SOW_-_FA4484-16-R-0035.pdf
PDF 148 KB Posted
- Attached to
- Fence Install
- Solicitation number
- FA4484-16-R-0035
About this file
Revised Statement of Work to adjust approximate measurements. Revision also includes map of Building 487.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Questions_ _Answers.pdf | ||
| MFR_-_Attachment_J.2_Submittal_Schedule.pdf | ||
| SF_1442_Fence_Install_Solicitation.pdf | ||
| J2._Submittal_Schedule.xlsx | XLSX spreadsheet | |
| J4._SFS_Appendix_4_to_Annex_C_-_10June2015.PDF | ||
| J1._Wage_Determination.pdf | ||
| J3._Past_Performance_Survey_-_Fence_Install.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK
FOR
NEW FENCING SECTION BUILDING 487 and FREEDOM PARK
AT
JOINT BASE MDL, LAKEHURST, NEW JERSEY
1. DESCRIPTION OF SERVICES. The contractor shall provide all personnel, equipment, tools, materials, supervision, and other items necessary to install new fence section extension, new fabric on original fence, and partial fence removal connecting area at B487. Also, contractor shall remove old wooden fence and install approximately 100 feet of new TREX or equivalent style composite railings, dark brown in color at Freedom Park. Contractor is responsible for taking all measurements as required for installation.
2. TECHNICAL_REQUIREMENTS: The Contractor shall provide all the necessary labor, equipment, materials, transportation, and supervision to meet all of the following requirements:
Digging permit needed for fence install.
Building 487:
INSTALL NEW FENCE SECTION POLES, RAILS, FABRIC
1. Install new chain link fence total length approximately 261 linear feet, 5 feet high, brown vinyl coated fabric and fabric ties, couplings, posts, top and bottom rails.
2. Install posts at nine foot intervals, installed depth 3 feet minimum in concrete.
3. Posts shall be 2-1/2 inch corner, 1-3/4 inch line post, top and bottom rails, and metal fabric brown vinyl coated, 9 gauge, stretched with ties.
4. Install new 4 foot wide gate into new fence area on south side near bowling alley. See attached drawing.
REPLACE EXISTING FENCE FABRIC
1. Remove existing fence fabric on approximately 261 L.F. of chain link fabric.
2. Replace fabric, according to standard procedure new fence fabric, 9 gauge, brown vinyl coated, stretched with ties.
REPLACE FENCE SLATS
1. Install new brown vinyl fence slats, fit to the mechanical area fence surround, approximately 60 L.F.
REMOVE FENCE SECTION
1. Remove fence section posts, rails, fabric approx. 35 L.F. section between new and original area.
Freedom Park:
REMOVE FENCE SECTION
1. Remove wooden fence section posts, rails, etc. approximately 100 feet.
INSTALL NEW FENCE SECTION POSTS, RAILS, ETC.
1. Install new TREX or equivalent style composite railings, dark brown in color, total length approximately 100 linear feet 42 inches high, posts, and all hardware. Dark Brown in Color.
2. Install posts at depth of 3 feet minimum in concrete. Dark Brown in Color.
3. All railing components shall be Dark Brown in color.
4. All sections shall have top rail, cap and bottom rail with pickets not to exceed 4 inches on center.
5. All posts shall have decorative cap.
2.1. Submittals:
Catalog Cut Sheet of Composite Railing Style and Specifications due at Pre- Construction Conference.
Shop drawings of Composite Railing design and assembly. Due at Pre-Construction Conference.
Any adjacent areas dissembled, damaged, or removed by the contractor during installation shall be properly repaired by the contractor at no expense to the Government. Any and all debris / trash generated by this project shall be removed and properly disposed of off base by the contractor. The contractor or his representative (QAP) shall be on site during duty hours or the hours of work being accomplished. The contractor shall coordinate the time that work will be accomplished with the points of contact listed below. The contractor shall be responsible for daily clean up at the work site and complete restoration of the area after completion of the work. All work shall be accomplished in accordance with all Federal, state, and local laws and regulations, applicable building codes and standards, NEC, NFPA, BOCA, & CABO, and OCCUPATIONAL SAFETY AND HEALTH ADMINISTRATION (OSHA) codes.
3. SITE VISIT:
A site visit of the facility was scheduled on 7 September 2016 at 10:00 A.M. EST and Contractor attendance was highly recommended.
4. SPECIAL REQUIREMENTS:
The work site shall remain clean and clutter free since this area is an active employment site. All dumpsters or other containers for trash and debris shall be located in areas designated by the building manager and shall be subject to removal and / or relocation at the building manager’s request. These requirements shall not impact the performance period.
5. POINTS OF CONTACT:
Contracting Specialist: SSgt Angel Delgado, angel.delgado.1@us.af.mil Contracting Officer: Wanda L. Wilson, wanda.wilson.1@us.af.mil
The Contractor Manager or an alternate shall be available within sixty (60) minutes notice during normal duty hours, 7:30am to 4:15pm, to meet with Government personnel to discuss any problems encountered at the work site. Contractor will supply Government POC’s with phone number for contacting purposes.
6. BASE ENTRY:
The contractor shall obtain the necessary passes and /or identification for entry into Joint Base McGuire, Dix, Lakehurst for all employees prior to commencement of work. The Government reserves the right to refuse to issue an entrance pass to any employee for any reason deemed valid by the Government. The contractor shall be required to provide the Security Forces with vehicle registration(s), proof(s) of mailto:angel.delgado.1@us.af.mil mailto:wanda.wilson.1@us.af.mil insurance, driver license(s), and a picture ID(s) to obtain a pass for entry onto the base. The Pass and Registration building is located on Rt. 547, Lakehurst, NJ.
7. SECURITY FORCE AND FIRE PROTECTION:
The Base Security Police telephone number is 732-323-4000 and the Base Fire Department telephone number is 911 for reporting a fire.
8. PERFORMANCE PERIOD:
All work shall be completed within a forty five (45) calendar day period, excluding holidays.
9. INSPECTION / ACCEPTANCE OF PROJECT COMPLETION:
A final inspection will be scheduled upon completion of all work. Contact the Government POC’s two (2) days prior to completion for a site visit.
ATTACHMENT 1 BLD 487 MAP
34’
24’
76’
24’All dimensions approximate
New Fence Area
Remove Section
Replace existing fabric
New gate area
| B487 Fence |
| 8. PERFORMANCE PERIOD: |
| All work shall be completed within a forty five (45) calendar day period, excluding holidays. |
B487 Sketch