Questions & Answers Regarding the subject solicitation, do we need to submit PART II of Standard Form 330 for each sub-consultant in addition to the prime consultant, or we need to submit it for the prime consultant only.

The directions to complete the SF 330 are on the form. Contractors should submit Part I of Standard Form 330 for the prime contractor and Part II for each sub-consultant.