BLDG_500_-_SOW_(Amend_1).pdf

PDF 510 KB Posted

Attached to
Building Demolitions (bldgs 155, 500, 4900) Federal contract opportunity
Solicitation number
FA440717R0007
Issued by
Department of the Air Force Air Mobility Command

About this file

CLIN 0002 Amended SOW

View the file

Other files for this federal contract opportunity

Other files attached to Building Demolitions (bldgs 155, 500, 4900), newest first.
File Type Posted
POOL_&_BLDG_155_-_SOW_(Amend_1).pdf PDF
RFI_2.pdf PDF
FA4407-17-R-0007_(Amendment_1).pdf PDF
Building_4900_-_SOW_(Amend_1).pdf PDF
Site_Visit_Sheet.pdf PDF
Building_500_Storage_Tank_Report.pdf PDF
Building_4900_-_Soil_Sample_Report.pdf PDF
Building_500_-_Well_Construction_Report.pdf PDF
Building_4900_-_Asbestos_&_Lead_Survey.pdf PDF
Building_500_-_Soil_Sample_Report.pdf PDF
RFI_1.pdf PDF
Attach_6_-_Past_Performance_Questionnaire.pdf PDF
FA4407-17-R-0007_Solicitation.pdf PDF
Attach_2_-_CLIN_0002_SOW.pdf PDF
Attach_1_-_CLIN_0001_SOW.pdf PDF
Attach_5_-_General_Requirements.pdf PDF
Attach_3_-_CLIN_0003_SOW.pdf PDF
Attach_4_-_Wage_Determination.pdf PDF
Show all 18

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK FOR

BETM 130000

DEMOLISH MARS FACILITY Building 500

AT

SCOTT AIR FORCE BASE PLUM HILL ANNEX, ILLINOIS

375TH CIVIL ENGINEER SQUADRON

11 September 2017

I. Description of Work: The work consists of furnishing all labor, materials, equipment, transportation, and supervision necessary to demolish Building 500 and surrounding area to provide a clean site at the Plum Hill Annex.

A. Contractor shall submit an abatement plan for review and approval, which will subsequently be submitted to the Illinois Environmental Protection Agency for notification purposes. A 10-day notification period is required prior to starting any abatement work.

1. Contractor shall comply with all federal, state and local regulations for the abatement and disposal of hazardous materials.

2. All documents related to the disposal of hazardous material must be supplied to the contracting office and to the 375th Civil Engineer Squadron, Installation

Management Flight, Environmental Compliance Section (375 CES/CEIEC), 618-256-

2092. The Contractor must obtain the proper documents from 375 CES/CEIEC to ensure all materials leaving Scott AFB Annex (Plum Hill Site) can be tracked and accounted for, in accordance with all governing laws. The contractor shall supply 375

CES/CEIEC with weights of materials disposed of at landfill and a list of materials with weights recycled, including those taken to the base’s recycling center.

B. Demolition

1. The contractor shall be responsible for the complete demolition of Building 500, the MARS Facility. The building is approximately 3,519 square feet, 1 story, CMU structure with a 5-ply, metal deck roof with bar joists. Work includes demolition and disposal of structure, foundation, slab and fixtures.

2. Removal of 18 utility poles and associated guy wires. Some poles have been preserved with creosote. Accordingly, all poles must be removed to their full depth.

3. Cutting creosote-preserved poles at ground level and abandoning the buried portion is not acceptable.

4. Removal of approximately 54 utility pole anchors

5. Removal of detached shed.

6. Removal of all concrete and blacktop pads.

7. Removal of all mechanical equipment and transformer.

8. Removal of existing brush on property and along fence line.

9. Fence, gate, and blacktop drive are to remain. The fabric may be replaced as long as none of the poles are removed. They identify the boundries of the government site and eliminating any of them could cause boundry disputes with the local farmers.

(submit as an alternate).

C. Well Abandonment

1. The contractor shall be responsible for the complete abandonment of a drinking water well on the Plum Hill Annex property. Well abandonment will be performed in accordance with state and local laws and regulations.

2. Monitoring wells will be abandoned in accordance with 77 IAC Part

920.120. Water wells must be sealed within 30 days after abandonment and must be sealed by a licensed water well driller pursuant to the Water Well and Pump

Installation Contractor's License Act. The submersible pump, drop pipe, pressure tank, and associated electrical components shall be removed from the well. The well casing or liner shall be removed to at least three feet below final grade. The well shall be sealed in accordance with 77 IAC Part 920.120(b) (3) (A), which applies to unconsolidated formations. (Reference attached Well Construction

Report accordingly on the FBO site.

