FA4417-09-R-0021.pdf
PDF 352 KB Posted
- Solicitation number
- FA4417-09-R-0021
About this file
FA4417-09-R-0021
View the file
Other files
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ADAL AFOSI Det 309, Bldg 90310
- Project FTEV 05-1058, Specif ications and Draw ings Dated 14 April 2006
- Enter prices in Section B using TYPEWRITER of BLACK INK
- THIS ACQUISITION IS A HUBZONE SET- ASIDE
- This solicitation w ill be aw arded in accordance w ith FAR part 15, Contracting by Negotiation.
- DISCUSSION OF OFFER: The Government may aw ard a contract based solely on initial offers received, w ithout discussions of such offer.
Accordingly, each initial offer should be submitted on the most favorable terms from both a price and technical standpoint.
- DO: C2 NAICS CODE: 236210 SIZE STANDARD: $33,500,000
-SEE SECTION A CONTINUATION PAGE FOR ADDITIONAL BLOCK 10 INFORMATION
TIMOTHY M. THULIN 850-884-3298
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS
NEGOTIATED
16-Apr-2009
(RFP)
(IFB)
X
CALL:
ADAL AFOSI Det 309, Bldg 90310
B. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)
See Item 7
2. TYPE OF SOLICITATION
SEALED BID
3. DATE ISSUED
9. FOR INFORMATION A. NAME
SOLICITATION
NSN 7540-01-155-3212 1442-101 STANDARD FORM 1442 (REV. 4-85)
Prescribed by GSA
FAR (48 CFR) 53.236-1(e)
11. The Contractor shall begin performance w ithin _______10 calendar days and complete it w ithin ________210 calendar days after receiving aw ard, X notice to proceed. This performance period is X mandatory, negotiable. (See _________________________52.211-10
12 A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If "YES," indicate within how many calendar days after award in Item 12B.)
X YES NO
13. ADDITIONAL SOLICITATION REQUIREMENTS:
A. Sealed offers in original and __________1 copies to perform the w ork required are due at the place specif ied in Item 8 by ___________ local time ______________13 May 2009 (date). If this is a sealed bid solicitation, offers must be publicly opened at that time.
shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.
B. An offer guarantee is, X is not required.
C. All offers are subject to the (1) w ork requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
D. Offers providing less than _______60 calendar days for Government acceptance after the date offers are due w ill not be considered and w ill be rejected.
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair)
1. SOLICITATION NO.
IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.
4. CONTRACT NO.
7. ISSUED BY CODE
1 SOCONS
350 TULLY ST
HURLBURT FIELD FL 32544-5810
FA4417
PAGE OF PAGES
1 OF
CODE
(Title, identifying no., date):
12B. CALENDAR DAYS
04:00 PM (hour)
Sealed envelopes containing offers
5. REQUISITION/PURCHASE REQUEST NO. 6. PROJECT NO.
FTEV 05-1058
8. ADDRESS OFFER TO (If Other Than Item 7)
850-884-2041FAX:TEL: 850-884-1268 TEL: FAX:
FA4417-09-R-0021 45
20B. SIGNATURE
(REV. 4-85)STANDARD FORM 1442 BACK
TO SIGN
NSN 7540-01-155-3212
SOLICITATION, OFFER, AND AWARD (Continued)
(Construction, Alteration, or Repair)
CODE FACILITY CODE
17. The offeror agrees to perform the w ork required at the prices specif ied below in strict accordance w ith the terms of this solicitation, if this offer is accepted by the Government in w riting w ithin ________ calendar days after the date offers are due.
the minimum requirements stated in Item 13D. Failure to insert any number means the offeror accepts the minimum in Item 13D.)
AMOUNTS SEE SCHEDULE OF PRICES
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AMENDMENT NO.
DATE
20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN
OFFER (Type or print)
AWARD (To be completed by Government)
21. ITEMS ACCEPTED:
22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM
(4 copies unless otherwise specified)
CODE
(Insert any number equal to or greater than
20C. OFFER DATE
25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
10 U.S.C. 2304(c) 41 U.S.C. 253(c)
CODE27. PAYMENT WILL BE MADE BY:26. ADMINISTERED BY
(Include ZIP Code)14. NAME AND ADDRESS OF OFFEROR 15. TELEPHONE NO. (Include area code)
See Item 14
(Include only if different than Item 14)16. REMITTANCE ADDRESS
30B. SIGNATURE
29. AWARD (Contractor is not required to sign this document.)
document and return _______ copies to issuing office.) Contractor agrees Your of f er on this solicitation, is hereby accepted as to the items listed. This award con-to f urnish and deliv er all items or perf orm all work, requisitions identif ied summates the contract, which consists of (a) the Gov ernment solicitation and on this f orm and any continuation sheets f or the consideration stated in this y our of f er, and (b) this contract award. No f urther contractual document is contract. The rights and obligations of the parties to this contract shall be necessary .
gov erned by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certif ications, and specif ications or incorporated by ref er-ence in or attached to this contract.
30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31A. NAME OF CONTRACTING OFFICER (Type or print)
30C. DATE
(Type or print)
TEL: EMAIL:
31B. UNITED STATES OF AMERICA 31C. AWARD DATE
BY
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
(Contractor is required to sign this28. NEGOTIATED AGREEMENT
(M ust be fully completed by offeror)OFFER
FA4417-09-R-0021
Section A - Solicitation/Contract Form
BLOCK 10 CONTINUATION
- ENTER CONTRACTOR DUNS NO.:
-ENTER CONTRACTOR CAGE CODE:
- All offerors MUST complete the Online Representations and Certifications Appliocation (ORCA) @ https://orca.bpn.gov/ . Failure to complete all required Representations and Certifications will make your proposal ineligible for award.
