Site Sustainment PWS for Vigilant Warrior Training Site

PERFORMANCE WORK STATEMENT

FOR

SITE SUSTAINMENT

MAXWELL AFB VIGILANT

WARRIOR TRAINING SITE

Reviewed:

Quality Assurance Program Coordinator

Date

Program Manager/Functional Commander

APPROVED:

Contracting Officer

Table of Contents Section Number and Title

Page Number

1.0 Description of Services

3-5

2.0 Service Summary

6-8

3.0 Government Furnished property and Services

9-10

4.0 General Information

10-13

5.0 APPENDICES

13-15 Appendix A, Area Maps and/or Site Plans

14-16 Appendix B, Sustainment Quantity Estimates

Appendix C, Required Reports/Forms

Government Estimates and Prices

19-26

PERFORMANCE WORK STATEMENT

1.0 Description of Services. The Contractor shall provide all personnel, equipment, tools, supervision, and other items and services necessary to ensure that site sustainment is performed at Vigilant Warrior Training Site Lake Jordan, Titus Alabama. This sustainment would include trails sustainment, erosion control, mowing/trimming on improved/semi-improved grounds, tree removal, tree pruning, to include dead growth along trails, buildings, and fence lines, stump removal, tree pruning, as identified by the QAP, and herbicide/pesticide applications. All work shall be accomplished in accordance with this PWS. The contractor shall accomplish all site sustainment tasks identified in this PWS and Appendices A, and B, in order to meet the requirements and the Service Summary (SS). Base maps of areas maintained are provided in Appendix A, Area Maps and Site Plans. Specific ground area measurements are established in Appendix B, Site Sustainment Estimated Quantities. All work performed by the contractor shall be performed in accordance with all applicable laws, regulations, standards, instructions, and commercial practices.

1.1 Maintain Improved Grounds: The contractor shall provide services identified below for all improved grounds as identified in Appendix A.

1.1.1 Turf Areas. Grass, weeds, and vegetation shall be mowed between 2 to 4 inches, on improved grounds (all permanent/tent structures, and surrounds). Grass clippings shall be removed or mulched when visible after mowing. All tree limbs, pine cones, litter and other debris shall be picked up and disposed of prior to each mowing. Contractor shall dispose of collected material in appropriate waste containers designated by the Quality Assurance Personnel (QAP).

1.1.1.1 Trim. Grass, weeds, and vegetation shall be trimmed between 2 to 4 inches, around trees, buildings, fences, poles, posts, fire hydrants, and other fixed obstacles on improved/semi improved grounds. Trimming height shall match surrounding area grass heights. All areas shall be trimmed concurrent with mowing operations. Use of mechanical trimming in lieu of herbicide application is the preferred method of weed/grass removal along fence lines and other obstacles. Herbicides application to control unwanted growth shall be kept to a minimum when mechanical trimming will accomplish the task.

1.1.1.2 Fertilization. The Contractor shall have a pH adjustment and fertilizer application program for all improved turf. The type and amount of fertilizer or amendments applied should be based on the needs of the individual types (warm season grasses, cool season grasses) of turf to maintain optimal root growth.

1.1.2 Non-Turf Areas. The contractor shall be responsible to maintain trails and edges that support student/staff training operations. The contractor shall be required to apply a soil erosion control material such as SoilTac material or equal to all main trails to prevent erosion and to maintain each trail in a maneuverable and safe condition.

1.2 Maintain Semi-Improved Grounds. The contractor shall provide services identified below for all semi-improved grounds as identified in Appendix A.

1.2.1 Semi-Improved. Grass, weeds, insect infestation, and vegetation shall be maintained between 4 to 10 inches on semi-improved grounds (obstacle courses).

1.3 Maintain Un-Improved Grounds. Grass, weeds, insect, and vegetation shall be maintained to prevent woody encroachment and insect infestation on all fence lines and other un-improved grounds as identified in Appendix A.

