SOW_Facility_712_Fellowship_Area_(2).doc

DOC document 37 KB Posted

Attached to
Base Chapel Flooring Repair
Solicitation number
FA3022-14-T-0003
Issued by

About this file

Statement of Work

View the file

Other files

File Type Posted
Solicitation_FA3022-14-T-0003.pdf PDF
WD_05.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK

CHAPEL FLOORING

1.

GENERAL INTENTION: It is the declared and acknowledged intention and meaning to install new LVT (luxury vinyl tile) plank flooring and ceramic tile flooring complete and ready for use.

2.

GENERAL DESCRIPTION: The work shall include providing all labor, equipment, transportation, and materials to remove existing 12x12 vinyl composition tile, 12x12 ceramic tile and ¼ round shoe molding, prepare all surfaces for the installation of new LVT plank flooring, new ceramic tile and painted ¼ round shoe molding in accordance with the statement of work reference Technical Section – Part II. This general outline of work does not, in any way, limit the responsibility of the contractor to perform all work specified herein.

3. LOCATION:

The work shall be located at, Facility 712 on Columbus AFB, MS. The area will not be occupied during this project.

4.

The contractor shall coordinate work and obtain access to the facilities by contacting the 14 Civil Engineering, Maintenance Engineering Office (ph. 434-7346). The actual installation of materials will be accomplished during normal duty hours (duty hours 0730-1615, Monday through Friday). The contractor shall visit 14 Civil Engineering, Building 385, and make personal contact with a representative from the Maintenance Engineering Office prior to beginning work. A site visit shall be provided to the contractor so that all quantities can be verified.

5.

AVAILABILITY OF UTILITY SERVICES: All reasonable quantities of utilities will be made available to the contractor. Any temporary connections of lines that may be required shall be installed, maintained and removed by the contractor at their own expense and in a manner satisfactory to the Contracting Officer. Removal of such connections or lines shall be accomplished prior to final acceptance of the contract. The Government will not be held responsible for interruptions of utility services, and will not be liable for contractor delays, damages, or increased cost incurred by any such interruption of service. In the event that any property of the government is damaged or destroyed, it shall be repaired to its original condition by the contractor at no additional expense to the Government.

6.

SAFETY REQUIREMENTS shall be the applicable sections of EM 385-1-1, 1 Oct 87, which is available for reference from Maintenance Engineering, in Building 385.

7.

CLEAN UP: All debris and rubbish resulting from construction work shall be disposed of by the contractor off Government property. Site clean up shall be daily.

END OF SECTION

TECHNICAL SECTION – PART II

1.0 Work to be performed shall be as follows:

1.1 Remove approximately 1,405 SF of existing 12x12 vinyl composition tile floor within the fellowship hall of the facility.

1.2 Remove approximately 180 SF of existing 12x12 ceramic tile flooring within the kitchen area of the fellowship hall of the facility.

1.3 The contractor shall accomplish surface preparation on approximately 1,585 SF for each of the areas to receive new flooring.

1.4 The contractor shall purchase and install approximately 1,405 SF of new Luxury Vinyl Tile plank flooring. LVT shall match that of PermaStone – LA 402R, Latitude Santos, Mahogany, rolled edge.

1.5 The contractor shall purchase and install approximately 180 SF of 12x12 porcelain tile flooring. Porcelain tile shall be Florida Tile, Style shall be Cliffside, color #28260 Blue Oasis or an approved equal. Grout to be installed shall be a dark gray of a commercial grade to be determined by the government.

1.6 The contractor shall furnish and install new cement board for substructure support per manufacture’s recommendation.

1.7 The contractor shall remove approximately 180 LF of existing shoe molding within the work area.

1.8 The contractor shall purchase and install approximately 180 LF of new shoe molding to match the existing.

1.9 The contractor shall paint new shoe molding to match existing base board.

2.0 The government shall provide the following:

2.1 Removal of furniture and appliances within the work area.