Attachment 1 - Statement of Work - Signage For Bldg 9225.pdf

PDF 153 KB Posted

Attached to
Signage for Building 9225 Federal contract opportunity
Solicitation number
FA301625Q0015
Issued by
Department of the Air Force Air Education and Training Command

About this file

This Statement of Work outlines requirements for fabricating and installing signage at Building 9225 at JBSA-Lackland for the Department of the Air Force Air Education and Training Command. The contractor must install two sets of bronze plastic lettering displaying "37th TRAINING GROUP," "37th TRAINING SUPPORT SQUADRON," and "341st TRAINING SQUADRON" in Helvetica font. Sign A requires 12-inch tall, 1-inch deep letters on the east wall near the main entrance, while Sign B requires 24-inch tall, 2-inch deep letters on the south wall, with specific dimensional and placement requirements detailed for each.

The work must be performed between 5:00 PM and 10:00 PM Monday through Friday, with weekend work possible with approval. The contractor is responsible for site surveys, measurements, removal of existing signage, debris removal, surface repairs, installation, and returning the facility to its original condition. The contractor must designate an on-site project manager as the point of contact. Questions are due by February 7, 2025, at 10:00 AM, and work coordination should be made through Mr. Timothy Donelson at 210-671-2164.

View the file

Other files for this federal contract opportunity

Other files attached to Signage for Building 9225, newest first.
File Type Posted
front of bldg 9225.jpg JPG image
F2MTRD4292A002 - All vendor questions and answers.docx DOCX document
bldg 9225.jpg JPG image
Solicitation - FA301625Q0015.pdf PDF
Attachment 2 - Salient Characteristics - Signage For Bldg. 9225.pdf PDF
Building Layout - Signage for Bldg. 9225.pptx PPTX presentation

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SPECIFICATIONS

FOR

Signage for Bldg. 9225

STATEMENT OF WORK

Signage for Bldg. 9225

JBSA-Lackland

502 CONS

JBKAE 12 Nov 2024

F2MTRD4292A002

Fabricate Signs

1. PROJECT SCOPE: The contractor shall provide all personnel, equipment, supplies, tools, materials, and all non-personnel services necessary for install signage for Bldg. 9225.

Offerors shall inspect the site where services are to be performed and to satisfy themselves regarding all general and local conditions that may affect the cost of contract performance, to the extent that the information is reasonably obtainable.

1.1 The contractor shall

1.1.1 Shall be responsible to take measurements to confirm all signage fits accordingly prior to purchase.

1.1.2 Shall remove and dispose of all excess material/debris (off-property) from packing/shipping at the end of each workday.

1.1.3 Shall remove old signage letters and dispose offsite.

1.1.4 Shall fill holes created from removing old signage with clear silicone

1.1.5 Shall ensure both Fabricate Sign A and B signage font is Helvetica.

1.1.6 Shall ensure both Fabricate Sign A and B signage consist of:

1.1.6.1 37th TRAINING GROUP

1.1.6.2 37th TRAINING SUPPORT SQUADRON

1.1.6.3 341st TRAINING SQUADRON

1.1.7 All lettering will be evenly spaced.

2. PROJECT DESCRIPTION:

The Contractor shall:

2.1 Conduct a site survey to assess the building location and layout. Identify any special equipment necessary for installation into a brick wall at Bldg. 9225 to complete the installation of signage.

