STATEMENT OF WORK
05June2009
ANNUAL LOAD TEST OF 21 VEHICLES TO COMPLY WITH
TO 36-1-191 Para 3.10.5.1 and AFOSH STD 91-501 Para 16.4.5.2
1.0. SCOPE_ Contractor shall provide all labor, tools, equipment, materials and weights necessary to conduct annual load tests on 21 vehicles of Altus AFB vehicle fleet. All work will be accomplished in Building 353 Vehicle maintenance compound, at Altus AFB OK.
2.0. PRINCIPAL FEATURES: Per TO 36-1-191 Para 3.10.5.1 and AFOSH STD 91-501 Para 16.4.5.2, 21 vehicles with some articulating and some extendible boom platforms is to be load tested in accordance with each vehicle manufacturers checklist and producers.
2.5. The contractor shall proceed with the load testing in a continuous and diligent manner. Vehicles will be load tested on two separate occasions, during the month of June and during the month of January. This will enable the use of a certified and tested vehicle while the off-cycle vehicle is being tested. Items required to complete the load test will be in the contractor's possession and the contractor shall proceed with the load test without interruptions. Night, weekend or holiday work must be approved in advance, and will be kept to an absolute minimum. Hours of Operation for Altus AFB vehicle maintenance are Monday through Friday, 07:00- 16:00
3.0 GOVERNMENT FURNISHED PROPERTY:
3.1. Altus AFB vehicle maintenance will provide a forklift to unload and reload test weights from contractor's vehicle.
3.1. Qualified operator during load test.
3.2. Check list and load testing producers established by manufacturers of each vehicle to be load tested.
4.0. CONTRACTOR RESPONSIBILITIES:
4.1. The contractor shall become familiar with the load test, work area and requirements. They will verify all field measurements and certified weights to conduct the load test work on all 21 vehicles.
4.2. The successful vendor shall provide separate load test certificate for each vehicle upon completing of load test
4.3. The contractor shall maintain a safe working area at all times. All safety rules local, OSHA and AFOSH are to be adhered strictly during the entire time vendor is on Altus AFB.
4.4. Vendor is responsible for their travel lodging and meal expenses to, from and while they are at Altus AFB.
5.0. POINT OF CONTACT; WS10 Bulent "Bernie" Uygur at (580) 481-6517.
Other files
| File | Type | Posted |
|---|---|---|
| Attachment 1 Vehicle List.xlsx | XLSX spreadsheet | |
| FA4419-09-T-0125.doc | DOC document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
File details come from the government source that posted it. Updated .