Questions and Answers

FA302218R0023, Freedom Park Playground and Splash Pad

1. Where will the main sewer line attach? The specs have a French drain through the middle of the playground, where will the main drainage line attach? What is the distance the drain line needs to be to attach to their sanitary sewer?

- There is a storm drain line that runs past the playground to the south. It is approximately 120ft from the playground. Please see the drawings. The storm drain line is depicted in green.

2. Will the Recycling Center on Base recycle the materials from the playground or will we have dumpsters on site for the demolition?

- The Contractor is responsible for disposing of the materials removed from the project.

3. Will the sand volleyball court be removed? (Will the sand affect the splash pad?)

- No, the volleyball court will not be removed

4. Will the trees be removed prior to construction or will they be integrated into the playground space?

- No trees will be removed

5. Will a portion of the fence be removed to allow access for equipment prior to construction?

- The fence can be removed to get equipment in to the project area, but there can be no damage to the running track. Any damage to the running track will be the responsibility of the contractor to correct.

6. Can we have a zoomed in image of water and sewer lines for better reference?

- See image below.

7. In order to keep with ADA and CPSC standards based on the fall heights of the decks will we increase the surfacing depth to meet standards?

- The Playground needs to meet safety standards

8. What is the size of the water supply line and where is it located for the splash pad?

- Water supply will come from across Simler Blvd as shown on the drawing. Water line is a 10in water supply line

9. Where is the electrical tie in? What phase and voltage are available?

- Electrical supply will come from the existing pavilion. There is a panel located at the pavilion and it is 120/208V 3 phase, with 6 spare breaker slots.

10. Can you clarify disposal of existing equipment/materials. Are we responsible for disposal or transporting the demoed equipment/materials? Can we leave piled nearby, or do we need to dispose on/off base, etc?

- The Contractor will be responsible to remove and dispose of all playground materials and pieces at an off base location.

11 Can you provide a zoomed in drawing of the playground area to display electric/freshwater/ sewer lines?

- An updated picture has been added to the project file.