3. If slurry is used, a mud balance and/or Marsh Funnel will be used to ensure that the density (pounds per gallon) of the abandonment mud mixture conforms to the manufacturer's specification. The grout will be placed by tremie pipe, submerged in the grout at all times. The tremie pipe may be raised as the grout is placed as long as the discharge end remains submerged in the grout. The grout will be placed from the bottom to the top of the hole in one continuous operation. All abandoned monitoring wells will be checked 24 to 48 hours after mud/solid bentonite emplacement to determine whether curing is occurring properly. More specific curing specifications or quality assurance checks may be recommended by the manufacturer and will be followed. Additionally, if significant settling has occurred, a sufficient amount of mud/solid bentonite will be added to attain its initial level. These slurry/solid bentonite curing checks and any addition of mud/solid bentonite will be recorded in the field logs.

4. The Illinois Department of Public Health will be notified by telephone or in writing at least 48 hours prior to the commencement of any work to abandon a well. The individual performing the sealing shall submit a sealing form to the local health department not more than 30 days after the well is sealed.

Information required on the sealing form is provided in 77 IAC Part 120(e).

Below is the contact information for the St. Clair County Health Department:

5. St. Clair County Health Department

#19 Public Square, Suite 150

Belleville, IL 62220

(618) 233-7769 or email Jennifer.meyer@co.st-clair.il.us

D. Soil Grading and Disturbance

1. The contractor shall provide clean fill soil over the demolition site to match the existing surrounding grade, and grade any disturbed areas with an emphasis on proper drainage. All fill materials shall be non-contaminated with the proper documentation to demonstrate as such, and meet the requirements of 35 Illinois Administrative Code (IAC) 1100. Proposed amendments to 35 IAC 1100, the Clean Construction or Demolition Debris (CCDD) Fill Operations, can be tracked on the Illinois Pollution Control Board website

(www.ipcb.state.il.us/COOL/external/PendingRulemakings.aspx).

2. Furnish and install IDOT specified Class 1 or 1B seed and fertilizer. (IDOT Article 250)

3. Furnish and install straw mulch ground cover. (IDOT Article 251)

4. Any soil disturbed as a result of any aspect of this project shall be containerized and sampled for contaminants. The contractor shall provide results of the sampling to the government. If soil is clean of contaminants, it becomes the property of the contractor. If soil is contaminated, it shall be disposed of at a licensed landfill. The contractor shall provide documentation that contaminated soil was handled and disposed of in accordance with federal, state, and local regulations. (This paragraph only applies to the creosote poles that will be removed and testing at each of the sites to determine the extent of possible contamination to the surrounding soils. Testing at each pole location shall be figured into the total cost and any contaminated removal may be addressed as a modification at a later date). For bidding purposes, due to our inability to know for certain if the soils are contaminated or not, assume that it is clean soil. After award, if there is contaminated soil discovered, it may be handled by a change order.

E. OBTAIN REGULATORY CLOSURE OF LEAKING UNDERGROUND

STORAGE TANK (LUST)

1. The contractor shall be responsible for obtaining a No Further Remediation letter from the Illinois Environmental Management Agency (IEMA) for Scott AFB’s Tank #87 LUST site (Illinois Emergency Management Agency (IEMA) Incident

#930373) IAW 35 Illinois Administrative Code (IAC) 734. (It is the contractors responsibility to close out the tank as provided by the reports that are on the FBO site.)

2. All plans and reports conducted and submitted to the IEPA pursuant to 35 IAC 734, Section 734.135 must contain the referenced certification from a Licensed Professional Engineer or Professional Geologist IAW the IAC.

3. Previous Tank Removal Report, Corrective Action Completion Report (CACR) for Tank #87, IEPA response letter to CACR, and October 2014 Plum Hill Soil and Well Sampling Report are included as attachments to this statement of work.

4. The requirement to record the No Further Remediation Letter with the Office of Recorder for St. Clair County will be completed by the government.

