Special Contract Requirements
Contract Clauses
FAR Clauses Incorporated by Reference
Number Title Effective Date
Alternate/ Deviation
Variation Effective Date
52.204-13 System for Award Management Maintenance. Oct 2018 52.204-18 Commercial and Government Entity Code Maintenance. Aug 2020 52.212-4 Contract Terms and Conditions-Commercial Products and Commercial Services. Nov 2023 52.223-23 Sustainable Products and Services. (DEVIATION 2025-O0004) May 2024 Deviation 2025-O0004 Mar 2025
DFARS Clauses Incorporated by Reference
Number Title Effective Date
Alternate/ Deviation
Variation Effective Date
252.203-7000 Requirements Relating to Compensation of Former DoD Officials. Sep 2011 252.203-7002 Requirement to Inform Employees of Whistleblower Rights. Dec 2022 252.204-7003 Control of Government Personnel Work Product. Apr 1992 252.204-7018 Prohibition on the Acquisition of Covered Defense Telecommunications Equipment or Services. Jan 2023 252.211-7008 Use of Government-Assigned Serial Numbers. Sep 2010 252.223-7006 Prohibition on Storage, Treatment, and Disposal of Toxic or Hazardous Materials. Sep 2014 252.223-7008 Prohibition of Hexavalent Chromium. Jan 2023 252.225-7001 Buy American and Balance of Payments Program. Feb 2024 252.225-7002 Qualifying Country Sources as Subcontractors. Mar 2022 252.225-7012 Preference for Certain Domestic Commodities. Apr 2022 252.225-7048 Export-Controlled Items. Jun 2013 252.225-7056 Prohibition Regarding Business Operations with the Maduro Regime. Jan 2023 252.225-7060 Prohibition on Certain Procurements from the Xinjiang Uyghur Autonomous Region. Jun 2023 252.232-7010 Levies on Contract Payments. Dec 2006 252.244-7000 Subcontracts for Commercial Products or Commercial Services. Nov 2023 252.247-7023 Transportation of Supplies by Sea. Oct 2024
FAR Clauses Incorporated by Full Text
52.212-5 Contract Terms and Conditions Required to Implement Statutes or Executive Orders
- Commercial Products and Commercial Services. (DEVIATION 2025-O0003 and 2025-O0004)
(Jan 2025) Deviation 2025-O0004 (Mar 2025)
Contract Terms and Conditions Required To Implement Statutes or Executive Orders-Commercial Products and Commercial Services (MAR 2025) (DEVIATION 2025-O0003 and 2025-O0004)
(a) The Contractor shall comply with the following Federal Acquisition Regulation (FAR) clauses, which are incorporated in this contract by reference, to implement provisions of law or Executive orders applicable to acquisitions of commercial products and commercial services:
(1) 52.203-19, Prohibition on Requiring Certain Internal Confidentiality Agreements or Statements (section 743 of Division E, Title VII, of the (Jan 2017) Consolidated and Further Continuing Appropriations Act, 2015 (Pub. L. 113-235) and its successor provisions in subsequent appropriations acts (and as extended in continuing resolutions)).
(2) 52.204-23, Prohibition on Contracting for Hardware, Software, and Services Developed or Provided by Kaspersky Lab Covered Entities (Section (Dec 2023) 1634 of Pub. L. 115-91).
(3) 52.204-25, Prohibition on Contracting for Certain Telecommunications and Video Surveillance Services or Equipment. (Section 889(a)(1)(A) of Pub. (Nov 2021) L. 115-232).