2.2 Shall work duty hours Monday through Friday and weekends until all workstation and panels are install.

2.3 Shall ensure Fabricate Sign A consist of:

2.3.1 1-inch-deep plastic letters

2.3.2 12-inch-tall plastic letters

2.3.3 Bronze in color

2.3.4 Location of Signage

2.3.4.1 East wall of Bldg. 9225 left of the main entrance door

2.3.4.2 Signage starts approximately 2 feet below from top of wall

2.3.4.3 Signage will be centered on wall.

2.3.4.4 Signage width will be approximately 14 feet and 6 inches.

2.3.4.5 Signage height will be approximately 6 feet and 9 inches

502 CONS

JBKAE 12 Nov 2024

F2MTRD4292A002

2.4 Shall ensure Fabricate Sign A consist of:

2.4.1 Approximately 2-inch-deep plastic letters

2.4.2 Approximately 24-inch-tall plastic letters

2.4.3 Bronze in color

2.4.4 Location of Signage

2.4.4.1 Approximately 40 feet from the corner of the South wall of Bldg. 9225 between the first 2 rain downspouts.

2.4.4.2 Signage starts approximately 3 feet below from top of wall

2.4.4.3 Signage will be centered on wall.

2.4.4.4 Signage width will be approximately 29 feet.

2.4.4.5 Signage height will be approximately 13 feet and 6 inches.

2.5 The contractor shall contact Mr. Timothy Donelson at 210-671-2164 with any questions.

3 Delivery

The contractor shall be responsible for off-loading items from delivery vehicles and shall provide any additional equipment to accomplish the task.

3 . 1 The contractor shall also be responsible for properly protecting the service entrance and flooring of the building in which the items are to be received.

3.2 There is a loading dock/ramp available on the north side of the building.

4 Address

37 TRG

1220 Truemper Drive Building 9225 San Antonio, TX 78236

5 Site Maintenance

5.1 The contractor shall maintain work areas in a neat, clean, and safe condition.

5.2 The contractor shall be responsible for providing, installing, and the removal of any temporary signage, barriers, barricade tape, etc. which may be required to control pedestrian in the work area.

5.3 The contractor shall collect all trash, debris, refuse, garbage, etc. (related to contractor personnel and this requirement).

5.4 The aforementioned materials shall be removed from the site by appropriate means daily.

5.6 Storage of materials shall be coordinated with Mr. Timothy Donelson 210-671-3768.

502 CONS

JBKAE 12 Nov 2024

F2MTRD4292A002

5 . 7 The contractor shall be responsible for freight, unpacking, delivery, installation, and disposal.

6 Clean up

6 . 1 The Contractor shall also remove all packaging materials from JBSA Lackland TX and shall be responsible for any refuse containers needed for trash and packing materials.

6.2 The contractor shall be responsible for returning the facility to its original state prior to cleaning and repairing any damage caused by the contractor’s personnel or equipment.

7 Site Program Manager/Point of Contact (POC)

7.1 The Contractor shall designate an on-site project manager as the Site POC.

7.2 The Site POC shall be the interface for all work site communications with the

Government, including quality, safety, and discrepancy matters.

8 Hours of Operation and Special Conditions

8.1 Work hours shall begin at 5:00 p.m. through 10:00 p.m., Monday through Friday, exclusive of Federal holidays.

8.2 At the option of the Government and with approval of the Contracting Officer, work may be permitted on Federal holidays, weekends, or after 7:00 a.m. at no additional cost to the Government.

New Year's Day Martin Luther King Jr's Birthday President’s Day Memorial Day Juneteenth Independence Day Labor Day Columbus Day Veterans' Day Thanksgiving Day Christmas Day

9 ACCEPTANCE

Upon completion of the work, the contractor shall be subject to a final acceptance by the Customer POC and Contracting Officer and/or designee.

10 RECORDS MANAGEMENT

The Contractor shall manage all data created for Government use or legally controlled by the

502 CONS

JBKAE 12 Nov 2024

F2MTRD4292A002

Government, in support of the functional activity or required by AF publication, IAW with the AF Records Management procedures in Air Force Instruction (AFI) 33-322, Air Force Manual (AFMAN) 33-363 and Air Force Instruction (AFI) 33-364 (or their subsequent replacements)".

11 CONTRACT MANAGEMENT

No changes in or deviation from the scope of service shall be affected without a modification executed by the Contracting Officer authorizing such changes.

End of Statement of Work