RFI Questions_Answers_LAK Demolition2.docx
DOCX document 24 KB Posted
- Solicitation number
- FA301626R00330003
About this file
This file is a Questions and Answers (Q&A) document addressing contractor inquiries regarding demolition services at JBSA Lackland Air Force Base and LAK Chapman Annex. The document provides clarifications on utility disconnection responsibilities, hazardous material handling, site requirements, and project specifications across seven buildings (B2988, B2989, B4395, B5584, B7362, B7561, and B148/B140).
Key clarifications include: the contractor is responsible for removing electrical risers after CPS (utility provider) disconnection, though some facilities have been previously disconnected; rodent and vermin extermination are the contractor's responsibility per the Performance Work Statement; the government will accept examples of previously approved plans if compliant with current codes; the Period of Performance has been recalculated to 325 days from award to accommodate utility permanent disconnect application delays and NESHAP requirements; all debris must be manifested to TCEQ-permitted landfills (Covel Gardens or Tessman Road); post-land surveys by licensed professionals are required; temporary 6-foot perimeter fencing screened with brown fabric is mandated; all soil removal requires testing per Environmental Protection Standard 1.57.20; and building-specific requirements such as bollard removal to 3 feet below grade, basement concrete demolition to 3 feet below grade, and construction entries with bull rock are specified. The document also addresses square footage discrepancies between PWS listings and facility dimension calculations, clarifies HVAC unit quantities by building, and confirms that hydroseeding (rather than watering) is now required for grass establishment per PWS Revision 3 dated July 2026.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
RFI Questions & Answers Demolition Services At JBSA LAK/ LAK Chapman Annex
1. Buildings 2988 & 2989: Is CPS going to take down the feed from the transformer pole to the service pole? Would CPS or the winning contractor be responsible to take the riser off the pole that feeds the buildings? CPS will disconnect only and will remove transformers on another date; riser removal is Contractor’s responsibility
2. Building 5584: The feed comes to the building underground. Contractors need to know where it feeds from and how far away it is from the building? Will CPS disconnect this feed or do contractors need to include pricing to pull it out? CPS disconnect wires/cables from transformer service risers and/or entrances are Contractor’s responsibility; however, for this facility CPS reports no existing service; service has been previously disconnected
3. Building 7561: The feed comes from underground we need to know where it is fed from and how far away it is from the building and is cps going to disconnect it or do we need to disconnect it and pull the wire out? This facility is permanently disconnected from a removed service transformer
4. Buildings 7362 & 148 Will CPS disconnect the overhead power from the transformer pole and remove the wire to the buildings? Building 148 has 2 feeds going to it. CPS will disconnect only and will remove transformers on another date; riser removal is Contractor’s responsibility
5. Please confirm the rodent and vermin extermination will be handled by the GC and not the Civil Engineering Squadron responsible for rodent extermination and pest management. Contractor’s responsibility to handle Entomology issues is confirmed as stated in the PWS
6. GCs must submit all material on Technical Factors 1, 2 and 3. Please confirm the 502nd is truly requesting a full project specific deliverable with each proposal submission or if examples of previously approved plans would be accepted.
802 CES is open to accept “examples” of previously approved plans as long submissions are in compliance with applicable current codes and standards (i.e. JBSA Environmental Protection Standard 1 57 20)
7. What is the scale that price will be compared to technical subfactor when comparing proposals?
802 CES is not able to answer this question
8. It seems B4395 hazmat report is password protected? Can this file be released to certified bidders? HazMat Reports were issued without password protection; however, I’m forwarding the report again for your convenience
9. Can the environmental report for B7591 be released?
HazMat Reports were issued without password protection; however, I’m forwarding the report again for your convenience
10. Will compaction on slab backfill be required to tested by a third-party testing agency?
No.
a. If compaction is required, will it be 90% or 95%? 90%
11. Will watering for grass establishment be required?
This requirement has been changed to hydroseeding; is now reflected in the PWS revision 3 July 2026.
a. If required, how long does the contractor need to factor in for irrigation? Water requirements are as per hydroseeding provider
12. With Lackland being a NESHAP’s facility and the extensive preparation and then submittal of paperwork to submit to the state for approval to work, the POP for these projects being 20 -75 days from the award date might not be possible to even start within that timeframe. Has that been considered?
Recalculated the total PoP to 325 days; this is in consideration of the Utilities Permanent Disconnect Application Processes which have been experiencing increased delays & costs. I suggest that the Awarded Contractor start Demo Project by contacting Utility Service Providers to apply for Permanent Service Disconnect so the Private Service Provider begin their own processes to permanently disconnect each demo facility. The PoP change will be reflected on the PWS as a total; is up to the Contractor to distribute demo time for each facility.
13. While reviewing the solicitation package, we had a question regarding the hazardous material reports. We wanted to inquire whether any updated or revised hazardous material reports are available, as the reports currently included may not reflect all of the information necessary for preparing accurate pricing.
Additionally, we would appreciate clarification regarding the site visit. We understand there may have been a site visit that was not reflected in the solicitation documents. If any additional information, documentation were provided as a result of that site visit, we would appreciate it if they could be shared.
Currently, there are no further hazmat reports to provide. Yes there was a Site visit initially scheduled for 16 June per the solicitation and rescheduled to 23 June per the amendment to the solicitation, which both were posted on SAM.gov under Notice IDs FA301626R0033 & FA301626R00330002. There are no site visit documents to provide.
14. Can the buildings square foot and height be provided?
Please, review revised PWS, structures square footage and heights are included on the PWS, specifically on Facility Data Attachments (last pages of PWS)
15. Will we be allowed to demo more than one building at a time?
The PWS does not limit number of facilities to be demolished within a specific period of time; facilities demolition schedule should be compatible with Contractor’s existing business and manpower capabilities
16. Is there a designated dump site or can we select where to haul debris?
IAW JBSA Environmental Protection Specification 1 57 20, all excess soil/waste materials shall be properly manifested/transported to an TCEQ-permitted landfill (Covel Gardens or Tessman Rd Landfill are locally available) and approved by 802 CES/CEIE. (a Copy of JBSA Environmental Protection Spec 1 57 20 is included w/ PWS)
17. Can a satellite picture of the buildings be provided?
Although 802 CES is conducting maps updates and upgrades efforts, the resulting imagery is not available for Contractor use yet
18. Are we allowed to work 7 days a week?
The Project Contract Officer is the only one authorized to approved/disapprove work schedules
19. Will all utilities be disconnected from the buildings prior to demolition?
No, although some facilities have been abandoned and some of their utilities have been previously disconnected is the awarded Contractor responsibility to contact each Utility Service Provider to coordinate and apply for each facility permanent utility service disconnect as soon as possible after Contract Award (PWS Rev 3 July Para 1,page1)
20. Are there any hazardous materials associated with the buildings?
Yes, a HazMat Reports for each facility under this Project has been issued to 502 CONS and will accompany the PWS & QASP
21. It appears to be discrepancies in the square footage listed in the PWS. Could you please confirm the correct square footage for the following structures:
· B2988: In Section 2.2.1, CLIN 0001, the structure is listed as 2,256 SF. However, based on the dimensions provided in the Facility MPLS specifications (70'L x 50'W), the calculated square footage is 3,500 SF.
· B2989: In section 2.2.2 CLIN 0002, the structure is listed as 198 SF. However, based on the dimensions provided in the Facility MPLS specifications (40'L x 30'W), the calculated square footage is 1,200 SF.
· B4395: In Section 2.2.3, CLIN 0003, the structure is listed as 210 SF. However, based on the dimensions provided in the Facility MPLS specifications (21'L x 16'W), the calculated square footage is 336 SF.
· B5584: In Section 2.2.3, CLIN 0004, the structure is listed as 7,645 SF. However, based on the dimensions provided in the Facility MPLS specifications (302'L x 153'W), the calculated square footage is 42,206 SF.
· B140: In Section 2.2.5, CLIN 0007, the structure is listed as 14,618 SF. However, based on the dimensions provided in the Facility MPLS specifications (178'L x 154'W), the calculated square footage is 27,412 SF.
The measurements come from the Facility Data Sheet for each facility (measurements have been also confirmed by PM); however, square footage represents mission capable space. I suggest utilizing “L X W” measurements along with height measurements to calculate true structure size, all measurements are included on the Facility Data Sheets, provided as PWS Attachments 1-7
22. Are you requiring a post-land survey for each structure to be provided by a licensed professional land surveyor?
Yes, as stated on PWS 3 July 20206, Para. 1
23. Number 20 in the PWS states:
"Prior to soil removal, the contractor shall perform the following test methods and analytical parameters for every 200 CY of soil that is to be removed from JBSA."
Based on our review, there does not appear to be more than 200 CY of soil to be removed collectively from the site. Will TCLP testing still be required, or can this requirement be omitted?
Revised PWS 1July 2026 (now Para. 19 ) states that the Contractor shall test all soil to be remove from JBSA LAK (this shall be in accordance with Environmental Protection Standard 1 57 20)
24. Number 19 in the PWS states:
"The Contractor shall erect a suitable perimeter fence around the work site."
Would a 4-foot safety fence be considered acceptable, or would caution tape suffice?
PWS revised to specify temporary fencing as (PWS 3 July 2026, Para 18): Contractor shall erect a suitable perimeter 6ft fence screened with brown fabric around the work site.
25. Can the quantity of HVAC units be provided for each building?
3 facilities have HVAC units remaining:
B4395: 1ea (wall mounted) B7362; 4ea (3ea are basement window units) B140; 1ea
26. B140 - Is an asbestos, lead and contaminated soil survey available? 2. To what depth are piers to be demoed? 3. If backfill required? 4. Is seeding or sodding required or just rough grade finish? 5. Can a utility cut off location be provided? 6. Is project fencing required? 7. Is a SWPPP plan needed? 8. Are the sidewalks to be demoed, if so to what extent? 9. Does the parking lot demo? 10. If project fencing is needed, can we capture the entire parking lot? 11. Will a construction entry with bull rock be needed?
Please review PWS, and HazMat Reports. The parking shall remain; fence can capture the facility parking area only. Yes bull rock is required for all demos.
27. B2988 & B2989 - Is an asbestos, lead and contaminated soil survey available? 2. Will project fencing be required, is so can the existing chain link fence of the adjacent site be utilized as part of the project fence? 3. Will a SWPPP plan be needed? 4. Is a utility location cut of plan available? 5. Will the demolition area need to be back filled? 6. Is seeding or sodding required or just rough grade finish? 7. Will a construction entry with bull rock be needed?
Please review PWS, and attached HazMat Reports
28. B4395 - Is an asbestos, lead and contaminated soil survey available? 2. Will project fencing be required, is so can the existing base entry gates be utilized as part of the project fence? 3. Will a SWPPP plan be needed? 4. Is a utility cut of location plan available? 5. Is the building foundation to be demoed? 6. Is the surrounding concrete paving to be demoed, if so to what extent? 7. Will the bollards be left in place or will the be demoed, if so to what depth will the casings need to be removed? 8. Is a location plan available for the bollard operation system? 9. If the foundation and or the surrounding concrete paving demoes, will backfill be required? 10. Will seeding or sodding be needed? 11. Will the existing security gates remain in place, if so will the need to remain operable or should they be permanently closed?
Please review PWS, and attached HazMat Reports; Bollard shall be demoed up to 3ft bellow its grade; Existing gates shall remain, and as they are.
29. B5584 - s an asbestos, lead and contaminated soil survey available? 2. Will project fencing be required? 3. Will a SWPPP plan be needed? 4. Is a utility cut of location plan available? 5. Will the dirt/fill that currently covers the RCP be pushed into the hole after demo of should it be relocated/removed from site? 6. Does the government have a perfered side for a gate install? 7. Will a construction entry with bull rock be required? 8. Will seeding or sodding be needed? 9. Can the installed gate for access remain in place after construction or will the fence need to be returned to like existing condition?
Please review PWS, and attached HazMat Reports. Proposed demo access gate shall remain after demo; it shall be installed away from existing training area.
30. B7362 - Is an asbestos, lead and contaminated soil survey available? 2. Will project fencing be required? 3. Will a SWPPP plan be needed? 4. Is a utility cut of location plan available? 5. Will a construction entry with bull rock be required? 6. Will seeding or sodding be needed? 7. To what depth do piers need to be demoed? 8. Does the floor at the basement need to be demoed completely or can it be honeycolmbed, left in place and back filled, if so can the concrete walls of the basement be demoed to 5' below grade and left in place? 9. Do the surrounding sidewalks demo, if so to what extent? 10. Do the trees that are adjcent to the building demo?
Please review PWS and attached HazMat Reports. Basement concrete shall be demoed up to 3ft below their "grade".
31. B7561 - Is an asbestos, lead and contaminated soil survey available? 2. Will project fencing be required? 3. Will a SWPPP plan be needed? 4. Is a utility cut of location plan available? 5. Will the construction entry that is currently in place be utilized for the project or will a new entry be needed? 6. If the current entry is to be used will the awarded contractor of this project be responsible for restoring the site, if so would that include backfill, seeding or sodding?
HazMat reports were provided; Contractor shall fence their own fence and access gate to isolate from current construction. Site restoration spec is included on the PWS.