- Disclosure of Magnitude of Construction: The magnitude of this project is estimated between $250,00 and
$500,000.
- A SITE VISIT HAS BEEN SCHEDULED FOR 30 April 2009@ 10:30 a.m., LOCAL TIME AT THE 1
ST
SPECIAL OPERATIONS CONTRACTING SQUADRON, 350 TULLY ST, BUILDING 90339, HURLBURT
FIELD, FL 32544. Fax or email written request with the name of those who will attend the site visit to SrA Tim
Thulin, Contract Specialist, Fax (850) 884-1272 or e-mail at timothy.thulin@ hurlburt.af.mil. Request must be received no later than 27 April 2009 @ 9:00 a.m. ONLY ONE SITE VISIT WILL BE HELD. You must enter the base from the main gate (Off Highway 98). Please allow extra time to obtain your pass.
- SUBMISSION OF QUESTIONS: Questions regarding this solicitation must be submitted in writing in Word format to the individuals listed above no later than the close of business 5 calendar days after the site visit.
- SUBMISSION OF PROPOSALS. Offerors are responsible for submitting proposals so as to reach the Government office designated in the solicitation by the date/time specified. Personnel requiring access to Hurlburt Field for the purpose of delivering a proposal must fax or e-mail a written request containing the company name and the name of the person(s) requiring access to SrA Tim Thulin, Contract Specialist, Fax (850) 884-1272 or e-mail at timothy.thulin@ hurlburt.af.mil. Requests must be received NLT 72 hours prior to the date and time established for receipt of proposals. You must enter the base from the main gate (Off Hwy 98). Please allow extra time to obtain your pass.
- For either the site visit or submission of proposals, all personnel requesting access to Hurlburt Field must possess a valid State or Government picture identification card. Personnel requesting vehicle access to Hurlburt Field must provide a valid driver's license, current vehicle registration, and valid vehicle insurance certificate.
https://orca.bpn.gov/
Section B - Supplies or Services and Prices
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0001 1 Lump Sum ADAL AFOSI Det 309, Bldg 90310
FFP
Contractor shall furnish all labor, materials, equipment, and supervision to construct addition and repair (ADAL) AFOSI Det 309, Bldg 90310 in accordance with the attached specifications and drawings dated 14 April 2006, FTEV 05-1058.
**********RECOVERY ACT OF 2009**********
FOB: Destination
SIGNAL CODE: A
NET AMT
Section E - Inspection and Acceptance
INSPECTION AND ACCEPTANCE TERMS
Supplies/services will be inspected/accepted at:
CLIN INSPECT AT INSPECT BY ACCEPT AT ACCEPT BY
0001 Destination Government Destination Government
CLAUSES INCORPORATED BY REFERENCE
52.246-12 Inspection of Construction AUG 1996
Section F - Deliveries or Performance
DELIVERY INFORMATION
CLIN DELIVERY DATE QUANTITY SHIP TO ADDRESS UIC
0001 210 Calendar Days
After the Issuance of the Notice to Proceed
1 1SOCES
MICHAEL TUOMINEN
415 INDEPENDENCE RD
HURLBURT FIELD FL 32544-5267
850-884-6025
FOB: Destination
F2F323
52.247-34 F.O.B. Destination NOV 1991
CLAUSES INCORPORATED BY FULL TEXT
52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984)
The Contractor shall be required to (a) commence work under this contract within 10 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 210 calendar days. The time stated for completion shall include final cleanup of the premises.
(End of clause)
52.211-12 LIQUIDATED DAMAGES--CONSTRUCTION (SEP 2000)
(a) If the Contractor fails to complete the work within the time specified in the contract, the Contractor shall pay liquidated damages to the Government in the amount of $155.06 for each calendar day of delay until the work is completed or accepted.
(b) If the Government terminates the Contractor's right to proceed, liquidated damages will continue to accrue until the work is completed. These liquidated damages are in addition to excess costs of repurchase under the Termination clause.
Section H - Special Contract Requirements
HF004 REQUIRED INSURANCE (IAW FAR 28.306(b))
Reference FAR clause entitled ―Insurance...‖ the Contractor shall, at its own expense, procure and thereafter maintain the following kinds of insurance with respect to performance under the contract. The Contractor will have the option to complete a form entitled ―Notification of Compliance with Contract Insurance Requirements‖ that will be provided by the Government at time of award, or to submit an insurance certificate before any work commences on the installation.
a. Workman’s Compensation and Employers Liability Insurance as required by law except that if this contract is to be performed in a state which does not require or permit private insurance, then compliance with the statutory or administrative requirements in any such state will be satisfactory. The required Workmen’s compensation insurance shall extend to cover employer’s liability for accidental bodily injury or death and for occupational diseases with a minimum liability limit of $100,000.00.
b. General Liability Insurance. Bodily injury liability insurance, in the minimum limits of $500,000.00 per occurrence shall be required on the comprehensive form of policy.
c. Automobile Liability Insurance. This insurance shall be required on the comprehensive form of policy and shall provide bodily injury liability and property damage liability covering the operation of all automobile used in connection with the performance of the contract. At least the minimum limits of $200,000.00 per person and
$500,000.00 per occurrence for bodily injury and $20,000 per occurrence for property damage shall be required.
HF005 EXCLUSION OF PAYMENT FOR MATERIALS STORED ON SITE
Payment in advance of installation, for materials stored on site, will not be considered under this contract.
HF009 DESIGNATION OF GOVERNMENT INSPECTOR
The Base Civil Engineer (or his/her authorized representative) is designated as the representative of the Contracting
Officer for purpose of serving as the Government's Construction Contract Inspector (CCI). This includes performing technical surveillance, including workmanship, and ensuring compliance with the plans and specifications under this contract. This provision in no way authorizes anyone other than the Contracting Officer to commit the Government to changes in the terms of this contract.
