AIR PARK Questions and Answers.pdf
PDF 74 KB Posted
- Attached to
- Air Park Static Aircraft Movement
- Solicitation number
- FA441723Q0023
About this file
This document contains questions and answers regarding a solicitation from the Department of the Air Force Special Operations Command for static aircraft movement services at an air park. The contractor will be responsible for moving AC-130H and AC-130U aircraft to and from support stands, which the contractor must build to specification. The period of performance has been extended to 60 days from contract award. The government will provide a specialized tow bar and technical manuals are available upon request. The existing bird proofing on the AC-130H must be removed and replaced, and bird proofing must be accomplished on the AC-130U.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Airpark Move REVISED SOW 28 Jul 23.pdf | ||
| RFQ - FA441723Q0023.pdf | ||
| Attachment D AF 3581.pdf | ||
| Airpark Move SOW 13 Jul 23.pdf | ||
| Wage Determination 15-4531.txt | TXT text file | |
| Solicitation - FA441723Q0023.pdf | ||
| Attachment C - AFI 84-103.pdf | ||
| Attachment B - TO 1-1-8.pdf | ||
| Attachment A - C-130 Static Display Movement.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AIR PARK STATIC AIRCRAFT MOVEMENT
QUESTIONS & ANSWERS
Question 1: Due to the complexity of the project, and having to give 2-3 week notices, is it possible to change the Period of Performance (PoP) from 30 to 60 days?
Answer: Yes, the SOW has been updated to reflect a PoP of 60 days after contract award.
Question 2: Is the Contractor responsible for building the support stands.
Answer: Yes, the contractor is responsible for building the support stands to spec as outlined in the SOW.
Question 3: Will the Government provide a specialized tow bar?
Answer: Yes. 1 SOMSG requires at least a 2 week notice prior to use of the equipment.
Question 4: Is a T.O. available for the track and tub for the engines?
Answer: Yes, a T.O. is available upon request from 1 SOMXG.
Question 5: The aircraft are already bird proofed. Is there other bird proofing that needs to be done or is the current bird proofing acceptable?
Answer: The existing bird proofing on the AC-130H needs to be removed and replaced.
There is no existing bird proofing on the AC-130U which requires to be accomplished.