1.4 Debris, Trash and Litter Policing. The Contractor shall pick up and dispose of litter, trash, or other debris visible while performing work in any area. The contractor shall grind and or chip all wood/organic materials from any removal operations. At the direction of the QAP such wood chips or organic material shall be used for site filler and or beautification. All unused organic material will be the contractor’s responsibility to dispose of off site in accordance with all Federal, State, and Local waste disposal regulations, guidelines, and policies. The Contractor shall dispose of all non-organic materials such as trash or litter. This material shall be collected and disposed of in appropriate waste containers designated or identified by the Quality Assurance Personnel (QAP). Under no circumstances will burning of any debris be allowed unless written coordination/approval is given by Alabama Power Company.

1.5 Prune Trees The Contractor shall prune or trim trees that pose growing into any fence line building/structure, or tent to a minimum safety. Clearances are: 4 feet from fence line, and 1 foot from buildings. Trees that pose threats to buildings, fence line or structures shall be identified by the QAP. Topping shall not be permitted. Also, tree/timber cutting or removal will not be allowed except as approved by Officer Training School after coordination and approval has been given by the Base Civil Engineer and Alabama Power Forestry Commission. Contractor shall be responsible for removing all debris generated from trimming or pruning operations. Notify the QAP and/or Contracting Officer when pruning around utility poles or power lines is needed.

1.5.1 Tree Pruning Standards. The Contractor shall perform all tree work in accordance with contract specifications and the following tree care standards unless otherwise directed by the QAP or Contracting Officer. ANSI A300 (Part 1) 2001 Tree Pruning

1.5.2 Tree Stump Removal. Tree Stump Removal shall be accomplished on an as need basis to eliminate any safety hazards to students and staff during training operations. The QAP will identify and assign any needed stump removal tasks to the contractor. Areas for stump removal will consist of trails, paths, fence lines, and obstacle courses that are used for student training operations. Stump removal operations shall be coordinated and accomplished in a manner as not to pose any safety concerns to students/staff and in accordance with this PWS.

1.5.3 Stump Removal Process. The contractor shall grind stumps to a minimum of 6 inches below finish grade to minimize any safety concerns. The contractor shall be required to furnish any and all trained personnel to accomplish this task. The contractor shall also be responsible to provide all equipment, labor, material, and supervision needed to perform this task

1.6 Herbicide/Pesticide Application Procedures. The contractor shall contact Mr. Brian Seale of the Alabama Power Companies Forestry Commission prior to any Herbicide or Pesticide applications being accomplished. Mechanical grass/weed removal is the preferred method. However, contractor personnel handling and applying herbicides/pesticides shall possess state certification in Right of Way categories. Contractor personnel handling and applying herbicides/pesticides for broadleaf weed control (pest weeds) and Insect control shall possess state certification in Ornamental & Turf categories. The contractor shall perform treatment of pest weeds (broadleaf weed control) in accordance with federal and state regulations and DoD/Maxwell AFB Pest Management Programs prescribed in AFI 32-1053 para 4.7.4 and 4.7.6 and DoDI 4150.7 Encl 4 para 5b(3).

1.6.1 The Contractor shall submit a weed control plan to the Contracting Officer and MSD/CE entomology shop for approval, prior to any herbicide/pesticide application being allowed. The plan must be updated before any new herbicide/pesticide is used. The weed/Insect control plan shall detail:

(1) The type of herbicide(s) to be applied; with the name & EPA number & application rate (amount per acre)

(2) Timing of application(s)

(3) The type of application equipment

1.6.2 Contractor personnel handling and applying herbicides/pesticides shall possess a current State of Alabama certification (http://aec.army.mil/usaec/pest/pest05.html), business license and training in the appropriate herbicide/pesticide categories. A copy of all state certifications/licenses of personnel applying pesticides/herbicides shall be provided to the QAP seven days prior to the application of any pesticide. No uncertified technicians will be authorized to mix or apply herbicides.

1.6.3 The Contractor shall furnish the QAP with labels and Material Safety Data Sheets (MSDS) for all herbicides/pesticides to be approved by the Maxwell AFB Pest Management Coordinator prior to use. Herbicides/Pesticides will be applied in accordance with label directions, including required personal protective equipment, application rates, and use restrictions. The contractor shall comply with all Federal, State, and local environmental laws for any and all herbicide and pesticide applications such as stated in the EPA Clean Water Act. No herbicide/pesticide applications will be authorized within 25 feet of any water or stream beds. The Contractor shall submit a report (DD Form 1532-1) to the QAP the following regular workday after application listing the target pest, temperature, wind speed, direction, the type and amount of chemical used per location and pesticide applicator(s). Wind speed information can be obtained from the Base Weather Office at 334-953-2071 .