HF011 PREPARATION OF SCHEDULE FOR CONSTRUCTION CONTRACTS
The reports contemplated by clause entitled "Schedule for Construction Contracts" shall be accomplished on and in accordance with instructions pertaining to AF Form 3064 (Contract Progress Schedule) and AF Form 3065 (Contract
Progress Report).
HF012 POST-AWARD/PRE-PERFORMANCE CONFERENCE
A Pre-Performance Conference shall be conducted in accordance with FAR 52.236-26 (IAW FAR 36.522).
HF015 TELEPHONE COMSEC MONITORING
All communications with DOD organizations are subject to COMSEC review. Contractor personnel will be aware that telecommunications networks are continually subject to intercept by unfriendly intelligence organizations. The
DOD has authorized the military departments to conduct COMSEC monitoring and recording of telephone calls originating from or terminating at DOD organizations. Therefore, civilian contractor personnel are advised that any time they place a call to or receive a call from a military organization, they are subject to COMSEC procedures. The contractor will assume the responsibility for ensuring wide and frequent dissemination of the above information to all employees dealing with official DOD information.
HF016 AVAILABILITY OF UTILITIES SERVICES
Notwithstanding provisions of Contract Clause, FAR 52.236-14, "AVAILABILITY AND USE OF UTILITY
SERVICES," reasonable required amounts of water, gas, electricity, etc., essential to contract performance, will be made available at no cost to the contractor from existing systems, outlets, and supplies. Temporary connections, outlets, and distribution lines as required shall be installed by the contractor at his own expense.
HF017 VEHICLE OPERATION AND REGISTRATION
The prime contractor is responsible for all employees or sub-contracting employees performing duties on the Air
Force installation cited in the contract. The contractor shall obtain base identification and a vehicle pass for all contractor personnel who make frequent visits to or perform work while on the Air Force installation cited in the contract. Upon receipt of award, the contractor will be provided a letter signed by the Contracting Officer to be taken to the Pass and Registration section to obtain a visitor pass.
HF018 HOURS OF WORK
Normal hours of work on Hurlburt Field are 7:00 AM to 4:00 PM (CST), Monday through Friday, excluding holidays. Access to work sites is restricted to these hours and days unless otherwise approved by the Contracting
Officer three (3) workdays in advance.
HF019 INSTALLATION RULES AND REGULATIONS
Rules and regulations of Hurlburt Field apply to all contractors and their employees. Regulations include, but are not limited to, presenting valid picture identification for base entrance, obtaining and using vehicle passes for all contractor-owned and/or privately owned vehicles, obeying all posted directives, and strictly adhering to security police direction where security police have been dispatched to a particular location.
HF020 HURRICANE SEASON
Hurricane season for the state of Florida is normally the period from 1 June through 30 November. During an actual hurricane condition, you may be contacted by this office and requested to secure equipment and clean up your work area. In accordance with contracts clauses FAR 52.236-9 and FAR 52.236-12, you are required to maintain your work area free of debris and in a safe and secure condition at the completion of each workday, with particular care during the hurricane season.
HF029 WORK BY THE GOVERNMENT OR OTHERS
The government reserves the right to undertake performance by government forces or other contractors the same type or similar work as the government deems necessary or desirable and to do so will not breach or otherwise violate this contract.
HF037 WIDE AREA WORK FLOW DODAAC AND EMAIL DISTRIBUTION TABLE
DFARS 252.232-7003 Electronic Submission of Payment Requests applies to this contract.
USE OF WAWF IS MANDATORY – Requests for payment shall be processed electronically via the Wide Area
Work Flow (WAWF) system. There are no charges or fees to use WAWF. If you are not currently registered with
WAWF, contact the WAWF Help Desk at 1-866-618-5988 or 1-801-605-7095. Web Based Training is located at http://www.wawftraining.com/ and a live training database is located at https://wawftraining.eb.mil/. For specific questions, contact your administrator listed on the front of this contract.
Questions concerning payment should be directed to the Defense Finance Accounting Services (DFAS) Limestone at
1-800-390-5620 or faxed to 1-866-392-7091. You must have your contract number and invoice number ready when inquiring about payment status. Payment information can also be accessed at the DFAS web site:
http://www.dfas.mil.
The following codes will be required to route your invoices and emails through WAWF.
