Question_ _Answer_FA4417-14-R-0013.docx
DOCX document 13 KB Posted
- Attached to
- Repair HVAC System, HQ AFSOC Bldg. 1
- Solicitation number
- FA4417-14-R-0013
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Solicitation_FA4417-14-R-0013_Site-Visit_Sign-In_Sheet.pdf | ||
| FA4417-14-R-0013-00002.doc | DOC document | |
| FA4417-14-R-0013-00001.doc | DOC document | |
| Attachment_4_-_Past_Performance_Questionnaire.pdf | ||
| Attachment_5_-_Financial.pdf | ||
| FA4417-14-R-0013.pdf | ||
| Attachment_2_-_Drawings.pdf | ||
| Attachment_3_-_Wage_Rates.pdf | ||
| Attachment_1_-_Specifications.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Questions & Answers
FA4417-14-R-0013
Repair HVAC System, HQ AFSOC Bldg. 1
QUESTION: Spec Section 230500 - 1.08 A, TEST AND BALANCE/COMMISSIONING, states the following: "The Mechanical Contractor shall provide the services of a third party, independent firm for Test and Balance and Commissioning." Is this correct? Generally, the Test & Balance and Commissioning subcontractors are first tier subs to the General Contractor.
ANSWER: Either way is fine.