1.6.4 Storage and mixing of herbicides/pesticides by the Contractor will not be allowed on site. Contractors must have a spill kit on each vehicle capable of containing 110% of the greatest container volume. The contractor shall provide the government with a spill response plan no more than ten work days after award of contract. All wastes shall be the responsibility of the Contractor and will be disposed of off site in accordance with all Federal and State regulations pertaining to hazardous chemicals, wastes, and herbicides/pesticides. In no manner will the Government be responsible for off-base disposals.

1.7.0 Contractor Provided Equipment and Supplies.

1.7.1 Contractor-Furnished Equipment/Vehicles. The contractor shall provide and maintain all equipment and vehicles necessary to perform the requirements of this contract. The contractor may perform cleaning, minor repair and other normal maintenance requirements of equipment on site. Maintenance and repair of contractor vehicles or their privately owned vehicles shall not be accomplished on site. No chemicals such as fuel oils will be allowed around or near any waterways. Contractor vehicles shall have the company name prominently displayed on both sides of the vehicle and be maintained to present a neat, professional appearance.

1.7.1.1 All equipment used in the performance of this contract shall be in good operable condition and carry a U/L (Underwriters Laboratory) listing, if applicable. Equipment found to be unsafe and unable to function as designed, shall not be used in performance of this contract. The contracting officer or designated representative may inspect the contractor’s equipment and vehicles at any time and direct the removal of any unsafe or unusable equipment or vehicle from the site.

1.7.1.2 The contractor shall coordinate availability of a sufficient quantity of equipment and vehicles to effectively fulfill the scope of this contract. Equipment failure or maintenance requirements shall not alleviate the contractor from meeting the performance standards contained in this contract.

1.8.0 Miscellaneous Requirements

· Practice water conservation

· Turn off unnecessary lights

· Report fire hazards, conditions, and items in need of repair to the QAP

· Turn in lost and found articles to the QAP

· The Contractor shall notify the QAP of any condition, including adverse weather or special requests from government personnel that may interrupt or delay performance under this PWS. Once the condition is resolved the Contractor shall resume interrupted work as soon as practical. When this period exceeds 24 hours the QAP must approve the delay.

2.0 Service Summary (SS): The contract service requirements are summarized in performance objectives that relate directly to mission essential items. The performance threshold briefly describes the minimally acceptable levels of service required for each requirement. The SS and the contractor’s Quality Control Plan provide information on contract requirements, the expected level of contractor performance and the expected method of government assessment and confirmation of services provided. These thresholds are critical to mission success. Procedures as set forth in the FAR 52.212-4 (a), Contract Terms and Conditions - Commercial Items, Inspection/Acceptance, will be used to remedy all deficiencies. During the first initial 30 days of the contract, two additional errors on each task shall be allowed in an effort to identify normal phase-in problems.

Performance Objective
PWS Para
Performance

Threshold Remedy

SS-1

Maintain Improved Grounds

a. Mow

b. Trim

c. Pesticide/Herbicide

d. Fertilization

1.1, inclusive
No more than 5 valid defects per month
Re-performance

Within 8 hours of notification

SS-2

Maintain Semi-Improved Grounds

a. Mow semi-improved areas (Obstacle Courses)

b. Trim semi-improved areas (Obstacle Courses)

1.2, inclusive
No more than 5 valid defects per month
Re-performance

Within 8 hours of notification

SS-3

Maintain Un-Improved Grounds

a. Fence Lines

b. Trail edges

1.3, inclusive
No more than 5 defects per month
Re-performance

Within 1 day of notification or a mutually acceptable timeframe to the QAP and contractor.

SS-4

Control Vegetation and erosion on trails and fence lines

1.4
No more than 3 valid defects per month
Re-performance

Within 4 hours of notification

SS-5

Debris, Trash and Litter Policing

1.5
No more than 3 valid defects per month
Re-performance

SS-6

Tree Pruning/Stump Removal

1.6, inclusive
No more than 3 valid defects per month
Re-performance

SS-7

Quality Control

Contractor’s Quality Control Plan (incorporated into contract after award).

