TERPS_Tree_Removal_Questions.pdf

PDF 41 KB Posted

Attached to
AFICA- TERPS Tree Removal Federal contract opportunity
Solicitation number
FA4484-18-Q-0013
Issued by
Department of the Air Force Air Mobility Command

About this file

Questions and Answers for FA4484-18-Q-0013

View the file

Other files for this federal contract opportunity

Other files attached to AFICA- TERPS Tree Removal, newest first.
File Type Posted
Attachment_7-_UPDATED_Wage_Det_Burlg.pdf PDF
Attachment_2-Wage_Determination.pdf PDF
Attachment_4-_Anti-Terrorism_statement.pdf PDF
Attachment_1-_FAR_52.212-3_Alt_1.pdf PDF
Attachment_3-Security_Forces_Appendix.pdf PDF
Attachment_5-_Medical_statement.pdf PDF
Attachment_6-_Area_Map.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

TERPS Tree Removal Questions

FA4484-18-Q-0013

1. Is an Erosion and Sedimentation Control Plan required for this work and, if so, is that the responsibility of the contractor to prepare?

a. Yes, an erosion control plan is required. The plan must be prepared by a professional engineer.

2. Is a county permit required for this work and, if so, is that the responsibility of the contractor to purchase/obtain?

a. Yes, it is the contractors responsibility.

3. When will the contract be award?

a. The contract will be awarded before end of the government’s fiscal year, which ends

September 30.

4. Will working on weekends be permitted?

a. No, working on weekends is not permitted unless prior coordination has been approved by the COR.

5. Is chipping or grinding permitted off site?

a. Yes, the contractor may remove or transport waste/debris to offsite location. If the contractor chooses to chip/grind onsite however, all chips/grindings and any other debris, roots, stumps, branches, etc., must be removed and properly disposed of before seeding process.

6. Do current stumps need to be grubbed?

a. Yes, current stumps/roots will need to be grubbed. (completely removed)

7. Who will determine the mixture of seed for the area?

a. USAF AMC 787 CES CEIEA Chief, John Joyce.

8. Would it be possible to request a copy of the Burlington county conversation district certificate of specifications for this requirement? After calling the Burlington County Conversation office, there should be a certificate of compliance already filed for this project stating the required seed, fertilizer and mulch specifics

a. After talking with Burlington county official (Robert Reitmeyer), the cert. of compliance or report of compliance will be done after the permit is issued from the Burlington County Soil Conservation office, upon completion of job. For inspection of soil erosion and seed establishment.

9. What is the timber mix/type of wood within the 27.5 acres?

a. Oak, maple, pine, locust, cherry, sassafras.

10. What a the preferred access roads for equipment and truck to travel in and out of Joint Base MDL?

a. The site is best accessed by Rt. 530 Trenton Rd. And is located outside of cantonment area so no gate access or passes are required in this location.

11. In accordance with FAR 36.204, could you please indicate what the magnitude of construction range is for the Tree Removal project? If this requirement is a services or supply contract (not construction), please indicate so and disregard this request for magnitude.

a. This is a service contract so FAR 36.204 does not apply.

12. Can you please advise what seed mix is required to be used?

a. Switchgrass.

13. Can the government, please clarify what kind of references it will be required? Do you need POC information? Previously contract number?

a. POC information.