‐ What is the condition of the Mobile GSC Unit upon start of work:
o The fabricated Duct work for the Mobile GCS side of the ducting is provided as GFE. The contractor must provide the fabricated duct work for the HVAC package unit as displayed in figure 5 in the SOW (also reposted directly below).
Contractor provided converters / fabricated HVAC unit example
‐ Are the square to round converter industrial grade duct components being provided as GFE?
o The GCS side will be GFE ducting that is already fabricated to accept a round 16” duct. The Contractor must provide the HVAC package unit fabricated duct.
GFE / GSC Unit Fabrication State – NOT INCLUDING THE DUCTING
‐ What are the required ducting lengths based on GCS Unit placement?
o Upper duct must be 12-15 ft and the lower duct must be 6-9 ft.
o NOTE: This assumes the package HVAC unit has both intake and exhaust on the same end as shown in the example pictures. If not, more length will be needed.