This document is a Statement of Work (SOW) for a mobile training area to be built at an EOD proficiency range. The contractor is required to prefabricate, transport, and install three 40-foot intermodal shipping containers in an L-shape configuration, with two containers stacked to create a two-story structure and the third container attached perpendicularly with a rooftop walkway. The containers must meet specific requirements for doors, stairs, windows, railings, and interior layout with hallways, hides, and rooms. This SOW is in support of a federal contract opportunity from the Department of the Air Force Air Mobility Command to procure the EOD Training Conex, as detailed in the related solicitation.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Statement of Work (SOW) for

EOD Proficiency Range Mobile Training Area - Addendum 01

23 July 2024

60 CES/CED has a requirement for a mobile training area to be built at the demolition proficiency range. The purpose is to simulate an urban environment for realistic training and to have an easily repairable structure to conduct explosive operations.

Description: The contractor shall prefabricate, transport, and install three 40-foot intermodal shipping containers. The containers shall be placed on the EOD proficiency range in the shape of an L. Two of the containers shall be stacked to create a two-story structure, and the third container shall be attached perpendicular to the aforementioned structure. The third structure shall have a rooftop walkway that can be accessed from the two-story structure. All specifications of the containers are listed below:

1. Doors – Five exterior doors (Two per ground level container and one on the second-floor container leading out to a walkable rooftop) minimum 30” x 80” .

Wood or metal construction (preferred metal) with handles and latch.

a. Nine interior doors (three per container, depending on interior layout) minimum 30” x 80” . Wood construction.

2. Stairs – Interior stairs 36” wide with a landing at the top and bottom measuring at least 47”. Wood or metal construction

3. Windows – 12 in total, 36” x 42” (2 on each long side of all containers). Clear plastic panes instead of glass.

4. Exterior railings on walkable rooftop (see attachment for layout diagram).

Metal or wood construction.

5. Walkable rooftop shall be covered in diamond plating for anti-slip.

6. A series of non-movable hallways, hides, and rooms shall be created in the interior of the single wide containers. The single level container shall have at least three rooms accessable by a hallway. The bottom level of the two story container shall be left open with no rooms. The top level of the two story container shall be divided into at least two rooms. The dimensions of the rooms and various hide layouts will be finalized during post-award discussions.