This is a Statement of Work (SOW) for mailbox removal and installation services at an Official Postal Center, effective July 10, 2026.
The contractor must remove and dispose of non-functioning dormitory mailboxes from eight buildings (1355, 1353, 1352, 1334, 1309, 1308, 1305, and 1304) and install USPS-approved replacement mailboxes. Work hours are 8:00 a.m. to 4:30 p.m., Monday through Friday. The contractor bears full responsibility for providing all labor, materials, specialized equipment, and disposal of removed items. Each new mailbox must include one master key and two keys per mailbox compartment. Installation must be permanent with smooth-functioning locks requiring no excessive force, and all mailboxes are to be swapped one-for-one without retrofitting or structural alterations. The contractor must coordinate delivery, removal, and installation with the government point of contact and maintain daily cleanup of debris, with final cleanup completed prior to inspection. Electrical power is provided at no cost, though the contractor must provide temporary connections and coordinate with Dorm Management. A pre-work site meeting with the contractor's key personnel is mandatory to discuss procedures and disposal areas. The contractor must comply with OSHA Title 29 CFR, National Electric Code, National Building Code, and applicable federal and state environmental and safety regulations. A commissioning walk-through will occur within five days of completion with the Official Postal Manager, Postal Service Center, and Resource Advisor to verify functionality and safety compliance. Any deficiencies identified must be corrected at no additional cost to the government. The contractor is responsible for all vendor tools and equipment on-site, and personnel are restricted to assigned areas. Final checkout requires approval from the Official Postal Manager, and any work not meeting SOW requirements or requiring rework due to deficiencies will be corrected without additional government cost at the Contracting Officer's discretion.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Statement of Work (SOW) for
Official Postal Center
Mailbox removal and Installation
10 July 2026
BACKGROUND
The dormitory mailboxes need to be replaced as many of them no longer function correctly. New replacement boxes are needed so that the Postal Service Center can properly deliver letter mail and dormitory residents can access their letter mail during non-customer service hours.
1. PROJECT LOCATION
Work for this contract must be performed at Building 1355,1353, 1352, 1334, 1309, 1308, 1305 &
1304. Work at the site must be accomplished between the hours of 0800a.m. and 4:30 p.m., Monday through Friday.
2. SCOPE
2.1. General
This statement of work encompasses the detailed requirements for the removal and installation of USPS approved mailboxes. The Contractor must provide all labor, materials, and specialized equipment as necessary to perform the work described herein as well as disposal of the removed items.
2.2. Description of Work
The contractor must disassemble, disconnect, remove and dispose (off-base) of the existing mailboxes.
The contractor will be responsible to offload, uncrate new mailboxes, and install new mailboxes. Each mailbox must have one master key and 2 keys per mailbox compartment.
3. INSTALLATION REQUIREMENTS
Contractor must supply all parts, labor, and equipment necessary to permanently install new mailboxes. The opening and closing of all regular and master locks must function smoothly and not require excessive force to open. The Contractor must effectively collaborate with Official Mail
Center as well as the Facility Manager by providing information about the location, design, dimensions, and all aspects of the project throughout the install process. All mailboxes will be swapped one for one and there will be no retrofitting or alterations of the current support structure.
4. COMMISSIONING
A walk-through will take place within 5 days of completion with the Official Postal Manager, Postal
Service Center and Resource Advisor. The contractor must demonstrate functionality and compliance acceptable to all safety standards. All deficiencies must be rectified by the Contractor at no extra charge to the Government in a later specified amount of time if/when any defects are noted.
5. JOB CONDITIONS
5.1. Delivery/Storage/Handling
Work and storage space is limited at the site. The contractor will be responsible for coordinating delivery, removal, and installation of mailboxes with Government listed point of contract.
5.2. Cleanup
The Contractor must remove all debris resulting from their work from the premises at the site and dispose of properly daily. Also, a final cleanup must be conducted when the work is complete and prior to final inspection.
5.3. Power
Electrical power required for the project work will be made available to the Contractor at no cost. The Contractor, at their expense, must provide all temporary connections, fittings, etc., from the source to the point of use. Arrangements for use of these facilities must be coordinated with Dorm Management.
6. GENERAL
6.1. Pre-Work Site Meeting
A site visit or teleconference must be made by the Contractor's key personnel who will be performing the on-site work to discuss disposal areas for any removed materials, procedures for working around the operating facility, etc. The Contractor must comply with the latest OSHA regulations Title 29 Code of Federal Regulations (CFR) regarding safety in the work area.
The Contractor must also comply with applicable Federal and State laws and regulations concerning human health and environmental protection, including those pertaining to air and water pollution, and the disposal of solid and hazardous wastes, substances, and materials.
The Contractor must consult the latest referenced OSHA, Environmental Protection Agency
(EPA), State, and local documents for pertinent regulations. In the event of an emergency or drill the contractor employees must follow diagrammed e x i t procedures which are posted in numerous locations in the area.
6.2. Contractor Personnel
All labor must be in strict conformance with rules, regulations, and recommendations of
OSHA, National Electric Code (NEC), municipal and State codes, National Building Code, or any other authorities having local jur isdiction pertaining to the work. An effort must also be made to use the objectionable product outside of peak operational hours.
6.3. Vendor Responsibilities
Vendor technicians will maintain control of all vendor tools and equipment at the jobsite. At no time will the government be responsible for lost, damaged, or missing tools, equipment, or parts that are property of the vendor on the jobsite. Any debris or trash created by the vendor on the job site will be disposed of by the vendor. Contractor personnel are only to be in their assigned areas and are not allowed in other areas without section supervision approval and/or escort.
6.4. Vendor Checkout
After completing the work that is outlined in this SOW, the vendor must check out with the Official
Postal Manager (OPM). OPM will inspect all work performed and will ensure work has been accomplished IAW this SOW and meets requirements necessary for the government.
6.4.1. Any dust, dirt, and debris on the ground that is caused by the contract will be swept up and cleaned before the contract leaves and will be disposed of. The areas will be checked by the OPM and contractor will not be released until area is clean.
6.4.2. Any work accomplished that is not according to this SOW or items that require rework due to workmanship or neglect will be corrected at no additional cost to the Government at the discretion of the Contracting Officer.
DORMITORY MAILBOXES
Bldg 1304/1309
Bldg 1352 & 1353
Bldg 1305, 1308, 1334
Bldg 1355
Dormitory Locations