Repair Roof at 50FTS B216 - Questions and Answers Solicitation FA3022-17-R-0019
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Questions and Answers
FA3022-17-R-0019
Repair Roof at 50FTS, B216
Questions:
1. Will the facility supply the water access for pressure washing the roof?
2. Will the water runoff from the pressure washing have to be collected and disposed of? If yes, Will the disposal be the responsibility of the contractor?
3. Will the facility supply any electrical power if needed?
4. Is there a site disposal for solid and liquid generated waste or will this be required to be taken off site and disposed of by the contractor?
5. What is your site specific fall protection plan/requirements?
Answers:
1. Yes the facility will have water access
2. The runoff must be collected and removed by the contractor
3. There will be electrical power
4.all disposal is the responsibility of the contractor and shall be offsite
5.The fall protection is a contractor responsibility in accordance with ALL OSHA guidelines