2.1
No more than 3 valid defect per month
Contractor shall provide a written Corrective Action Report.

2.1 Quality Control The contractor shall develop and maintain a quality control program to ensure site sustainment services are performed in accordance with commonly accepted commercial practices and services identified in this PWS. The contractor shall develop and implement procedures to identify, prevent, and ensure non-performance and continual repeat of defective service does not occur. A written Quality Control Plan shall be submitted to the contracting officer for review, feedback and acceptance. The plan shall be submitted no later than the pre-performance conference. The plan shall specifically address the contractor’s strategy to provide quality workmanship, continual process improvement and for correcting deficiencies as required.

2.2. Quality Assurance. The government shall inspect and evaluate the contractor’s performance to ensure services are received in accordance with requirements set forth in this contract. The QAP shall inspect by watching actual task performance, physically checking an attribute of the completed task, checking a management information report, investigating customer complaints, conferring with facility managers, or otherwise inspecting the task or its results to determine whether or not performance meets the standards contained in this PWS. The QAP will use the contractor’s work schedule or modified version thereof, to record surveillance results. Results of the surveillance then become the official Air Force record of the Contractor’s performance. When a performance threshold has not been met or contractor performance has not been accomplished, the QAP will initiate and provide the Contracting Officer a Contract Action Report (CAR) for issuance to the contractor. The contractor shall respond to the CAR IAW instructions provided and return it to the Contracting Officer within 10 calendar days of receipt.

2.3 Assessment Methods.

2.3.1 100% Assessment. This method requires the QAP to inspect the service each time it occurs. Results shall be annotated on the inspection schedule. Any deficiency shall be documented and the contractor shall re-perform service immediately, if appropriate, or within 24 hours at no increase in contract amount. Any unsatisfactory inspection identified but re-performed acceptably shall still be counted as an unsatisfactory inspection for trending purposes.

Receiving two or more unsatisfactory 100% assessment within a 12 month period may result in unsatisfactory past performance documentation. Continued receipt of unsatisfactory 100% assessment during the contract period shall constitute a negative trend and the Contracting Officer may take any appropriate action in accordance with the FAR 52.212-4 (a), Contract Terms and Conditions - Commercial Items, Inspection/Acceptance.

2.3.2 Periodic Assessment. This method requires the QAP to employ a “spot check” style of evaluation based on the contractor’s schedule. Periodic assessment will be conducted on a scheduled basis (daily, weekly, monthly, quarterly, semi-annual or annually) and may be adjusted, based on quality trends.

Any unsatisfactory inspection (defect) result shall be recorded, and the Contractor shall re-perform the service after notification by the QAP.

Failing to meet the performance threshold as outlined in the SS for any of these performance objectives in any one month period shall result in a warning or letter of concern from the Contracting Officer.

Failing to meet the performance threshold as outlined in the SS of these performance objectives in any combination for any two, or more consecutive or non-consecutive months during a contract period shall constitute an immediate Progress Meeting with the Multi-functional Team. All remedies shall be in accordance with the FAR 52.212-4 (a), Contract Terms and Conditions - Commercial Items, Inspection/Acceptance.

2.3.3 Periodic Progress Meetings. The Contracting Officer, Functional Commander, QAP, other government personnel as appropriate, and the Contractor shall periodically meet to discuss the Contractor’s performance. The following issues shall be discussed, opportunities to improve the contract, any modifications required of the contract, unsatisfactory inspections and trends against each performance objective observed, positive performance and steps taken by the Contractor to prevent unsatisfactory occurrences in the future. The Contractor shall provide a summation of unsatisfactory inspections and customer complaints and provide insight into any identified trends.

The minutes of these meetings will be reduced to writing, signed by the Contracting Officer and any other signatures as deemed appropriate, distributed to the functional area and the contractor. Should the contractor not concur with the minutes, the contractor will provide a written notification to the Contracting Office identifying areas of non-concurrence for resolution.