F. GENERAL NPDES PERMIT: Storm water discharge from a construction site requires a Notice of Intent (NOI) under the National Pollutant Discharge Elimination System (NPDES) to be submitted to the Illinois Environmental Protection Agency prior to any construction activities exceeding one acre. The scope of this project exceeds one acre. The NOI shall be signed, certified and stamped by an Illinois Registered Engineer and submitted electronically along with three (3) hardcopies to the 375th Civil Engineer Squadron, Installation Management Flight, Environmental Compliance Section

(CES/CEIEC) Water Permits manager for local coordination, and signatures. The final package will then be submitted by CEIEC to the Illinois Environmental Protection Agency Division of Water Pollution Control. General information, forms and instructions are available on-line at http://www.epa.state.il.us/water/forms.html. For specific questions and guidance contact the Water Permit manager at 618-256-2092. A Storm Water Pollution Prevention Plan (SWPPP) shall be developed for each construction site covered by the Notice of Intent. The SWPPP shall be prepared in accordance with good engineering practices. The SWPPP shall identify potential sources of pollution which may reasonably be expected to affect the quality of storm water discharges associated with construction site activities. In, addition, the SWPPP shall describe and ensure the implementation of best management practices which will be used to reduce the pollutants in storm water discharges associated with construction site activity and to assure compliance with the terms and conditions of the Notice of Intent.

G. Furnish testing (laboratory or on-site) and surveying services appropriate to perform all work listed above. (Only the testing of the soils surrounding the poles. No additional surveying or testing at this site would be required).

II. Accomplishment of Work:

A. Contractor shall site verify any and all dimensions and/or existing site conditions prior to the commencement of work. Commencement of work shall begin within ten (10) calendar days upon the receipt of the Notice to Proceed issued by the Contracting Officer after verifying that all communication equipment has been removed.

B. Contractor shall be required to apply for and submit to the Contracting Officer an

AF Form 103, Work Clearance Request, for all work to be accomplished under this delivery order five (5) days prior to the commencement of work. The AF Form 103 can be obtained from the project manager or inspector and approved by the 375th Civil

Engineer Squadron, Operations Support Element (375 CES/CEOE), 618-256-4710. This requirement will be coordinated with the project manager.

C. Contractor shall brief all sub-contractors on all safety and fire prevention regulations. Because the work site is located at a Scott AFB annex, an AF Form 592, Welding, Cutting, and Brazing Permit, is not required for welding, cutting, or brazing operations. The Contractor must abide by all local fire codes and ordinances. The 375th

Civil Engineer Squadron, Fire and Emergency Services Flight, Fire Prevention Office

(375 CES/CEFP), 618-256-5130, is available for fire prevention guidance, yet local fire district officials should also be consulted.

D. In accordance with the 1990 Amendments to the Clean Air Act, all products used in executing this project must not be related to the Class I Ozone Depleting Chemicals identified in Air Force Policy. The following products are considered Class I ODCs:

CFC-11, CFC-12, CFC-113, CFC-114, Halon 1211, Halon 1301, Halon 2402, CFC-13, CFC-111, CFC-112, CFC-211, CFC-212, CFC-213, CFC-214, CFC-215, CFC-216, CFC-217, Carbon Tetrachloride, and Methyl Chloroform.

E. Field Conditions: The Contractor shall be responsible for all field measurements to accomplish work. Quantity and sizes of materials shall be determined from site visits and drawings. The contractor shall carefully examine the entire site and building and shall make all necessary investigations to become thoroughly aware of the existing conditions.

F. Work Conditions: The contractor shall coordinate work with the Contracting

Officer. The Contractor shall notify the Contracting Officer or the inspection representative the day he/she moves onto the work site to commence work. The

Contractor shall again provide notification the day he/she returns to the work site after an interruption of work of two or more days. The Contractor shall also provide an original work schedule and updates if required. This schedule shall describe major work items and projected completion dates.

G. Protection of Property: The Contractor shall protect from damage all property not belonging to the government located adjacent to the work site, and the Contractor shall repair, replace or otherwise be held liable for all such damage. Private property includes, but is not limited to, vehicles, equipment, land, or items of supplies. Exercise control measures of all dust and toxic fumes associated with demolition operations, in order to prevent hazards or illness to the public. The Contractor is also liable for any damage to the site's fence or gate.

H. Upon completion of the work, all construction equipment and debris shall be removed from the site and the area shall be left in a neat and completely acceptable condition as required by the General Provisions.

I. Specifications: Work shall be performed in strict accordance with this contract’s general specifications, as well as all applicable local, state, and national Building and Life

Safety codes, American Disability Act (ADA) regulations, Illinois Department of

Transportation (IDOT) Specifications for Roadways and Bridges, National Roof

Contractor's Association specifications, and American Society for Testing and Materials

(ASTM) specifications. Safety issues must adhere to all applicable Occupational Safety and Health Act (OSHA) regulations, to include all other issues listed in the US Army

Corps of Engineers Safety and Health Requirements manual (EM 385-1-1).