(4) 52.209-10, Prohibition on Contracting with Inverted Domestic Corporations .(Nov 2015)
(5) 52.232-40, Providing Accelerated Payments to Small Business Subcontractors (31 U.S.C. 3903 and 10 U.S.C. 3801).(Mar 2023)
(6) 52.233-3, Protest After Award (31 U.S.C. 3553).(Aug 1996)
(7) 52.233-4, Applicable Law for Breach of Contract Claim (Public Laws 108-77 and 108-78 ( 19 U.S.C. 3805 note)).(Oct 2004)
(b) The Contractor shall comply with the FAR clauses in this paragraph (b) that the Contracting Officer has indicated as being incorporated in this contract by reference to implement provisions of law or Executive orders applicable to acquisitions of commercial products and commercial services:
52.203-6, Restrictions on Subcontractor Sales to the Government with (41 U.S.C. 4704 and 10 U.S.C. 4655).(1) (Jun 2020), Alternate I (Nov 2021)
(2) 52.203-13, Contractor Code of Business Ethics and Conduct (41 U.S.C. 3509)).(Nov 2021)
(3) 52.203-15, Whistleblower Protections under the American Recovery and Reinvestment Act of 2009 (Section 1553 of Pub. L. 111-5). (Applies to (Jun 2010) contracts funded by the American Recovery and Reinvestment Act of 2009.)
52.203-17, Contractor Employee Whistleblower Rights (41 U.S.C. 4712); this clause does not apply to contracts of DoD, NASA, the Coast Guard, or (4) (Nov 2023) applicable elements of the intelligence community-see FAR 3.900(a).
52.204-10, Reporting Executive Compensation and First-Tier Subcontract Awards (Pub. L. 109-282) ( 31 U.S.C. 6101 note).(5) (Jun 2020)
[Reserved].(6)
52.204-14, Service Contract Reporting Requirements (Pub. L. 111-117, section 743 of Div. C).(7) (Oct 2016)
52.204-15, Service Contract Reporting Requirements for Indefinite-Delivery Contracts (Pub. L. 111-117, section 743 of Div. C).(8) (Oct 2016)
52.204-27, Prohibition on a ByteDance Covered Application (Section 102 of Division R of Pub. L. 117-328).[X] (9) (Jun 2023)
52.204-28, Federal Acquisition Supply Chain Security Act Orders-Federal Supply Schedules, Governmentwide Acquisition Contracts, and Multi-Agency (10) Contracts. (Pub. L. 115-390, title II).(Dec 2023)
(11)
(i) 52.204-30, Federal Acquisition Supply Chain Security Act Orders-Prohibition. (Pub. L. 115-390, title II).(Dec 2023)
Alternate I of 52.204-30.(ii) (Dec 2023)
(12) 52.209-6, Protecting the Government's Interest When Subcontracting With Contractors Debarred, Suspended, Proposed for Debarment, or Voluntarily Excluded. ( 2025) (31 U.S.C. 6101 note).Jan
52.209-9, Updates of Publicly Available Information Regarding Responsibility Matters (41 U.S.C. 2313).(13) (Oct 2018)
[Reserved].(14)
52.219-3, Notice of HUBZone Set-Aside or Sole-Source Award ( ) (15 U.S.C. 657a).(15) Oct 2022
52.219-4, Notice of Price Evaluation Preference for HUBZone Small Business Concerns ( ) (if the offeror elects to waive the preference, it shall so (16) Oct 2022 indicate in its offer) (15 U.S.C. 657a).
[Reserved](17)
[X] (18)
(i) 52.219-6, Notice of Total Small Business Set-Aside (15 U.S.C. 644).(Nov 2020)
Alternate I of 52.219-6.(ii) (Mar 2020)
(19)
(i) 52.219-7, Notice of Partial Small Business Set-Aside (15 U.S.C. 644).(Nov 2020)
Alternate I of 52.219-7.(ii) (Mar 2020)
52.219-8, Utilization of Small Business Concerns (15 U.S.C. 637(d)(2) and (3)).(20) ( )Jan 2025
(21)
(i) 52.219-9, Small Business Subcontracting Plan (15 U.S.C. 637(d)(4)).( )Jan 2025
Alternate I of 52.219-9.(ii) (Nov 2016)
Alternate II of 52.219-9.(iii) (Nov 2016)
Alternate III of 52.219-9.(iv) (Jun 2020)
Alternate IV of 52.219-9.(v) ( )Jan 2025
[X] (22)
(i) 52.219-13, Notice of Set-Aside of Orders (15 U.S.C. 644(r)).(Mar 2020)
Alternate I of 52.219-13.(ii) (Mar 2020)
52.219-14, Limitations on Subcontracting ( ) (15 U.S.C. 657s).(23) Oct 2022
52.219-16, Liquidated Damages-Subcontracting Plan (15 U.S.C. 637(d)(4)(F)(i)).(24) (Sep 2021)
52.219-27, Notice of Set-Aside for, or Sole-Source Award to, Service-Disabled Veteran-Owned Small Business (SDVOSB) Concerns Eligible Under the (25) SDVOSB Program ( ) (15 U.S.C. 657f).Feb 2024
[X] (26)
(i) 52.219-28, Small Business Program Rerepresentation (15 U.S.C. 632(a)(2)).Postaward ( )Jan 2025
Alternate I of 52.219-28.(ii) (Mar 2020)
52.219-29, Notice of Set-Aside for, or Sole-Source Award to, Economically Disadvantaged Women-Owned Small Business Concerns ( ) (27) Oct 2022 (15 U.S.C. 637(m)).