3.0 GOVERNMENT FURNISHED PROPERTY AND SERVICES

3.1 Government Furnished Facilities. None.

3.2 Government Furnished Supplies and Equipment. None.

3.3 Government Furnished Utilities. The Government will furnish electricity, water and sewage service as necessary for accomplishment of work in accordance with this contract.

3.3.1 Utility Conservation. The Contractor shall adhere to all base level utility conservation practices or requirements. The Contractor shall be responsible for operating under conditions that prevent waste of utilities.

3.4 Telephone Service. None.

3.5 Security, Fire and Medical Services. None.

3.6 Refuse Collection and Disposal. The Contractor shall use existing bulk containers to dispose of trash or refuse generated from accomplishment of services detailed in this PWS. The contractor shall adhere to all base level recycling programs to include disposal of yard/tree waste in specified dumpster collection stations. The QAP shall identify these specific dumpsters for yard/tree waste.

3.7 Mail Service. None.

4.0 General Information

4.1 Hours of Operation. The contractor shall perform the services required under this contract during the hours identified in paragraph 4.1.1.. The contractor is not required to perform services on Federal Holidays.

4.1.1 Normal Base Hours. Base hours of operation are Monday thru Friday 0700-1700 The Contractor may find it necessary to deviate from the normal base hours of operation, to ensure timely completion of work under this PWS at no additional cost to the government.

4.2 Federal Holidays.

New Year’s Day - 1 January

Martin Luther King Day - 3rd Monday in January

Washington’s Birthday - 3rd Monday in February

Memorial Day - last Monday in May

Independence Day - 4 July

Labor Day - 1st Monday in September

Columbus Day - 2nd Monday in October

Veteran’s Day - 11 November

Thanksgiving Day - 4th Thursday in November

Christmas Day - 25 December

If these holidays fall on Saturday, the preceding Friday will be observed. If these holidays fall on Sunday, the following Monday will be observed. If a holiday falls on a scheduled service day, the Contractor will be responsible for rescheduling services for the first day post the holiday observance.

4.3 Base/Site Closures. Work scheduled but not accomplished because of site closure due to weather, exercises, or actual alert, will be accomplished as soon as possible after reopening the site.

4.4 Contractor/Employee Base Pass and Identification, Special Clearances and Vehicle Passes. The contractor shall comply with all requirements and procedures IAW FAR 5353.242-9000, Contractor Access to Air Force Installations. All documentation shall be submitted at the pre-performance conference.

Section 4.5 Environmental Protection

4.5.1 Environmental Compliance

In all activities performed by the contractor, it shall be the contractor’s responsibility to comply with all applicable environmental requirements, and in particular those requirements concerning environmental quality, pest management, natural resource management, pollution control and abatement, air quality, water quality, wastewater, solid waste, hazardous materials, and hazardous waste. Responsibility for compliance with such requirements rests with the contractor, including liability for any fines, penalties, or other similar enforcement action and associated costs.

4.5.2 Hazardous Material Handling The Contractor must have approval from the base Hazardous Materials Manager prior to purchasing, handling, using, and storing any chemicals, solvents, lubricants, and other products (excluding pesticides) that require MSDSs. The Contractor shall identify these materials and products using the “Contractor’s Hazmat Questionnaire” and the “Contractor’s Environmental Reporting Entry Form.” The Contractor shall provide one copy of the MSDSs for each item to the Hazardous Materials Manager for review prior to any chemicals being brought onto Maxwell AFB. The Contractor shall maintain one copy of the MSDSs for each hazardous material line item used within the work center. The Contractor shall provide copies of appropriate pesticide documents listed in Section 1.6 to Environmental as well as a monthly log of quantity of hazardous materials used.

The Contractor shall not use any products that are or contain Toxic 17 chemicals, Extremely Hazardous Substances (EHS), Ozone Depleting Substances (ODS) and/or Persistent Bio-accumulative and Toxic (PBT) chemicals.

No hazardous materials may be stored on site by the contractor without prior coordination from 42 CES/CEV.

