Atch. 05 Land Mobile Crane Questions and Answers.pdf
PDF 37 KB Posted
- Attached to
- FY 26 Mobile Crane & Operator Services Federal contract opportunity
- Solicitation number
- FA441826Q0020
About this file
This is a Questions and Answers document for federal contract opportunity FA441826Q0020 regarding Land Mobile Crane services. The document clarifies six key points raised by potential vendors during the solicitation period.
The contract involves crane offloading services at Wharf Alpha with a 14-day Period of Performance, with specific dates to be determined post-award. The maximum cargo weight to be lifted is 52,000 lbs (26 US short tons), and the crane staging location will be formally designated after contract award. Regarding scheduling, work is expected during standard workdays with flexibility for additional hours to meet project requirements, and work may be scheduled at any point during the 14-day period, including weekends. Vendors are permitted to submit quotes with separate standard workday rates and weekend rates to account for potential overtime costs under union agreements. Detailed offloading duration and scheduling information is contained in the Performance Work Statement, with further details to be provided after contract award.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Atch 03. Rev 1 Provision and Clauses - FA441826Q0020.pdf | ||
| Atch- 01. RFQ Fill-in sheet FA441826Q0020 - Land Mobile Crane and Operator Services.pdf | ||
| Atch 02. Land Mobile Crane Service PWS.pdf | ||
| Atch 03. SF 1449 Provision and Clauses - FA441826Q0020.pdf | ||
| Atch 04. SCA WD 2015-4427.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Question and Answers Land Mobile Crane
FA441826Q0020
Question 01: Can you confirm whether the crane staging location at Wharf Alpha will be designated after award, or if additional site information is available for lift radius assumptions?
Answer 01: The specific crane staging location will be formally designated after the contract has been awarded.
Question 02: Can you please clarify the discrepancy between the RFQ Sheet saying (14 days pop) and the SF1449 saying (7 days pop), Is the period of performance 7 days or 14 days?
Answer 02: The correct Period of Performance (POP) is 14 days and specific dates will be determined after award.
Question 03: Is the offloading expected to be 1 twelve hours in duration over 1 day or twelve hours duration for each day?
Answer 03: The offloading duration is outlined in the Performance Work Statement.
Further detailed scheduling will be provided after award of the contract.
Question 04: Maximum Cargo weight to be lifted says 52k, Can you clarify this metric please? Does this mean 52 Tonnes?
Answer 04: To clarify, the weight metric is in US short tons. The "52k" refers to 52,000 lbs, which is equivalent to 26 tons.
Question 05: How many hours per day will the crews be working?
Answer 05: The operational expectation is for a standard workday, with the built-in flexibility to work additional hours as necessary to meet project requirements.
Question 06: Will the crane be working on the weekend in the scheduled 14 day cycle, so I can accurately capture any overtime costs with our outstanding union agreement for the operator?
Answer 06: The expectation is that work can be scheduled at any point during the 14-day period of performance, including weekends. Quotes should account for any potential overtime costs in their proposals. Vendors are allowed to quote a standard work day rate and a separate weekend rate.