CAGE CODE:
ISSUE DODAAC: FA4417
ADMIN DODAAC: FA4417
INSPECT BY DODAAC: F2F332
SERVICE ACCEPTOR: F2F332
SHIP-TO CODE: F2F323
PAY DODAAC: F67100
FSC CODE: Z199
EMAIL POINT OF CONTACT LISTING: (Send emails to the following personnel):
SERVICE ACCEPTOR: michael.tuominen@hurlburt.af.mil
CONTRACT ADMINISTRATOR: timothy.thulin@hurlburt.af.mil
CONTRACTING OFFICER: michael.carnley@hurlburt.af.mil http://www.wawftraining.com/ https://wawftraining.eb.mil/ http://www.dfas.mil/ mailto:michael.tuominen@hurlburt.af.mil mailto:timothy.thulin@hurlburt.af.mil mailto:michael.carnley@hurlburt.af.mil
ADDITIONAL CONTACTS:
TYPE OF INVOICE: Recommend using the type of invoice indicated with "X" below:
__ Invoice as 2-in-1 (Recommended for Services)
__ Invoice and Receiving Report (Combo) (Recommended for Supplies)
_x_ Construction (NOTE: Invoices to be submitted only AFTER receipt of approved AF Form 3065, Contract Progress Report)
HF038 BASE RECYCLE PROGRAM
The contractor shall support and comply with all requirements of the Hurlburt Field Qualified Recycling Program
(QRP). The following instruction outlines procedures for the collection and handling of applicable recyclable materials:
Hurlburt Field Instruction (HFI) 32-7002 ―Qualified Recycling Program‖ dated 1 May 2002 – contact
1SOCES/CEV, 884-7964 for current copy
PROCESSING APPROVAL AND REPORTING USAGE OF HAZARDOUS MATERIALS ON HURLBURT
FIELD
Contractor shall comply with ALL rules and regulations for processing/using hazardous materials on Hurlburt Field, FL. The following regulations are applicable:
Air Force Instruction (AFI) 32-7086 ―Hazardous Materials Management‖ dated 1 Nov 2004
Download at: http://www.e-publishing.af.mil/pubfiles/af/32/afi32-7086/afi32-7086.pdf
Section I - Contract Clauses
52.202-1 Definitions JUL 2004
52.203-3 Gratuities APR 1984
52.203-5 Covenant Against Contingent Fees APR 1984
52.203-6 Restrictions On Subcontractor Sales To The Government SEP 2006
52.203-7 Anti-Kickback Procedures JUL 1995
52.203-8 Cancellation, Rescission, and Recovery of Funds for Illegal or
Improper Activity
JAN 1997
52.203-10 Price Or Fee Adjustment For Illegal Or Improper Activity JAN 1997
52.203-12 Limitation On Payments To Influence Certain Federal
Transactions
SEP 2007
52.204-4 Printed or Copied Double-Sided on Recycled Paper AUG 2000
52.204-6 Data Universal Numbering System (DUNS) Number APR 2008
52.204-7 Central Contractor Registration APR 2008
52.204-9 Personal Identity Verification of Contractor Personnel SEP 2007
52.209-6 Protecting the Government's Interest When Subcontracting
With Contractors Debarred, Suspended, or Proposed for
Debarment
SEP 2006
52.215-2 Audit and Records--Negotiation JUN 1999
52.215-8 Order of Precedence--Uniform Contract Format OCT 1997
52.219-8 Utilization of Small Business Concerns MAY 2004
52.219-14 Limitations On Subcontracting DEC 1996
52.219-28 Post-Award Small Business Program Rerepresentation JUN 2007
52.222-1 Notice To The Government Of Labor Disputes FEB 1997
52.222-3 Convict Labor JUN 2003
52.222-4 Contract Work Hours and Safety Standards Act - Overtime
Compensation
JUL 2005
52.222-5 Davis-Bacon Act--Secondary Site of the Work JUL 2005
52.222-6 Davis Bacon Act JUL 2005
52.222-7 Withholding of Funds FEB 1988
52.222-8 Payrolls and Basic Records FEB 1988
52.222-9 Apprentices and Trainees JUL 2005
52.222-10 Compliance with Copeland Act Requirements FEB 1988
52.222-11 Subcontracts (Labor Standards) JUL 2005
52.222-12 Contract Termination-Debarment FEB 1988
52.222-13 Compliance with Davis-Bacon and Related Act Regulations. FEB 1988
52.222-14 Disputes Concerning Labor Standards FEB 1988
52.222-15 Certification of Eligibility FEB 1988
52.222-21 Prohibition Of Segregated Facilities FEB 1999
52.222-26 Equal Opportunity MAR 2007
52.222-27 Affirmative Action Compliance Requirements for
Construction
FEB 1999
52.222-35 Equal Opportunity For Special Disabled Veterans, Veterans of the Vietnam Era, and Other Eligible Veterans
SEP 2006
52.222-36 Affirmative Action For Workers With Disabilities JUN 1998
52.222-37 Employment Reports On Special Disabled Veterans, Veterans
Of The Vietnam Era, and Other Eligible Veterans
SEP 2006
52.223-3 Hazardous Material Identification And Material Safety Data JAN 1997
52.223-5 Pollution Prevention and Right-to-Know Information AUG 2003
52.223-6 Drug-Free Workplace MAY 2001
52.223-13 Certification of Toxic Chemical Release Reporting AUG 2003
52.227-1 Authorization and Consent DEC 2007
52.227-2 Notice And Assistance Regarding Patent And Copyright
Infringement
DEC 2007
52.227-4 Patent Indemnity-Construction Contracts DEC 2007
52.228-2 Additional Bond Security OCT 1997
52.228-5 Insurance - Work On A Government Installation JAN 1997
52.228-11 Pledges Of Assets FEB 1992
52.228-12 Prospective Subcontractor Requests for Bonds OCT 1995
52.228-14 Irrevocable Letter of Credit DEC 1999
52.228-15 Performance and Payment Bonds--Construction NOV 2006
52.229-4 Federal, State, And Local Taxes (State and Local
Adjustments)
APR 2003
52.232-5 Payments under Fixed-Price Construction Contracts SEP 2002
52.232-17 Interest OCT 2008
52.232-23 Assignment Of Claims JAN 1986
52.232-27 Prompt Payment for Construction Contracts OCT 2008
52.232-33 Payment by Electronic Funds Transfer--Central Contractor
Registration
OCT 2003
52.233-1 Disputes JUL 2002
52.233-3 Protest After Award AUG 1996
52.233-4 Applicable Law for Breach of Contract Claim OCT 2004
52.236-2 Differing Site Conditions APR 1984
52.236-3 Site Investigation and Conditions Affecting the Work APR 1984
52.236-5 Material and Workmanship APR 1984
52.236-6 Superintendence by the Contractor APR 1984
52.236-7 Permits and Responsibilities NOV 1991