4.5.3 Solid and Hazardous Wastes The contractor shall not bring any solid or hazardous wastes or hazardous substances onto Maxwell AFB or any property under the control of Maxwell AFB. The contractor shall be responsible for the cost of proper disposal of solid and hazardous wastes generated by its activities under this contract. The terms “hazardous materials,” “solid wastes,” “hazardous wastes,” and “hazardous substances” are as defined in the Federal Water Pollution Control Act, CERCLA, SWDA, RCRA, the Clean Air Act, and the Toxic Substances Control Act, and their implementing regulations. 42 CES/CEV must be notified of any products that meet these criteria that are on base property.

4.5.4 Discharge of Materials and Spill Response No discharges of any chemicals are allowed on the property at any time. This includes, but is not limited to release of fuel, oil, pesticides, water from rinsing containers, or any other material released to the ground, air, or water. Contractor shall maintain vehicles and equipment so as to prevent leakage or unwanted release of petroleum products.

In case of an accidental discharge or spill, contractor shall immediately notify the QAP and cease activities at the site, except such activities that may be directed at containing a spill. The contractor is responsible to report and promptly clean up all spills in a manner consistent with current environmental regulations. In the event that it is necessary to utilize government material, equipment, or personnel to clean up a contractor-caused spill, the contractor shall be required to reimburse the government for all associated costs.

4.5.5 Protection of Waterways

Drainage ways, creeks, streams, wetlands, and other bodies of water are protected under the Clean Water Act (CWA). At all times, maintain an undisturbed vegetative buffer within 25 feet of waterways. Removal of vegetation within 25 feet of water courses will require coordination with 42 CES/CEV prior to work start.

4.5.6 Training The contractor shall ensure that all employees complete required Federal, State, local, and Air Force training. Contractor may contact 42 CES/CEV for required EMS (Environmental Management System) awareness training and other environmental training opportunities.

4.7 Traffic Laws. The Contractor and its employees shall comply with base traffic regulations.

4.9 Weapons, Firearms, and Ammunition. Contractor employees are prohibited from possessing weapons, firearms, or ammunition, on themselves or within their Contractor-owned or privately owned vehicle while on Maxwell AFB.

4.10 Reporting Requirements. Contractor personnel shall report to an appropriate authority any information or circumstances of which they are aware may pose a threat to the security of DoD personnel, Contractor personnel, resources, and classified or unclassified defense information.

4.11 Physical Security. The Contractor shall be responsible for safeguarding all government property and controlled forms provided for Contractor use. At the end of each work period, all government facilities, equipment, and materials shall be secured.

4.12 Contract Manager. The Contractor shall establish and maintain an office/cell phone number through which the contract manager or alternate(s) can be contacted during work hours. The contract manager or alternate shall be available during normal duty hours to meet on the installation within 2 hours with the government personnel designated by the Contracting Officer to discuss problem areas. The Contractor shall provide the CO telephone number(s) where surveillance results and complaints can be reported. The Contractor shall also provide to the Contracting Officer the names and phone/pager numbers of Contractor POCs for after business hours including nights, weekends, and holidays. This information will be kept updated by the Contractor whenever personnel changes occur. The contract manager or alternate shall have full authority to act for the Contractor on all contract matters relating to the daily operation of this contract.

4.13 Personnel. Contractor personnel shall present a neat appearance. Contractor personnel shall be easily recognizable while on the installation in conjunction with this contract. This shall be accomplished through the wear of distinctive clothing, overcoats, rain gear, or hats, bearing the company name or logo. The coloring or design of the items selected should be such that identifies personnel easily and quickly for reasons of safety and personal protection.

The government is authorized to restrict the employment under the contract of any Contractor employee or prospective contractor employee, who is identified as a potential threat to the health, safety, security, general well being, or operational mission of the installation and its population.

4.14 Key Control. The Contractor shall establish and implement methods of making sure all keys/combinations issued to the Contractor by the government are not lost or misplaced and are not used by unauthorized persons. The Contractor shall not duplicate any keys issued by the government. The Contractor shall immediately report to the QAP or Contracting Officer any occurrences of lost or duplicated keys. In the event keys, other than master keys, are lost or duplicated, the Contractor may be required, upon written direction of the Contracting Officer, to re-key or replace the affected lock or locks without cost to the government. The government may, however, at its option, replace the affected lock or locks or perform re-keying and deduct the cost of such from the monthly payment due the Contractor. In the event a master key is lost or duplicated, the government shall replace all locks and keys for that system, and the total cost will be deducted from the monthly payment due the Contractor.

