This is a Questions and Answers document for federal contract opportunity FA302026Q0008, addressing clarifications regarding FY26 Starlink WiFi Service requirements at Fort Leonard Wood.
The contract involves providing Starlink High-Performance kits and Wi-Fi mesh routers for 12 buildings, with equipment required only for two first-year buildings (3202 and 5400); the remaining 10 buildings already possess existing equipment. Offerors may propose GEN1, GEN2, or GEN3 Starlink kits with corresponding mesh routers. Internet service specifications include 2TB per month for 12 months plus four optional extension years, with the government electing to opt in or opt out of overage fees (data will be throttled if 2TB is exceeded). Products may be sourced through Starlink-authorized retailers rather than directly from Starlink. The government will handle installation of all equipment; offerors must provide lead time from award to delivery of all items. Deliveries should be directed to F3V5F5 – 368 TRS, 6007 Cooley Ave Building 1703, Fort Leonard Wood, MO 65473. The incumbent contract is FA302025P0026. Pooled plan options are not of interest at this time, though additional support options may be provided as supplemental information only. All price quotations must be submitted via the Combo form price table, with separate company letterhead quotes permitted as supplemental documentation and all technical submissions on separate documents per the Instructions to Offerors section.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Q+A: FA302026Q0008 Page 1
Questions and Answers
FA302026Q0008: FY26 Starlink WIFI Service – Fort Leonard Wood
1. What is the existing/incumbent contract ID number?
Answer: FA302025P0026
2. Are the 2 High Performance Kits and 4 Mesh Routers required for each of the 12 buildings where Wi-Fi is required?
Answer: No, only for the 2 first-year buildings (3202, 5400); the other 10 buildings already have existing equipment.
3. What is the shipping address?
Answer: F3V5F5 – 368 TRS 6007 Cooley Ave Bldg. 1703 Ft. Leonard Wood, MO 65473
4. What specific information is the Government asking for with regard to "Lead time / Period of Performance "?
Answer: The expected amount of time from date of award to delivery of all items.
5. Who will be responsible for installation of the STARLINK High Performance Kits and
STARLINK W-Fi Mesh Routers, the Government or the Contractor?
Answer: Government.
6. Attachment 1 includes images of the Starlink High-Performance GEN1 kits and GEN1 Wi-Fi mesh router. Would you be open to considering the High-Performance GEN2 or the latest High- Performance GEN3 kits, along with the newest GEN3 Wi-Fi mesh routers?
Answer: Yes.
7. Attachment 1 related to the Starlink internet service states "2TB total (monthly service for 12 months and 4 option years to extend)." Does this mean 2TB per month for 12 months, totaling 24TB for the year? Or is it 2TB for the entire year, which would be approximately 166.66GB per month?
Answer: 2TB per month
8. Can these products be purchased from a StarLink authorized commercial reseller? Or they must be purchased directly through StarLink?
Answer: Can be purchased through a Starlink-authorized retailer.
Q+A: FA302026Q0008 Page 2
9. Is there interest in seeing an option for a pooled plan?
Answer: No, not at this time.
10. Is there interest in providing additional support options as information only?
Answer: Yes, it is not required but can be sent as information only.
11. Does the government want to Opt In or Opt Out of overage fees? (data will be throttled if the 2TB is exceeded)
Answer: Yes
12. Are offerors required to submit any information other than a completed pricing table and the contractor identification information? If so, please provide additional detail on each requirement and desired format information.