Q&A__2.pdf

PDF 69 KB Posted

Attached to
Repaint Two 90k Water Tanks Federal contract opportunity
Solicitation number
FA3022-17-T-0031
Issued by
Department of the Air Force Air Education and Training Command

About this file

Question and Answers #2

View the file

Other files for this federal contract opportunity

Other files attached to Repaint Two 90k Water Tanks, newest first.
File Type Posted
FA302217T0031_Amended_Solicitation.pdf PDF
Recent_Lead_Test_Results.pdf PDF
Attachment_2_-_WD_MS170136.pdf PDF
Q&A.pdf PDF
FA3022-17-T-0031_Solicitation.pdf PDF
Attachment_3_-_AF_Form_66.xlsx XLSX spreadsheet
Attachment_4_-_Technical_Paint_Spec.pdf PDF
Attachment_1_-_Repaint_Water_Tank_SOW_v.2.pdf PDF
Attachment_5_-_Fire_Tank_Locations.pdf PDF
Attachment_5_-_Technical_Paint_Spec.pdf PDF
Repaint_Water_Tanks_Combined_Synopsis.pdf PDF
Attachment_6_-_Fire_Tank_Locations.pdf PDF
Attachment_4_-_Wage_Determination.pdf PDF
Attachment_3_-_Provisions_and_Clauses.pdf PDF
Attachment_2_-_Repaint_Water_Tank_SOW.pdf PDF
Show all 15

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Q&A #2 for Repaint Water Tanks Project

Q1: Can the owner provide a lead test report for the interior and exterior of the tanks?

A1: The report has been uploaded to FBO.

Q2: When do both tanks need to be completed?

A2: Per clause 52.211-10 in the solicitation, the contractor has 48 calendar days after receipt of NTP.

Q3: What are the dimensions of the water tanks?

A3: While there are not any specific specifications available, the Civil Engineering Squadron’s rough estimate are: Diameter: ~20 feet, Height: ~40 feet.

Q4: When is time of award?

A4: Time of award will be no later than 30 September 2017.

Q5: Section 3.5.4.4 states to use Hydro Flon as the top coat. PART 2 PRODUCTS section 2.2.2.4 states to use 1074 endura-Shield as the topcoat. Which product would you like to use? The 1074 is considerably less expensive than the Hydro Flon.

A5: The paint technical specfication sheet was uploaded erroneously, please disregard. Please follow all requirements in the Statement of Work.

Q6: Is a bid bond required?

A6: Yes, per the soliciation a bid bond of 20% or three million dollars, whatever is less, is required.