Attachment 1 Statement of Work
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Barrier_Electrical_Repair_Site_Visit_Questions.pdf | ||
| Attachment_2_-_WD_15-5157_-_10_Jul_18.pdf | ||
| FA302219QA005.pdf | ||
| Attachment_3_-_Clause_List.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FA302219QA005 Page 1 of 2
STATEMENT OF WORK
REWIRE ACTIVE VEHICLE BARRIER CONTROL SYSTEMS
COLUMBUS AFB, MISSISSIPPI
30 November 2018
GENERAL – PART I
1.1 This Statement of Work (SOW) defines the scope of work to accomplish the rewiring of the active vehicle barrier control systems located in facilities 9017, 9022, 9023, 9026, 110 and 1130 at Columbus AFB, MS. The contractor shall provide all labor, material, equipment, management, supervision, coordination and transportation required to accomplish this work.
1.2 WORK SCHEDULE, PLANS AND WORKING HOURS: Work days for this contract will be Monday through Friday between the hours of 0730 and 1615 Central US and Saturday through Sunday between the hours of 0730 and 1800, except for Federal holidays. The facilities may be occupied during the hours of work and coordination will be required with the Government Representative to minimize the effect of work on traffic. The contractor shall not begin any work until he/she has 100% of materials need to complete and provide fully operational barrier systems.
Written permission from the Contract Officer and the Service Contracts Section of the Civil Engineering Squadron shall be obtained for any deviation from the designated working times.
1.3 AVAILABILITY OF UTILITY SERVICES: All reasonable quantities of utilities will be made available to the contractor. The government shall not be held responsible for interruptions of utility services, and will not be liable for contractor delays, damages, or increased cost incurred by any such interruption of service. The contractor shall be responsible for providing all labor, equipment, and materials to make necessary temporary utility connections. The temporary connections shall be coordinated with the Government Representative before being made and shall be removed upon project completion.
1.4 CLEAN-UP: All debris and rubbish not specified to become government property resulting from construction work will be disposed of by the contractor off government property. Disposal will be in compliance with federal, state, and local hauling and disposal regulations. Site clean-up shall be daily.
1.5 SAFETY REQUREMENTS: Safety requirements shall be the applicable sections of the most current EM 385-1-1 and Occupational Safety and Health Administration (OSHA) Regulations. These Regulations can be located through an online search.
FA302219QA005 Page 2 of 2
The contractor shall ensure that any lifting devices or ladders meet any and all applicable safety standards.
1.6 SITE CONDITIONS: The Contractor acknowledges satisfaction as to the nature and location of the work, the general and local conditions, access to job site; disposal, handling and storage of materials; availability of labor, water, electric power or similar physical conditions at CAFB; the character of equipment and facilities needed preliminary to and during the performance of the work; and all other matters that can in any way affect the work or the cost thereof under this contract. The contractor acknowledges that any damage to the existing structure in and around the facility will be returned to its existing conditions prior to the completion of subject work at no additional cost to the government.
1.7
TECHNICAL – PART II
2.1 The contractor shall perform all work required to remove surge protectors and rewire the DSC 2000 active barrier control systems at the gates and hydraulic power units (HPUs) in order to return all barrier systems to a fully operational status to the satisfaction of the Government. All work shall be accomplished in accordance with the relevant Unified Facilities Criteria UFC4-022-01 and all criteria referenced therein.
2.2 All “Data Line” surge protectors and wiring immediately connecting the surge protectors shall be removed from any controls within the listed facilities.
2.3 Any removed wiring shall be replaced with appropriately sized uninterrupted wire according to the National Electric Code and any applicable United Facilities Criteria.
2.4 All work shall be accomplished by a Delta Scientific certified technicians.
2.5 The contractor shall provide a one (1) year warranty from time of acceptance for materials and workmanship.
END OF SECTION
| COLUMBUS AFB, MISSISSIPPI |
| 30 November 2018 |