52.219-30, Notice of Set-Aside for, or Sole-Source Award to, Women-Owned Small Business Concerns Eligible Under the Women-Owned Small Business (28) Program ( ) (15 U.S.C. 637(m)).Oct 2022
52.219-32, Orders Issued Directly Under Small Business Reserves (15 U.S.C. 644(r)).(29) (Mar 2020)
52.219-33, Nonmanufacturer Rule (15 U.S.C. 637(a)(17)).(30) (Sep 2021)
52.222-3, Convict Labor (E.O.11755).[X] (31) (Jun 2003)
[X] (32) 52.222-19, Child Labor-Cooperation with Authorities and Remedies (E.O. 13126).(Jan 2025)
[Reserved](33)
[Reserved](34)
(35)
(i) 52.222-35, Equal Opportunity for Veterans (38 U.S.C. 4212).(Jun 2020)
Alternate I of 52.222-35.(ii) (Jul 2014)
(36)
(i) 52.222-36, Equal Opportunity for Workers with Disabilities (29 U.S.C. 793).(Jun 2020)
Alternate I of 52.222-36.(ii) (Jul 2014)
52.222-37, Employment Reports on Veterans ( ) (38 U.S.C. 4212).(37) Jun 2020
52.222-40, Notification of Employee Rights Under the National Labor Relations Act (E.O. 13496).(38) (Dec 2010)
[X] (39)
(i) 52.222-50, Combating Trafficking in Persons (22 U.S.C. chapter 78 and E.O. 13627).(Nov 2021)
Alternate I of 52.222-50 (22 U.S.C. chapter 78 and E.O. 13627).(ii) (Mar 2015)
(40) 52.222-54, Employment Eligibility Verification (Executive Order 12989). (Not applicable to the acquisition of commercially available off-the-shelf (Jan 2025) items or certain other types of commercial products or commercial services as prescribed in FAR 22.1803.)
(41)
(i) 52.223-9, Estimate of Percentage of Recovered Material Content for EPA-Designated Items (May 2008) ( 42 U.S.C. 6962(c)(3)(A)(ii)). (Not applicable to the acquisition of commercially available off-the-shelf items.)
Alternate I of 52.223-9 (42 U.S.C. 6962(i)(2)(C)). (Not applicable to the acquisition of commercially available off-the-shelf items.)(ii) (May 2008)
52.223-11, Ozone-Depleting Substances and High Global Warming Potential Hydrofluorocarbons (42 U.S.C. 7671, ).(42) (May 2024) et seq.
52.223-12, Maintenance, Service, Repair, or Disposal of Refrigeration Equipment and Air Conditioners (42 U.S.C. 7671, ).(43) (May 2024) et seq.
52.223-20, Aerosols (42 U.S.C. 7671, ).(44) (May 2024) et seq.
52.223-21, Foams (42 U.S.C. 7671, ).(45) (May 2024) et seq.
52.223-23, Sustainable Products and Services (MAR 2025) (DEVIATION 2025-O0004)) (7 U.S.C. 8102, 42 U.S.C. 6962, 42 U.S.C. 8259b, and 42 U.S.C. (46) 7671l).