52.236-8 Other Contracts APR 1984
52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements
APR 1984
52.236-10 Operations and Storage Areas APR 1984
52.236-11 Use and Possession Prior to Completion APR 1984
52.236-12 Cleaning Up APR 1984
52.236-13 Accident Prevention NOV 1991
52.236-14 Availability and Use of Utility Services APR 1984
52.236-15 Schedules for Construction Contracts APR 1984
52.236-17 Layout of Work APR 1984
52.236-21 Specifications and Drawings for Construction FEB 1997
52.236-21 Alt I Specifications and Drawings for Construction (Feb 1997) -
Alternate I
APR 1984
52.236-26 Preconstruction Conference FEB 1995
52.242-13 Bankruptcy JUL 1995
52.242-14 Suspension of Work APR 1984
52.243-4 Changes JUN 2007
52.244-5 Competition In Subcontracting DEC 1996
52.244-6 Subcontracts for Commercial Items DEC 2008
52.246-21 Warranty of Construction MAR 1994
52.248-3 Value Engineering-Construction SEP 2006
52.249-2 Termination For Convenience Of The Government (Fixed-
Price)
MAY 2004
52.249-2 Alt I Termination for Convenience of the Government (Fixed-
Price) (May 2004) - Alternate I
SEP 1996
52.249-10 Default (Fixed-Price Construction) APR 1984
52.253-1 Computer Generated Forms JAN 1991
252.201-7000 Contracting Officer's Representative DEC 1991
252.203-7001 Prohibition On Persons Convicted of Fraud or Other Defense-
Contract-Related Felonies
DEC 2008
252.204-7003 Control Of Government Personnel Work Product APR 1992
252.204-7004 Alt A Central Contractor Registration (52.204-7) Alternate A SEP 2007
252.204-7006 Billing Instructions OCT 2005
252.209-7004 Subcontracting With Firms That Are Owned or Controlled By
The Government of a Terrorist Country
DEC 2006
252.219-7011 Notification to Delay Performance JUN 1998
252.223-7001 Hazard Warning Labels DEC 1991
252.223-7006 Prohibition On Storage And Disposal Of Toxic And
Hazardous Materials
APR 1993
252.225-7012 Preference For Certain Domestic Commodities DEC 2008
252.227-7033 Rights in Shop Drawings APR 1966
252.231-7000 Supplemental Cost Principles DEC 1991
252.232-7003 Electronic Submission of Payment Requests and Receiving
Reports
MAR 2008
252.232-7010 Levies on Contract Payments DEC 2006
252.236-7000 Modification Proposals-Price Breakdown DEC 1991
252.243-7001 Pricing Of Contract Modifications DEC 1991
252.243-7002 Requests for Equitable Adjustment MAR 1998
252.244-7000 Subcontracts for Commercial Items and Commercial
Components (DoD Contracts)
JAN 2009
252.247-7023 Transportation of Supplies by Sea MAY 2002
252.247-7024 Notification Of Transportation Of Supplies By Sea MAR 2000
52.203-15 WHISTLEBLOWER PROTECTIONS UNDER THE AMERICAN RECOVERY AND
REINVESTMENT ACT OF 2009 (MAR 2009)
(a) The Contractor shall post notice of employees rights and remedies for whistleblower protections provided under section 1553 of the American Recovery and Reinvestment Act of 2009 (Pub. L. 111-5).
(b) The Contractor shall include the substance of this clause including this paragraph (b) in all subcontracts.
52.204-11 AMERICAN RECOVERY AND REINVESTMENT ACT-REPORTING REQUIREMENTS (MAR
2009)
(a) Definitions. As used in this clause—
Contract, as defined in FAR 2.101, means a mutually binding legal relationship obligating the seller to furnish the supplies or services (including construction) and the buyer to pay for them. It includes all types of commitments that obligate the Government to an expenditure of appropriated funds and that, except as otherwise authorized, are in writing. In addition to bilateral instruments, contracts include (but are not limited to) awards and notices of awards;
job orders or task letters issued under basic ordering agreements; letter contracts; orders, such as purchase orders, under which the contract becomes effective by written acceptance or performance; and bilateral contract modifications. Contracts do not include grants and cooperative agreements covered by 31 U.S.C. 6301, et seq. For discussion of various types of contracts, see FAR Part 16.
First-tier subcontract means a subcontract awarded directly by a Federal Government prime contractor whose contract is funded by the Recovery Act.
Jobs created means an estimate of those new positions created and filled, or previously existing unfilled positions that are filled, as a result of funding by the American Recovery and Reinvestment Act of 2009 (Recovery Act). This definition covers only prime contractor positions established in the United States and outlying areas (see definition in
FAR 2.101). The number shall be expressed as ―full-time equivalent‖ (FTE), calculated cumulatively as all hours worked divided by the total number of hours in a full-time schedule, as defined by the contractor. For instance, two full-time employees and one part-time employee working half days would be reported as 2.5 FTE in each calendar quarter.
Jobs retained means an estimate of those previously existing filled positions that are retained as a result of funding by the American Recovery and Reinvestment Act of 2009 (Recovery Act). This definition covers only prime contractor positions established in the United States and outlying areas (see definition in FAR 2.101). The number shall be expressed as ―full-time equivalent‖ (FTE), calculated cumulatively as all hours worked divided by the total number of hours in a full-time schedule, as defined by the contractor. For instance, two full-time employees and one part-time employee working half days would be reported as 2.5 FTE in each calendar quarter.
Total compensation means the cash and noncash dollar value earned by the executive during the contractor’s past fiscal year of the following (for more information see 17 CFR 229.402(c)(2)):
(1) Salary and bonus.