4.15 Schedules. The contractor shall submit a schedule for all services described in this PWS and Appendices A and B to the Contracting Officer or QAP for acceptance at the pre-performance conference and at each change in the growing/non-growing season. The schedule shall identify plots, acreages, or site areas and days of the week service will occur. The contractor shall be allowed 30 days to adjust work schedules based on inspections, use, and traffic and with facility managers, if applicable. This second work schedule shall be submitted to the Contracting Officer or QAP for acceptance within 10 days after the first contract month period. The contractor shall not deviate from the accepted schedule without prior acceptance from the Contracting Officer, or QAP. Permanent changes to the schedule must be submitted 10 days before implementation and receive Contracting Officer or QAP acceptance before the Government will allow the proposed changes. The schedule may be submitted electronically using a file format compatible with Government software programs such as "Microsoft Office" software.

4.16 Occurrence based (non-permanent) schedule changes due to customer requests or base exercises shall be submitted to the QAP and do not require Contracting Officer acceptance. The QAP shall have the ability to adjust the contractors improved grounds mowing schedule for DV and/or VIP visits to either the route or a specific area on site at no additional cost.

5.0 APPENDICES. The government will make all publications, forms, references and report formats listed available. Publications can be accessed on-line at http://www.e-publishing.af.mil/. Supplements or amendments to listed publication from any organizational level may be issued during the life of the contract. The Contractor shall immediately implement those changes in publications, which result in a decrease, or no change in the contract price. Prior to implementing any such revision, supplement, or amendment that will result in an increase in contract price, the Contractor shall submit to the Contracting Officer a price proposal and obtain prior approval. Price proposals shall be submitted within 15 calendar days from the date the Contractor receives notice of the revision, supplement, or amendment giving rise to the increase in cost of performance. Changes in the contract price due to supplements and amendments shall be considered under the FAR 52.212-4, Contract Terms and Conditions - Commercial Items clause. Failure of the Contractor to submit a price proposal within 15 calendar days from the date of receipt of any change, shall entitle the government to performance in accordance with such change, at no increase in contract price.

APPENDIX A –AREA MAPS OR SITE PLANS

APPENDIX B - GROUNDS MAINTENANCE QUANTITY ESTIMATES

APPENDIX C - REQUIRED REPORTS/FORMS

APPENDIX A –AREA MAPS OR SITE PLANS

Improved Grounds Turf Semi-improved Grounds Un-improved Grounds Areas Requiring Fertilization

Pesticide Applications

Herbicide Applications

Trash or Litter Removal

Tree Pruning/Removal

Stump Removal

APPENDIX B – Site Sustainment Estimated Quantities

ITEM
DESCRIPTION
ESTIMATED QUANTITIES
ESTIMATED WORKLOAD
Quantity
Unit
Growing Season
Non-Growing Season
1
Maintain Improved Grounds Turf
80
Acres
26-34
0-6
2
Fertilization Areas
80
Acres
12-16
0-3
3
Maintain Semi-Improved Grounds
40
Acres
0-1
4
Tree Pruning/Removal
50
Each
Not to exceed
5
Pesticide/Herbicide applications
1,742,400
Square Feet
26-34
0-6
6
Stump Removal
50
Each
Not to exceed
0-6
7
Maintain Un-Improved Grounds
30
Acres
80 man hours
N/A
8
Debris, Trash and Litter Removal
120
Unit
As required

APPENDIX C - Required Reports/Forms

Required
Due Date
Contractor’s QCP
Pre-Performance Conference
Annual Work Schedule
Pre-Performance Conference
Primary/Alternate POCs
Pre-Performance Conference
AF Form 332 – Civil Engineer Work Order
As Needed
AF Form 3952 - Chemical/Hazardous Material Authorization
As Needed
Herbicide - Weed Control Plan
Pre-Performance Conference
DD Form 1532-1 Pest Management Maintenance Record
As Needed
AF Form 483 – Competency Card
As Required