FA441720Q0006 -Site Visit Questions and Answers (26 Nov 19).pdf
PDF 711 KB Posted
- Attached to
- Bosch CCTV Installation and Camera Replacement
- Solicitation number
- FA441720Q0006
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FA441720Q0006
Site Visit Questions & Answers
26 November 2019
VCC – B90905:
1. What size monitors for the VCC (window area / office)?
21” – 23” LED Monitors are requested.
2. Can use empty rack space in Comm Room?
Yes, the contractor will be able to utilize the empty rack space.
3. Ensure 2 strand fiber availability from VCC to BDOC
Yes, this has been confirmed with the Base Communications Squadron.
4. Monitor view from decoder can be a single image or quad – customer option
Single view of the VCC lobby camera, is preferred.
Fuel Deopt – B90916:
5. Ensure 2 strand fiber availability from building to BDOC
Yes, this has been confirmed with the Base Communications Squadron.
Marina:
6. Ensure 120v electrical to be provided at pole for camera power*
Yes, this has been confirmed with the Base Civil Engineering Squadron.
7. Ensure 2 strand fiber availability to be provided at camera pole*
Yes, this has been confirmed with the Base Communications Squadron.
8. What is the process to spot underground utilities prior to setting pole base?
The Government will complete dig permits, and provide a map with locations of utility lines.
9. Are there any wind speed or Hurricane requirements for the camera pole?
The pole and foundation need to be able to withstand at least 130mph winds.
FA441720Q0006
Site Visit Questions & Answers
26 November 2019
10. The SOW clause 1.3 mentions: All cameras must meet the Air Force standards and be listed on the Air Force Authorized Equipment List, dated 25 June 2019.
Please refer to the Air Force Authorized Equipment List, dated 25 June 2019.
11. What are the camera models to be considered for this project? Is the contractor required to figure out the suitable models? Where can we access the “Air Force Authorized Equipment List, dated 25 June 2019”?
Please refer to the Air Force Authorized Equipment List, dated 25 June 2019.
12. Is any storage of data required?
No, storage of data is not a requirement for this effort.
13. Is providing NVR, monitor and server required as a part of the project? Or are the new cameras going to be hooked up to an existing NVR and data storage system?
Cameras will be hooked up to existing DVR/NVR system.
14. Is the cabling required supposed to be of CAT6 specifications?
CAT5e or CAT6. It is up to the contractor to determine what is the best option for each location.
15. Is the length of the cabling known?
The length of the cabling is not known at this time.
16. Are PoE switches required?
Yes, PoE switches are required.
File details come from the government source that posted it. Updated .