(2) Awards of stock, stock options, and stock appreciation rights. Use the dollar amount recognized for financial statement reporting purposes with respect to the fiscal year in accordance with the Statement of Financial Accounting
Standards No. 123 (Revised 2004) ( FAS 123R), Shared Based Payments.
(3) Earnings for services under non-equity incentive plans. Does not include group life, health, hospitalization or medical reimbursement plans that do not discriminate in favor of executives, and are available generally to all salaried employees.
(4) Change in pension value. This is the change in present value of defined benefit and actuarial pension plans.
(5) Above-market earnings on deferred compensation which is not tax-qualified.
(6). Other compensation. For example, severance, termination payments, value of life insurance paid on behalf of the employee, perquisites or property if the value for the executive exceeds $10,000.
(b) This contract requires the contractor to provide products and/or services that are funded under the American
Recovery and Reinvestment Act of 2009 (Recovery Act). Section 1512(c) of the Recovery Act requires each contractor to report on its use of Recovery Act funds under this contract. These reports will be made available to the public.
(c) Reports from contractors for all work funded, in whole or in part, by the Recovery Act, and for which an invoice is submitted prior to June 30, 2009, are due no later than July 10, 2009. Thereafter, reports shall be submitted no later than the 10th day after the end of each calendar quarter.
(d) The Contractor shall report the following information, using the online reporting tool available at www.FederalReporting.gov.
(1) The Government contract and order number, as applicable.
(2) The amount of Recovery Act funds invoiced by the contractor for the reporting period. A cumulative amount from all the reports submitted for this action will be maintained by the government's on-line reporting tool.
(3) A list of all significant services performed or supplies delivered, including construction, for which the contractor invoiced in this calendar quarter.
(4) Program or project title, if any.
(5) A description of the overall purpose and expected outcomes or results of the contract, including significant deliverables and, if appropriate, associated units of measure.
(6) An assessment of the contractor’s progress towards the completion of the overall purpose and expected outcomes or results of the contract (i.e., not started, less than 50 percent completed, completed 50 percent or more, or fully completed). This covers the contract (or portion thereof) funded by the Recovery Act.
(7) A narrative description of the employment impact of work funded by the Recovery Act. This narrative should be cumulative for each calendar quarter and only address the impact on the contractor’s workforce. At a minimum, the contractor shall provide—
(i) A brief description of the types of jobs created and jobs retained in the United States and outlying areas (see definition in FAR 2.101). This description may rely on job titles, broader labor categories, or the contractor’s existing practice for describing jobs as long as the terms used are widely understood and describe the general nature of the work; and
(ii) An estimate of the number of jobs created and jobs retained by the prime contractor, in the United States and outlying areas. A job cannot be reported as both created and retained.
(8) Names and total compensation of each of the five most highly compensated officers of the Contractor for the calendar year in which the contract is awarded if—
(i) In the Contractor’s preceding fiscal year, the Contractor received—
(A) 80 percent or more of its annual gross revenues from Federal contracts (and subcontracts), loans, grants (and subgrants) and cooperative agreements; and
(B) $25,000,000 or more in annual gross revenues from Federal contracts (and subcontracts), loans, grants (and subgrants) and cooperative agreements; and
(ii) The public does not have access to information about the compensation of the senior executives through periodic reports filed under section 13(a) or 15(d) of the Securities Exchange Act of 1934 (15 U.S.C. 78m(a), 78o(d)) or section 6104 of the Internal Revenue Code of 1986.
(9) For subcontracts valued at less than $25,000 or any subcontracts awarded to an individual, or subcontracts awarded to a subcontractor that in the previous tax year had gross income under $300,000, the Contractor shall only report the aggregate number of such first tier subcontracts awarded in the quarter and their aggregate total dollar amount.
(10) For any first-tier subcontract funded in whole or in part under the Recovery Act, that is over $25,000 and not subject to reporting under paragraph 9, the contractor shall require the subcontractor to provide the information described in (i), (ix), (x), and (xi) below to the contractor for the purposes of the quarterly report. The contractor shall advise the subcontractor that the information will be made available to the public as required by section 1512 of the Recovery Act. The contractor shall provide detailed information on these first-tier subcontracts as follows:
(i) Unique identifier (DUNS Number) for the subcontractor receiving the award and for the subcontractor’s parent company, if the subcontractor has a parent company.
(ii) Name of the subcontractor.
(iii) Amount of the subcontract award.
(iv) Date of the subcontract award.
(v) The applicable North American Industry Classification System (NAICS) code.
(vi) Funding agency.
(vii) A description of the products or services (including construction) being provided under the subcontract, including the overall purpose and expected outcomes or results of the subcontract.
(viii) Subcontract number (the contract number assigned by the prime contractor).
(ix) Subcontractor’s physical address including street address, city, state, and country. Also include the nine-digit zip code and congressional district if applicable.
(x) Subcontract primary performance location including street address, city, state, and country. Also include the nine-digit zip code and congressional district if applicable.
(xi) Names and total compensation of each of the subcontractor’s five most highly compensated officers, for the calendar year in which the subcontract is awarded if—
(A) In the subcontractor’s preceding fiscal year, the subcontractor received—
(l) 80 percent or more of its annual gross revenues in Federal contracts (and subcontracts), loans, grants (and subgrants), and cooperative agreements; and
(2) $25,000,000 or more in annual gross revenues from Federal contracts (and subcontracts), loans, grants (and subgrants), and cooperative agreements; and
(B) The public does not have access to information about the compensation of the senior executives through periodic reports filed under section 13(a) or 15(d) of the Securities Exchange Act of 1934 (15 U.S.C. 78m(a), 78o(d)) or section 6104 of the Internal Revenue Code of 1986.