(47)
(i) 52.224-3 Privacy Training (5 U.S.C. 552 a).(Jan 2017)
Alternate I of 52.224-3.(ii) (Jan 2017)
[X] (48)
(i) 52.225-1, Buy American-Supplies (41 U.S.C. chapter 83).(Oct 2022)
Alternate I of 52.225-1.(ii) (Oct 2022)
(49)
(i) 52.225-3, Buy American-Free Trade Agreements-Israeli Trade Act (19 U.S.C. 3301 note, 19 U.S.C. 2112 note, 19 U.S.C. 3805 note, 19 U.S.C. (NOV 2023) 4001 note, 19 U.S.C. chapter 29 (sections 4501-4732), Public Law 103-182, 108-77, 108-78, 108-286, 108-302, 109-53, 109-169, 109-283, 110-138, 112-41, 112-42, and 112-43.
Alternate I [Reserved].(ii)
Alternate II of 52.225-3.(iii) (Jan 2025)
Alternate III of 52.225-3.(iv) (Feb 2024)
Alternate IV (Oct 2022) of 52.225-3.(v)
52.225-5, Trade Agreements (19 U.S.C. 2501, ., 19 U.S.C. 3301 note).(50) (NOV 2023) et seq
52.225-13, Restrictions on Certain Foreign Purchases (E.O.'s, proclamations, and statutes administered by the Office of Foreign Assets [X] (51) (Feb 2021) Control of the Department of the Treasury).
52.225-26, Contractors Performing Private Security Functions Outside the United States (Oct 2016) (Section 862, as amended, of the National Defense (52) Authorization Act for Fiscal Year 2008; 10 U.S.C. Subtitle A, Part V, Subpart G Note).
52.226-4, Notice of Disaster or Emergency Area Set-Aside (Nov 2007) (42 U.S.C. 5150).(53)
52.226-5, Restrictions on Subcontracting Outside Disaster or Emergency Area (42 U.S.C. 5150).(54) (Nov 2007)
52.226-8, Encouraging Contractor Policies to Ban Text Messaging While Driving (E.O. 13513).[X] (55) (May 2024)
52.229-12, Tax on Certain Foreign Procurements .(56) (Feb 2021)
52.232-29, Terms for Financing of Purchases of Commercial Products and Commercial Services (41 U.S.C. 4505, 10 U.S.C. 3805).(57) (Nov 2021)
52.232-30, Installment Payments for Commercial Products and Commercial Services (41 U.S.C. 4505, 10 U.S.C. 3805).(58) (Nov 2021)
52.232-33, Payment by Electronic Funds Transfer-System for Award Management (31 U.S.C. 3332).[X] (59) (Oct2018)
52.232-34, Payment by Electronic Funds Transfer-Other than System for Award Management (Jul 2013) (31 U.S.C. 3332).(60)
52.232-36, Payment by Third Party (31 U.S.C. 3332).(61) (May 2014)
52.239-1, Privacy or Security Safeguards (5 U.S.C. 552a).(62) (Aug 1996)
52.240-1, Prohibition on Unmanned Aircraft Systems Manufactured or Assembled by American Security Drone Act-Covered Foreign Entities (63) (Nov 2024) (Sections 1821-1826, Pub. L. 118-31, 41 U.S.C. 3901 note prec.).
52.242-5, Payments to Small Business Subcontractors (15 U.S.C. 637(d)(13)).(64) (Jan 2017)
(65)
(i) 52.247-64, Preference for Privately Owned U.S.-Flag Commercial Vessels (46 U.S.C. 55305 and 10 U.S.C. 2631).(Nov 2021)
Alternate I of 52.247-64.(ii) (Apr 2003)
Alternate II of 52.247-64.(iii) (Nov 2021)
(c) The Contractor shall comply with the FAR clauses in this paragraph (c), applicable to commercial services, that the Contracting Officer has indicated as being incorporated in this contract by reference to implement provisions of law or Executive orders applicable to acquisitions of commercial products and commercial services:
52.222-41, Service Contract Labor Standards (41 U.S.C. chapter67).(1) (Aug 2018)
52.222-42, Statement of Equivalent Rates for Federal Hires (29 U.S.C. 206 and 41 U.S.C. chapter 67).(2) (May 2014)
52.222-43, Fair Labor Standards Act and Service Contract Labor Standards-Price Adjustment (Multiple Year and Option Contracts) (29 U.S.C.
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .