QA_FA301625Q0246.docx
DOCX document 23 KB Posted
- Attached to
- JBSA Golf Cart/Pedestrian PreFabricated Bridges
- Solicitation number
- FA301625Q0246
About this file
This document is a Questions and Answers (Q&A) file for Solicitation FA301625Q0246, involving the removal and replacement of two prefabricated bridges at Joint Base San Antonio (JBSA). The Q&A addresses specific details about the bridges, including their lengths (Site A: 85', Site B: 80'), and clarifies technical requirements such as the mandatory powder finish for the bridges. The government specifically noted that a bid bond is not required, as this is a firm-fixed price services contract.
The solicitation, issued by the Department of the Air Force Air Education and Training Command, seeks a contractor to replace two existing bridges: a Golf Cart Bridge at JBSA Lackland and a Pedestrian Bridge at JBSA Chapman Training Annex. The bridges must be structurally sound, prefabricated, and compliant with ADA requirements to safely accommodate pedestrians and golf carts. Vendors are required to review the Request for Quote (RFQ) and Statement of Work (SOW), complete the RFQ document, and submit via email by the specified deadline. The solicitation has undergone multiple amendments, including site visit information and question/answer additions.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
QUESTIONS & ANSWERS (Q&A)
SOLICITATION: FA301625Q0246
AMENDMENT 2
JBSA Golf Cart/Pedestrian Prefabricated Bridges
18 September 2025
Question 1: What is the estimated length of bridges? Site A and Site B?
Government Answer: Site A 85’ - Site B 80’
Questions 2: How long are these bridges?
Government Answer: Site A 85’ - Site B 80’
Question 3: Is using corrosion resistant weathering steel an acceptable alternate to having a powder finish?
Government Answer: we are requiring the bridges to have a powder finish.
Question 4: Is a bid bond required for this solicitation?
Government Answer: A bid bond is not required as this is a firm-fixed priced contract and is considered a services contract and not construction.