52.215-2 AUDIT AND RECORDS--NEGOTIATION (MAR 2009)
(a) As used in this clause, "records" includes books, documents, accounting procedures and practices, and other data, regardless of type and regardless of whether such items are in written form, in the form of computer data, or in any other form.
(b) Examination of costs. If this is a cost-reimbursement, incentive, time-and-materials, labor-hour, or price redeterminable contract, or any combination of these, the Contractor shall maintain and the Contracting Officer, or an authorized representative of the Contracting Officer, shall have the right to examine and audit all records and other evidence sufficient to reflect properly all costs claimed to have been incurred or anticipated to be incurred directly or indirectly in performance of this contract. This right of examination shall include inspection at all reasonable times of the Contractor's plants, or parts of them, engaged in performing the contract.
(c) Cost or pricing data. If the Contractor has been required to submit cost or pricing data in connection with any pricing action relating to this contract, the Contracting Officer, or an authorized representative of the Contracting
Officer, in order to evaluate the accuracy, completeness, and currency of the cost or pricing data, shall have the right to examine and audit all of the Contractor's records, including computations and projections, related to--
(1) The proposal for the contract, subcontract, or modification;
(2) The discussions conducted on the proposal(s), including those related to negotiating;
(3) Pricing of the contract, subcontract, or modification; or
(4) Performance of the contract, subcontract or modification.
(d) Comptroller General. (1) The Comptroller General of the United States, or an authorized representative, shall have access to and the right to examine any of the Contractor’s directly pertinent records involving transactions related to this contract or a subcontract hereunder and to interview any current employee regarding such transactions.
(2) This paragraph may not be construed to require the Contractor or subcontractor to create or maintain any record that the Contractor or subcontractor does not maintain in the ordinary course of business or pursuant to a provision of law.
(e) Reports. If the Contractor is required to furnish cost, funding, or performance reports, the Contracting Officer or an authorized representative of the Contracting Officer shall have the right to examine and audit the supporting records and materials, for the purpose of evaluating (1) the effectiveness of the Contractor's policies and procedures to produce data compatible with the objectives of these reports and (2) the data reported.
(f) Availability. The Contractor shall make available at its office at all reasonable times the records, materials, and other evidence described in paragraphs (a), (b), (c), (d), and (e) of this clause, for examination, audit, or reproduction, until 3 years after final payment under this contract or for any shorter period specified in Subpart 4.7, Contractor Records Retention, of the Federal Acquisition Regulation (FAR), or for any longer period required by statute or by other clauses of this contract. In addition--
(1) If this contract is completely or partially terminated, the Contractor shall make available the records relating to the work terminated until 3 years after any resulting final termination settlement; and
(2) The Contractor shall make available records relating to appeals under the Disputes clause or to litigation or the settlement of claims arising under or relating to this contract until such appeals, litigation, or claims are finally resolved.
(g) The Contractor shall insert a clause containing all the terms of this clause, including this paragraph (g), in all subcontracts under this contract that exceed the simplified acquisition threshold, and--
(1) That are cost-reimbursement, incentive, time-and-materials, labor-hour, or price-redeterminable type or any combination of these;
(2) For which cost or pricing data are required; or
(3) That require the subcontractor to furnish reports as discussed in paragraph (e) of this clause.
The clause may be altered only as necessary to identify properly the contracting parties and the Contracting Officer under the Government prime contract.
52.219-28 POST-AWARD SMALL BUSINESS PROGRAM REREPRESENTATION (JUNE 2007)
(a) Definitions. As used in this clause--
Long-term contract means a contract of more than five years in duration, including options. However, the term does not include contracts that exceed five years in duration because the period of performance has been extended for a cumulative period not to exceed six months under the clause at 52.217-8, Option to Extend Services, or other appropriate authority.
Small business concern means a concern, including its affiliates, that is independently owned and operated, not dominant in the field of operation in which it is bidding on Government contracts, and qualified as a small business under the criteria in 13 CFR part 121 and the size standard in paragraph (c) of this clause.
(b) If the Contractor represented that it was a small business concern prior to award of this contract, the Contractor shall rerepresent its size status according to paragraph (e) of this clause or, if applicable, paragraph (g) of this clause, upon the occurrence of any of the following:
(1) Within 30 days after execution of a novation agreement or within 30 days after modification of the contract to include this clause, if the novation agreement was executed prior to inclusion of this clause in the contract.
(2) Within 30 days after a merger or acquisition that does not require a novation or within 30 days after modification of the contract to include this clause, if the merger or acquisition occurred prior to inclusion of this clause in the contract.
(3) For long-term contracts--
(i) Within 60 to 120 days prior to the end of the fifth year of the contract; and
(ii) Within 60 to 120 days prior to the exercise date specified in the contract for any option thereafter.
(c) The Contractor shall rerepresent its size status in accordance with the size standard in effect at the time of this rerepresentation that corresponds to the North American Industry Classification System (NAICS) code assigned to this contract. The small business size standard corresponding to this NAICS code can be found at http://www.sba.gov/services/contractingopportunities/sizestandardstopics/.
(d) The small business size standard for a Contractor providing a product which it does not manufacture itself, for a contract other than a construction or service contract, is 500 employees.
(e) Except as provided in paragraph (g) of this clause, the Contractor shall make the rerepresentation required by paragraph (b) of this clause by validating or updating all its representations in the Online Representations and
Certifications Application and its data in the Central Contractor Registration, as necessary, to ensure they reflect current status. The Contractor shall notify the contracting office by e-mail, or otherwise in writing, that the data have been validated or updated, and provide the date of the validation or update.
(f) If the Contractor represented that it was other than a small business concern prior to award of this contract, the
Contractor may, but is not required to, take the actions required by paragraphs (e) or (g) of this clause.
