This document appears to be a set of Questions for Clarification related to a federal contract opportunity. The key details are:

The RFQ solicitation is for Construction Materials, issued by the Department of the Air Force Special Operations Command. The questions focus on specific line items, including a 300KVA outdoor transformer (208/120V) and a 400A main breaker panel (208/120V, 3-phase, 4-wire). The customer has confirmed there will be no utility meter installed for this project, and the panel will be surface-mounted. The response includes details on the voltage, phase, and mounting requirements for these electrical equipment items.

View the file

Other files

File Type Posted
RFQ - FA441724Q0121 - Electrical Materials.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

1. Could you please provide us with a litle bit more info on the transformer, line #44 on your sheet.

I need to know exactly what they need. Will there be voltage requirements and is it for indoor or outdoor?

A: Transformer will be 300KVA (12470D/120WYE), It will also be outdoor. (208120 Volt)

Regarding product from Line item #51 on the list, the panel board, my supplier, and I have a few ques�ons to make sure we are providing you with the correct one. May you please provide the following informa�on. Thank you!

2. Need name of u�lity company in customer area to check meters against the u�lity's approval list?

A: There will be no meter installed for this project.

3. Please verify if customer is needing a Meter Main, Meter Socket or Meter Combo? meter main

4. If a meter combo is needed, we need to know how many circuits/spaces?

5. If need flush or surface mount?

A: If referring to the panel it will be surface mounted

6. Need to know voltage required for the customers applica�on?

A: Panel will be 400amp main breaker, 208/120v, 3 phase, 4 wire.

7. Need to know how many phases needed? single or three phase?

A: 3phase

8. Need to know if need overhead or underground?

A: Underground

9. Need to know if bypass (horn, manual, lever, test block) needed or none?

How many Jaws?