(g) If the Contractor does not have representations and certifications in ORCA, or does not have a representation in
ORCA for the NAICS code applicable to this contract, the Contractor is required to complete the following rerepresentation and submit it to the contracting office, along with the contract number and the date on which the rerepresentation was completed:
The Contractor represents that it ( ) is, ( ) is not a small business concern under NAICS Code 236210 - assigned to contract number .
(Contractor to sign and date and insert authorized signer's name and title).
52.223-9 ESTIMATE OF PERCENTAGE OF RECOVERED MATERIAL CONTENT FOR EPA-
DESIGNATED ITEMS (MAY 2008)
(a) Definitions. As used in this clause--
Postconsumer material means a material or finished product that has served its intended use and has been discarded for disposal or recovery, having completed its life as a consumer item. Postconsumer material is a part of the broader category of ―recovered material.‖
Recovered material means waste materials and by-products recovered or diverted from solid waste, but the term does not include those materials and by-products generated from, and commonly reused within, an original manufacturing process.
(b) The Contractor, on completion of this contract, shall--
(1) Estimate the percentage of the total recovered material content for EPA-designated item(s) delivered and/or used in contract performance, including, if applicable, the percentage of post-consumer material content; and
(2) Submit this estimate to:
1 SOCONS/LGCB
350 Tully Street
Hurlburt Field, FL 32544
52.225-21 REQUIRED USE OF AMERICAN IRON, STEEL, AND OTHER MANUFACTURED GOODS—
BUY AMERICAN ACT—CONSTRUCTION MATERIALS (MAR 2009)
(a) Definitions. As used in this clause—
Construction material means an article, material, or supply brought to the construction site by the Contractor or a subcontractor for incorporation into the building or work. The term also includes an item brought to the site preassembled from articles, materials, or supplies. However, emergency life safety systems, such as emergency lighting, fire alarm, and audio evacuation systems, that are discrete systems incorporated into a public building or work and that are produced as complete systems, are evaluated as a single and distinct construction material regardless of when or how the individual parts or components of those systems are delivered to the construction site.
Materials purchased directly by the Government are supplies, not construction material.
Domestic construction material means—
(1) An unmanufactured construction material mined or produced in the United States; or
(2) A construction material manufactured in the United States.
Foreign construction material means a construction material other than a domestic construction material.
Manufactured construction material means any construction material that is not unmanufactured construction material.
Steel means an alloy that includes at least 50 percent iron, between .02 and 2 percent carbon, and may include other elements.
United States means the 50 States, the District of Columbia, and outlying areas.
Unmanufactured construction material means raw material brought to the construction site for incorporation into the building or work that has not been—
(1) Processed into a specific form and shape; or
(2) Combined with other raw material to create a material that has different properties than the properties of the individual raw materials.
(b) Domestic preference.
(1) This clause implements—
(i) Section 1605 of the American Recovery and Reinvestment Act of 2009 (Recovery Act) (Pub. L. 111-5), by requiring, unless an exception applies, that all iron, steel, and other manufactured goods used as construction material in the project are produced in the United States; and
(ii) The Buy American Act (41 U.S.C. 10a - 10d) by providing a preference for unmanufactured domestic construction material.
(2) The Contractor shall use only domestic construction material in performing this contract, except as provided in paragraph (b)(3) and (b)(4) of this clause.
(3) This requirement does not apply to the construction material or components listed by the Government as follows:
(Contracting Officer to list applicable excepted materials or indicate ―none‖)
(4) The Contracting Officer may add other foreign construction material to the list in paragraph (b)(3) of this clause if the Government determines that—
(i) The cost of domestic construction material would be unreasonable.
(A) The cost of domestic iron, steel, or other manufactured goods used as construction material is unreasonable when the cumulative cost of such material will increase the cost of the contract by more than 25 percent;
(B) The cost of unmanufactured construction material is unreasonable when the cost of such material exceeds the cost of foreign material by more than 6 percent;
(ii) The construction material is not mined, produced, or manufactured in the United States in sufficient and reasonably available quantities and of a satisfactory quality; or
(iii) The application of the restriction of section 1605 of the Recovery Act or the Buy American Act to a particular construction material would be inconsistent with the public interest.
(c) Request for determination of inapplicability of Section 1605 of the Recovery Act or the Buy American Act.
(1)(i) Any Contractor request to use foreign construction material in accordance with paragraph (b)(4) of this clause shall include adequate information for Government evaluation of the request, including—
(A) A description of the foreign and domestic construction materials;
(B) Unit of measure;
(C) Quantity;
(D) Cost;
(E) Time of delivery or availability;
(F) Location of the construction project;
(G) Name and address of the proposed supplier; and
(H) A detailed justification of the reason for use of foreign construction materials cited in accordance with paragraph (b)(4) of this clause.
(ii) A request based on unreasonable cost shall include a reasonable survey of the market and a completed cost comparison table in the format in paragraph (d) of this clause.
(iii) The cost of construction material shall include all delivery costs to the construction site and any applicable duty.
(iv) Any Contractor request for a determination submitted after contract award shall explain why the Contractor could not reasonably foresee the need for such determination and could not have requested the determination before contract award. If the Contractor does not submit a satisfactory explanation, the Contracting Officer need not make a determination.
(2) If the Government determines after contract award that an exception to section 1605 of the Recovery Act or the
Buy American Act applies and the Contracting Officer and the Contractor negotiate adequate consideration, the
Contracting Officer will modify the contract to allow use of the foreign construction material. However, when the basis for the exception is the unreasonable cost of a domestic construction material, adequate consideration is not less than the differential established in paragraph (b)(4)(i) of this clause.
(3) Unless the Government determines that…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .